Question

Compute the Discounted Payback statistic for Project X and recommend whether the firm should accept or...

Compute the Discounted Payback statistic for Project X and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent and the maximum allowable discounted payback is 3 years. Time: 0 1 2 3 4 5 Cash flow: -1,000 500 480 400 300 150

2.98 years,accept

4.98 years, reject

3.49 years, reject

2.49 years, accept

Homework Answers

Answer #1
Year Cash flows Present value@10% Cumulative Cash flows
0 (1000) (1000) (1000)
1 500 454.55 (545.45)
2 480 396.69 (148.76)
3 400 300.53 151.77
4 300 204.90 356.67
5 150 93.14 449.81(Approx)

Hence discounted Payback period=Last period with a negative cumulative cash flow+(Absolute value of cumulative cash flows at that period/Cash flow after that period).

=2+(148.76/300.53)

=2.49 years(Approx).

Hence discounted payback is less than 3 years;project must be accepted.(Option D).

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Compute the Discounted Payback statistic for Project X and recommend whether the firm should accept or...
Compute the Discounted Payback statistic for Project X and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent and the maximum allowable discounted payback is 3 years.   Time: 0 1 2 3 4 5   Cash flow: -1,000 400 580 500 400 250 3.42 years, reject 4.72 years, reject 2.42 years, accept 2.72 years, accept
Compute the Payback statistic for Project X and recommend whether the firm should accept or reject...
Compute the Payback statistic for Project X and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 12 percent and the maximum allowable payback is 4 years. Time: 0 1 2 3 4 5 Cash flow: -3,100 950 700 850 725 625 Multiple Choice 3.83 years, Reject 2.83 years, Accept 2.83 years, Reject 3.83 years, Accept
Compute the Payback statistic for Project X and recommend whether the firm should accept or reject...
Compute the Payback statistic for Project X and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 12 percent and the maximum allowable payback is 4 years.   Time: 0 1 2 3 4 5   Cash flow: -2,100 350 700 800 750 525
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$1,000 $480 $480 $520 $300 $100
COMPUTE THE DISCOUNTED PAYBACK STATISTIC FOR PROJECT C. IF THE APPROPRIATE COST OF CAPITAL IS 6...
COMPUTE THE DISCOUNTED PAYBACK STATISTIC FOR PROJECT C. IF THE APPROPRIATE COST OF CAPITAL IS 6 PERCENT AND THE MAXIMUN ALLOWABLE DISCOUNTED PAYBACK PERIOD IS 3 YEARS. TIME:    0 1 2 3    4    5 CASH FLOW:    $-3,000    $1,280 $1,080    $1,120 $700 $500 ACCEPT OR REJECT THE PROJECT?
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7 percent and the maximum allowable discounted payback period is three years. Having a hard time coming up with the solution to this problem. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: Cash flow: –    0          1          2       3         4      5                      $2,000   $880 $780   $820 $500 $300 Should I accepted or rejected the problem? Discounted...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$1,900 $840 $750 $790 $480 $280
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$2,300 $1,000 $870 $910 $560 $360 Discounted payback period    years
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 10 percent, and the maximum allowable payback and discounted payback statistic for the projects are 2.5 and 3.5 years, respectively.   Time: 0 1 2 3   Project A Cash Flow -1,000 300 400 700   Project B Cash Flow -500 200 400 300 Use the payback decision rule to evaluate these projects;...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$2,600 $1,120 $960 $1,000 $620 $420
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT