Question

If a prospective project has a risk level greater than the average risk project in the...

If a prospective project has a risk level greater than the average risk project in the company, should the company evaluate the prospective project with the company's current cost of capital? Explain.

Homework Answers

Answer #1

If a prospective project has a risk level which is higher than the normal projects then a company should be using the risk weighted cost of capital than the normal cost of capital of the company.

The risk weighted cost of capital accounts for different level of risk associated with the project and then discount the product with the same risk weight and that will help the project to be evaluated fairly in order to be accepted or rejected.

risk weighted average cost of capital helps in determination of various kind of risk assignment to the cost of capital, which is specific in nature and then discounting the projects with those risk assigned weights will help in better analysis of whether to accept the project or reject the project.

So a company should not use the current cost of capital to evaluate a prospective project because it can lead to unfair evaluation.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A firm is considering the purchase of an asset whose risk is lower than the current...
A firm is considering the purchase of an asset whose risk is lower than the current risk of the firm, based on any method for assessing risk. In evaluating this asset, the decision maker should Question 7 options: Increase the IRR of the asset to reflect the greater risk. Lower the cost of capital used to evaluate the project to reflect the lower risk of the project. Reject the asset, since its acceptance would increase the risk of the firm....
Puckett Inc. risk-adjusts its WACC to account for project risk. It uses a risk-adjusted project cost...
Puckett Inc. risk-adjusts its WACC to account for project risk. It uses a risk-adjusted project cost of capital of 8% for below-average risk projects, 10% for average-risk projects, and 12% for above-average risk projects. Which of the following independent projects should Puckett accept, assuming that the company uses the NPV method when choosing projects? a. Project C, which has above-average risk and an IRR = 11%. b. Without information about the projects' NPVs we cannot determine which project(s) should be...
a. Gentle corporation has two divisions of equal size. Division A has a beta of 0.93,...
a. Gentle corporation has two divisions of equal size. Division A has a beta of 0.93, division B has a beta of 1.57. The company has no debt. The cost of capital for the entire corporation is 16%. Which of the two divisions have a lower cost of capital? Explain. b. Barrack mining uses a cost of capital of 11 % to evaluate an average risk project. It adds or subtracts 3% from its WACC to adjust for risk. Currently...
A company has two separate projects A and B. Project A has less risk than Project...
A company has two separate projects A and B. Project A has less risk than Project B and company requires WACC plus 0.5 percent return for Project A. Project B has more risk and the firm asks its WACC plus 1 percent return. The company has a debt-equity ratio of .45. The company’s cost of equity is 14.7 percent and the after-tax cost of debt is 5.1 percent. If you expect 11.64 percent rate of return from project A and...
The Rodriguez Company is considering an average-risk investment in a mineral water spring project that has...
The Rodriguez Company is considering an average-risk investment in a mineral water spring project that has a cost of $160,000. The project will produce 750 cases of mineral water per year indefinitely. The current sales price is $145 per case, and the current cost per case is $110. The firm is taxed at a rate of 36%. Both prices and costs are expected to rise at a rate of 6% per year. The firm uses only equity, and it has...
A project has a level of systematic risk of 1.25. The expected return on the market...
A project has a level of systematic risk of 1.25. The expected return on the market portfolio is 12%, and the risk free rate is 5%. If an investment’s internal rate of return is 12% a. The project should be accepted b. The project should be rejected because IRR is less than the required rate of return c. The project should be rejected because it is over-priced. d. Both b and c are correct e. Not enough information to tell
Please show me how to calculation with these question. A company estimates that an average-risk project...
Please show me how to calculation with these question. A company estimates that an average-risk project has a WACC of 12%, a below-average risk project has a WACC of 10%, and an above-average risk project has a WACC of 14%. Which of the following independent projects should the company accept? Project Y has below-average risk and an internal rate of return of 9%.   Project X has average risk and an internal rate of return of 11%.   Project Z has above-average...
1.) The cost of raising capital through retained earnings is __________ (greater than, less than) the...
1.) The cost of raising capital through retained earnings is __________ (greater than, less than) the cost of raising capital through issuing new common stock. 2.) The current risk-free rate of return is 3.80% and the current market risk premium is 6.10%. Blue Hamster Manufacturing Inc. has a beta of 1.56. Using the Capital Asset Pricing Model (CAPM) approach, Blue Hamster’s cost of equity is __________ (13.99%, 17,32%, 14.65%, 13.32%) 3.) Fuzzy Button Clothing Company is closely held and, as...
Piedmont Hotels is an all-equity company. Its stock has a beta of 1.17. The market risk...
Piedmont Hotels is an all-equity company. Its stock has a beta of 1.17. The market risk premium is 6.6 percent and the risk-free rate is 2.4 percent. The company is considering a project that it considers riskier than its current operations so it wants to apply an adjustment of 1.6 percent to the project's discount rate. What should the firm set as the required rate of return for the project? Multiple Choice 8.52% 8.91% 10.12% 7.31% 11.72% Bermuda Cruises issues...
In perfect capital markets, using a company's cost of capital to evaluate a project is (a)...
In perfect capital markets, using a company's cost of capital to evaluate a project is (a) always correct. (b) always incorrect. (c) correct for projects that have average risk compared to the firm's other assets. (d) always correct and correct for projects that have average risk compared to the firm's other assets.