Question

The Management of Cullumber Manufacturing Company is evaluating two forklift systems to use in its plant...

The Management of Cullumber Manufacturing Company is evaluating two forklift systems to use in its plant that produces the towers for a windmill power farm. The costs and the cash flows from these systems are shown below. The company uses a 8 percent discount rate for all projects.

Year 0 Year 1 Year 2 Year 3
Otis Forklifts $-3,107,450 $962,225 $1,373,886 $2,093,497
Craigmore Forklifts $-4,139,410 $860,236 $1,775,225 $2,885,110
NPV
Otis forklift $623,270
Craigmore Forklifts $469,367


Compute the IRR for each of the two systems. (Round intermediate calculation to 0 decimal places, e.g. 1,525 and final answers to 2 decimal places, e.g. 15.10%.)

IRR
Otis forklift %
Craigmore Forklifts %


Is the investment decision different from the one determined by NPV?

The investment decision is

differentsame

from the one determined by NPV.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Cullumber Incorporated management is considering investing in two alternative production systems. The systems are mutually exclusive,...
Cullumber Incorporated management is considering investing in two alternative production systems. The systems are mutually exclusive, and the cost of the new equipment and the resulting cash flows are shown in the accompanying table. The firm uses a 9 percent discount rate for their production systems. Year System 1 System 2 0 -$15,100 -$42,300 1 15,100 30,800 2 15,100 30,800 3 15,100 30,800 What are the payback periods for production systems 1 and 2? (Round answers to 2 decimal places,...
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent....
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent. Costs and cash flows for each project are given in the following table. Year Project 1 Project 2 0 -$1,292,224 -$1,321,796 1 238,000 384,000 2 329,000 384,000 3 430,000 384,000 4 504,000 384,000 5 800,000 384,000 Calculate NPV and IRR of two projects. (Enter negative amounts using negative sign, e.g. -45.25. Do not round discount factors. Round other intermediate calculations and final answer to...
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent....
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent. Costs and cash flows for each project are given in the following table. Year Project 1 Project 2 0 -$1,304,168 -$1,325,262 1 264,000 379,000 2 365,000 379,000 3 445,000 379,000 4 539,000 379,000 5 739,000 379,000 Calculate NPV and IRR of two projects. (Enter negative amounts using negative sign, e.g. -45.25. Do not round discount factors. Round other intermediate calculations and final answer to...
Cullumber Crafts Corp. management is evaluating two independent capital projects that will each cost the company...
Cullumber Crafts Corp. management is evaluating two independent capital projects that will each cost the company $290,000. The two projects will provide the following cash flows: Year Project A Project B 1 $84,750 $66,000 2 103,450 99,000 3 24,235 137,250 4 129,655 98,110 Collapse question part (a1) What is the payback period of both projects? (Round answers to 2 decimal places, e.g. 15.25.)
Ivanhoe Incorporated management is considering investing in two alternative production systems. The systems are mutually exclusive,...
Ivanhoe Incorporated management is considering investing in two alternative production systems. The systems are mutually exclusive, and the cost of the new equipment and the resulting cash flows are shown in the accompanying table. The firm uses a 8 percent discount rate for production systems. Year System 1 System 2 0 -$12,490 -$44,703 1 12,536 30,270 2 12,536 30,270 3 12,536 30,270 Compute the IRR for both production system 1 and production system 2. (Do not round intermediate calculations. Round...
Emporia Mills management is evaluating two alternative heating systems. Costs and projected energy savings are given...
Emporia Mills management is evaluating two alternative heating systems. Costs and projected energy savings are given in the following table. The firm uses 12.27 percent to discount such project cash flows. Year System 100 System 200 0 $-2,053,200 $-1,741,800 1 314,410 701,900 2 520,830 460,300 3 529,940 614,300 4 656,200 314,000 What is the NPV of the systems? (Enter negative amounts using negative sign e.g. -45.25. Do not round discount factors. Round answers to 0 decimal places, e.g. 5,275.) NPV...
Cullumber Company is considering buying a new farm that it plans to operate for 10 years....
Cullumber Company is considering buying a new farm that it plans to operate for 10 years. The farm will require an initial investment of $12.05 million. This investment will consist of $2.20 million for land and $9.85 million for trucks and other equipment. The land, all trucks, and all other equipment are expected to be sold at the end of 10 years for a price of $5.15 million, which is $2.50 million above book value. The farm is expected to...
Cullumber Company is about to issue $336,000 of 9-year bonds paying an 11% interest rate, with...
Cullumber Company is about to issue $336,000 of 9-year bonds paying an 11% interest rate, with interest payable annually. The discount rate for such securities is 10%. Click here to view the factor table. (For calculation purposes, use 5 decimal places as displayed in the factor table provided.) How much can Cullumber expect to receive for the sale of these bonds? (Round answer to 0 decimal places, e.g. 2,575.) Cullumber can expect to receive $enter a dollar amount to be...
Blossom Corp. management is investigating two computer systems. The Alpha 8300 costs $3,324,225 and will generate...
Blossom Corp. management is investigating two computer systems. The Alpha 8300 costs $3,324,225 and will generate cost savings of $1,213,225 in each of the next five years. The Beta 2100 system costs $4,000,500 and will produce cost savings of $1,115,750 in the first three years and then $2 million for the next two years. The company’s discount rate for similar projects is 14 percent. What is the NPV of each system? (Enter negative amounts using negative sign, e.g. -45.25. Do...
Wildhorse Industries management is planning to replace some existing machinery in its plant. The cost of...
Wildhorse Industries management is planning to replace some existing machinery in its plant. The cost of the new equipment and the resulting cash flows are shown in the accompanying table. The firm uses an 18 percent discount rate for projects like this. Should management go ahead with the project? Year Cash Flow 0 -$3,485,400 1 871,710 2 896,700 3 1,104,400 4 1,340,360 5 1,450,600 What is the NPV of this project? (Enter negative amounts using negative sign e.g. -45.25. Do...