Question

If the NPV of an independent project is higher than zero, this means that: Select one:...

If the NPV of an independent project is higher than zero, this means that:

Select one:

a. The project should be accepted.

b. Not accepting the project decreases the value of the firm.

c. The cash flows of the project provide a lower return than the required.

d. The project is not acceptable on a risk adjusted basis.

e. The firm’s stock price and consequently the wealth of its shareholders will decrease.

Homework Answers

Answer #1

a. The Project Should be accepted.

In net Present value, we have to discount the future cash inflows at a desired discount rate, then we get the future cash inflows in the present terms and subtract intial investment amount

NPV = PV of the future cassh flows - Intial Outlay.

If NPV is positive we can accept the Project. If NPV turns down negitive we can reject the project.

Since in the Question it is given that NPV is higher than 0, So the Project should be accepted.So Option a is the Correct answer.

b. Not accepting the project decreases the value of the firm.

Since the NPV is higher than 0, we can accept the Project. It increases the value of the firm. Hence the given option b is not correct.

c. The cash flows of the project provide a lower return than the required.

Since in the NPV we have discounted the values at the desired rate of return. If NPV is higher than 0, then we get the desired return. If NPV is lower than 0,then we are getting the lower return. Hence the givven option is wrong. So C is not the Correct answer.

d.The project is not acceptable on a risk adjusted basis.

If NPV is higher than 0, then we should accept the Project. The Project is giving more than desired return. Hence option d is not the correct answer.

e.The firm’s stock price and consequently the wealth of its shareholders will decrease.

If NPV is higher than 0, then the Project is giving the higher return more than we desired. So it increases the value to the firm. Consequently results in higher profits and indeed the Shareholders wealth increses. Hence option e is not the correct answer.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Which of the following statement is correct? Select one: a. All the answers are incorrect. b....
Which of the following statement is correct? Select one: a. All the answers are incorrect. b. A positive NPV means that the firm’s value will decrease if the project is adopted because the new project’s estimated return is lesst than the firm’s required rate of return. c. Reject the project if the IRR is greater than or equal to the required rate of return. d. Payback period is the discount rate that forces the NPV to equal zero. e. All...
The net present value (NPV) method estimates how much a potential project will contribute to ____...
The net present value (NPV) method estimates how much a potential project will contribute to ____ and it is the best selection criterion. The _____ the NPV, the more value the project adds; and added value means a ____ stock price. CFt is the expected cash flow at Time t, r is the project's risk-adjusted cost of capital, and N is its life, and cash outflows are treated as negative cash flows. The NPV calculation assumes that cash inflows can...
Capital Budgeting Decision Criteria: NPV NPV The net present value (NPV) method estimates how much a...
Capital Budgeting Decision Criteria: NPV NPV The net present value (NPV) method estimates how much a potential project will contribute to -Select-business ethicsshareholders' wealthemployee benefitsCorrect 1 of Item 1, and it is the best selection criterion. The -Select-smallerlargerCorrect 2 of Item 1 the NPV, the more value the project adds; and added value means a -Select-higherlowerCorrect 3 of Item 1 stock price. In equation form, the NPV is defined as: CFt is the expected cash flow in Period t, r...
When a capital budgeting project has an NPV of zero, what does this mean? The project’s...
When a capital budgeting project has an NPV of zero, what does this mean? The project’s IRR will be less than the required hurdle rate for the project The firm’s stockholders will earn a positive return, but it will be less than their required return, given the risk of the investment The firm’s stockholders will earn a negative return The firm’s security holders will earn their required rate of return, given the risk of the investment none of the above
Which of the following is statements related to capital budgeting is not true? A project is...
Which of the following is statements related to capital budgeting is not true? A project is considered acceptable if its NPV is greater zero. A project whose NPV is greater than its IRR is should be accepted. Both the NPV method and the IRR method of evaluating capital investment projects are widely considered to be superior to the payback method. An NPV of zero signifies that the project's cash flows are just sufficient to repay the invested capital and to...
1) If the NPV of a project with one sign reversal is positive, then its IRR:...
1) If the NPV of a project with one sign reversal is positive, then its IRR: Select one: a. must be greater than the required rate of return b. must be less than the required rate of return c. could be greater or less than the required rate of return d. cannot be determined without actual cash flows 2) Which of the following statements is INCORRECT? Select one: a. An acceptable project should have an NPV greater than or equal...
. Assuming zero Liquidity Risk Premium and Constant Inflation Risk Premium, the difference in yield between...
. Assuming zero Liquidity Risk Premium and Constant Inflation Risk Premium, the difference in yield between two Treasury securities results primarily from differences in Maturity Premium True or false 15. The NPV and IRR methods will always agree as to whether a project enhances or harms shareholder wealth. TF 16. The Profitability Index is an easier method than Net Present Value because it does not involve discounting future cash flows. TF 17. A manager should always choose the project with...
Net present value (NPV) Evaluating cash flows with the NPV method The net present value (NPV)...
Net present value (NPV) Evaluating cash flows with the NPV method The net present value (NPV) rule is considered one of the most common and preferred criteria that generally lead to good investment decisions. Consider this case: Suppose Hungry Whale Electronics is evaluating a proposed capital budgeting project (project Alpha) that will require an initial investment of $400,000. The project is expected to generate the following net cash flows: Year Cash Flow Year 1 $325,000 Year 2 $400,000 Year 3...
Net present value (NPV) Evaluating cash flows with the NPV method The net present value (NPV)...
Net present value (NPV) Evaluating cash flows with the NPV method The net present value (NPV) rule is considered one of the most common and preferred criteria that generally lead to good investment decisions. Consider this case: Suppose Happy Dog Soap Company is evaluating a proposed capital budgeting project (project Alpha) that will require an initial investment of $450,000. The project is expected to generate the following net cash flows: Year Cash Flow Year 1 $300,000 Year 2 $475,000 Year...
A project has an NPV of £12,632 when a discount rate of 12% is used and...
A project has an NPV of £12,632 when a discount rate of 12% is used and the same project has an NPV of (£6,935) when a discount rate of 24% is used. The approximate internal rate of return of the project is: Select one: a. 18.5% b. 15.16% c. 20.5% d. 19.75% An investment project costs $10,500 and will generate $4,000 in annual cash flows for five years. What is the exact internal rate of return (IRR)? Select one: a....