Question

Project L requires an initial outlay at t = 0 of $71,219, its expected cash inflows...

Project L requires an initial outlay at t = 0 of $71,219, its expected cash inflows are $11,000 per year for 11 years, and its WACC is 14%. What is the project's IRR? Round your answer to two decimal places.

  %

Homework Answers

Answer #1

Hi

we will use excel IRR formula to find our project's IRR

Below is excel formula and value for IRR:

Year Cash Flow
0 -71,219
1 11,000
2 11,000
3 11,000
4 11,000
5 11,000
6 11,000
7 11,000
8 11,000
9 11,000
10 11,000
11 11,000
IRR 10.07%

hence IRR is 10.07%

Thanks

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1.) Project L requires an initial outlay at t = 0 of $50,000, its expected cash...
1.) Project L requires an initial outlay at t = 0 of $50,000, its expected cash inflows are $15,000 per year for 9 years, and its WACC is 14%. What is the project's NPV? Do not round intermediate calculations. Round your answer to the nearest cent. $   2.) Project L requires an initial outlay at t = 0 of $57,430, its expected cash inflows are $10,000 per year for 10 years, and its WACC is 14%. What is the project's...
Project A requires an initial outlay at t = 0 of $56,841, its expected cash inflows...
Project A requires an initial outlay at t = 0 of $56,841, its expected cash inflows are $11,000 per year for 9 years, and its WACC is 13%. What is the project's IRR? Round your answer to two decimal places. Project P requires an initial outlay at t = 0 of $45,000, its expected cash inflows are $15,000 per year for 9 years, and its WACC is 12%. What is the project's MIRR? Do not round intermediate calculations. Round your...
Project L requires an initial outlay at t = 0 of $59,495, its expected cash inflows...
Project L requires an initial outlay at t = 0 of $59,495, its expected cash inflows are $9,000 per year for 11 years, and its WACC is 10%. What is the project's IRR? Round your answer to two decimal places.
Project L requires an initial outlay at t = 0 of $40,000, its expected cash inflows...
Project L requires an initial outlay at t = 0 of $40,000, its expected cash inflows are $11,000 per year for 9 years, and its WACC is 11%. What is the project's MIRR? Do not round intermediate calculations. Round your answer to two decimal places.
Project L requires an initial outlay at t = 0 of $50,000, its expected cash inflows...
Project L requires an initial outlay at t = 0 of $50,000, its expected cash inflows are $15,000 per year for 9 years, and its WACC is 13%. What is the project's NPV? Do not round intermediate calculations. Round your answer to the nearest cent. Project L requires an initial outlay at t = 0 of $55,000, its expected cash inflows are $8,000 per year for 9 years, and its WACC is 14%. What is the project's MIRR? Do not...
Project L requires an initial outlay at t = 0 of $48,000, its expected cash inflows...
Project L requires an initial outlay at t = 0 of $48,000, its expected cash inflows are $11,000 per year for 12 years, and its WACC is 10%. What is the project's payback? Round your answer to two decimal places. years
Project L requires an initial outlay at t = 0 of $53,000, itsexpected cash inflows...
Project L requires an initial outlay at t = 0 of $53,000, its expected cash inflows are $11,000 per year for 11 years, and its WACC is 12%. What is the project's payback? Round your answer to two decimal places.
Project L requires an initial outlay at t = 0 of $70,000, its expected cash inflows...
Project L requires an initial outlay at t = 0 of $70,000, its expected cash inflows are $13,000 per year for 6 years, and its WACC is 14%. What is the project's payback? Round your answer to two decimal places.   years
Project L requires an initial outlay at t = 0 of $50,000, its expected cash inflows...
Project L requires an initial outlay at t = 0 of $50,000, its expected cash inflows are $15,000 per year for 7 years, and its WACC is 11%. What is the project's payback? Round your answer to two decimal places.
Project L requires an initial outlay at t = 0 of $35,000, its expected cash inflows...
Project L requires an initial outlay at t = 0 of $35,000, its expected cash inflows are $11,000 per year for 9 years, and its WACC is 9%. What is the project's MIRR? Do not round intermediate calculations. Round your answer to two decimal points.