Question

The internal rate of return : (mark all that applies) is the more sound decision rule...

The internal rate of return : (mark all that applies)

is the more sound decision rule when dealing with mutually exclusive projects

is the rate that causes the net present value of a project to exactly equal zero.

does not need a required rate to calculate.

can effectively be used to analyze all investment scenarios.

rule states that a typical investment project with an IRR that is less than the required rate of return should be accepted.

Homework Answers

Answer #1

IRR should not be used in isolation to make any decision. IRR is the interest rate that makes the NPV = 0. There are a few drawbacks of the IRR approach which makes it a little less preferable. IRR should be greater than the required rate of return if you want to select the project. Hence, the correct options are-

Is the rate that causes the net present value of a project to exqctly equal zero.

Does not need a required rate to calculate.

Do leave an upvote if you find this helpful. In case of any doubt please let me know in the comment section.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The two fatal flaws of the internal rate of return rule are     A. arbitrary determination of...
The two fatal flaws of the internal rate of return rule are     A. arbitrary determination of a discount rate and failure to consider initial expenditures.     B. arbitrary determination of a discount rate and failure to correctly analyze mutually        exclusive investment projects.     C. arbitrary determination of a discount rate and the multiple rate of return problem.     D. failure to consider initial expenditures and failure to correctly analyze mutually       exclusive investment projects.
Which one of the following is TRUE? The NPV decision rule says to accept an investment...
Which one of the following is TRUE? The NPV decision rule says to accept an investment if the NPV is negative. The IRR decision rule states that a project should be accepted if its IRR exceeds the required return. The discount rate that causes the net present value of a project to equal zero is called the market rate. IRR is superior to NPV for choosing between different projects. Payback ignores the project's cost.
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Project A Project B Project C Project D Project E Project F Project G NPV= $4,711 ($711) ($657) $334 $9,842 $7,360 ($3,224) IRR= 44.51% 5.47% 8.06% 12.98% 22.56% 17.19% 5.47% MIRR= 25.23% 7.50% 8.97% 11.57% 16.26% 13.70% 7.50% PI= 2.178 0.822 0.945 1.028 1.394 1.294 0.871 The discounting rate (r)...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Criteria:                Project_A         Project_B             Project_C         Project_D          Project_E               Project_F             Project_G NPV= $137,083 $31,290 $6,016 $7,647 ($584) $12,521 $9,214 IRR= 31.80% 48.34% 12.03% 11.30% 9.94% 26.79% 37.87% MIRR= 18.52% 23.52% 10.62% 10.59% 9.97% 23.53% 20.76% PI= 1.69 2.25 1.040 1.038 1.00 2.25 1.92 The discounting rate...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Criteria:                Project_A         Project_B             Project_C         Project_D          Project_E               Project_F             Project_G NPV= $137,083 $31,290 $6,016 $7,647 ($584) $12,521 $9,214 IRR= 31.80% 48.34% 12.03% 11.30% 9.94% 26.79% 37.87% MIRR= 18.52% 23.52% 10.62% 10.59% 9.97% 23.53% 20.76% PI= 1.69 2.25 1.040 1.038 0.999 2.25 1.92 The discounting rate...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Criteria:                Project_A         Project_B             Project_C         Project_D          Project_E               Project_F             Project_G NPV= $137,083 $31,290 $6,016 $7,647 ($584) $12,521 $9,214 IRR= 31.80% 48.34% 12.03% 11.30% 9.94% 26.79% 37.87% MIRR= 18.52% 23.52% 10.62% 10.59% 9.97% 23.53% 20.76% PI= 1.69 2.25 1.040 1.038 0.999 2.25 1.92 The discounting rate...
4. Internal rate of return (IRR) The internal rate of return (IRR) refers to the compound...
4. Internal rate of return (IRR) The internal rate of return (IRR) refers to the compound annual rate of return that a project generates based on its up-front cost and subsequent cash flows. Consider the case of Blue Llama Mining Company: Blue Llama Mining Company is evaluating a proposed capital budgeting project (project Sigma) that will require an initial investment of $800,000. The company has been basing capital budgeting decisions on a project’s NPV; however, its new CFO wants to...
Modified internal rate of return: handles both the multiple IRR problem and the mutually exclusive projects...
Modified internal rate of return: handles both the multiple IRR problem and the mutually exclusive projects problem. handles the mutually exclusive projects problem. does not requires the use of a discount rate. does not handle the reinvestment rate assumption problem. handles the multiple IRR problem .
Explain the Concept Of Internal Rate Of Return (IRR) and explain the methodology’s flaws with mutually...
Explain the Concept Of Internal Rate Of Return (IRR) and explain the methodology’s flaws with mutually exclusive projects and nonconventional cash flows.
All techniques—Decision among mutually exclusive investments??? Pound Industries is attempting to select the best of three...
All techniques—Decision among mutually exclusive investments??? Pound Industries is attempting to select the best of three mutually exclusive projects. The initial investment and?after-tax cash inflows associated with these projects are shown in the following table. Cash flows Project A Project B Project C Initial investment? (CF)    ?$40,000 ?$80,000 ?$90,000 Cash inflows? (CF), tequals=1 to 5 ?$15,000 ?$26,500 ?$27,500 a. Calculate the payback period for each project. b. Calculate the net present value? (NPV) of each? project, assuming that the...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT