Question

compute the NPV for project M if the appropriate cost of capital is 7%. Time: 0...

compute the NPV for project M if the appropriate cost of capital is 7%.

Time: 0 1    2 3    4    5

Cashflow:    -$3,400 $730    $860 $900    $980    $480

Should the project be accepted or rejected?

Homework Answers

Answer #1
Year Cash flow PVIF@7% Present value
0 $     (3,400) 1.00000 -$3,400.00
1 $          730 0.93458 $682.24
2 $          860 0.87344 $751.16
3 $          900 0.81630 $734.67
4 $          980 0.76290 $747.64
5 $          480 0.71299 $342.23
Net present value -$142.06

Reject the project

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project M Time: 0 1 2 3 4 5 Cash flow –$2,200 $590 $720 $760 $840 $340 NPV $ Should the project be accepted or rejected?
Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project M Time: 0 1 2 3 4 5 Cash flow: –$3,100 $710 $840 $880 $960 $460 Should the project be rejected or accepted?
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$2,400 $1,040 $900 $940 $580 $380 Should the project be accepted or rejected? accepted rejected
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.)      Project C   Time: 0 1 2 3 4 5   Cash flow –$2,400 $1,040 $900 $940 $580 $380      Discounted payback period years    Should the project be accepted or rejected? Accepted Rejected
Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent....
Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: 0 1 2 3 4 5 Cash flow: –$1,600 $590 $2,080 –$640 $540 –$220 NPV= Should the project be accepted or rejected?
Compute the MIRR statistic for Project J if the appropriate cost of capital is 8 percent....
Compute the MIRR statistic for Project J if the appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project J Time: 0 1 2 3 4 5 Cash flow: −$2,700 $860 $2,330 −$690 $810 −$270 Should the project be accepted or rejected? accepted rejected
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent....
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal place.) Project Y Time: 0 1 2 3 4 Cash flow: –$9,300 $3,610 $4,440 $1,780 $560 NPV $ _________ Should the project be accepted or rejected? _____________
Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project M Time: 0 1 2 3 4 5 Cash flow: –$1,200 $390 $520 $560 $640 $140 Problem 13-3 NPV with Non-normal Cash Flows (LG13-3) Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent. (Negative...
Compute the payback statistic for Project A if the appropriate cost of capital is 9 percent...
Compute the payback statistic for Project A if the appropriate cost of capital is 9 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.) Project A Time: 0 1 2 3 4 5 Cash flow: −$3,000 $1,150 $1,080 $920 $700 $500 Should the project be accepted or rejected? accepted rejected
Compute the MIRR statistic for Project J if the appropriate cost of capital is 9 percent....
Compute the MIRR statistic for Project J if the appropriate cost of capital is 9 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project J Time: 0 1 2 3 4 5 Cash flow –$2,000 $650 $1,980 –$620 $600 –$200 MIRR % Should the project be accepted or rejected? Accepted Rejected
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT