Question

Using Excel (if applicable), CocaCola is considering Projects X and Y, whose cash flows are shown...

Using Excel (if applicable),

CocaCola is considering Projects X and Y, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. What is the crossover rate and what does it tell management?

WACC:

9%

0

1

2

3

4

CFS

-$1,000

$950

$750

$550

$350

CFL

-$1,000

$500

$600

$700

$1000

Homework Answers

Answer #1

Crossover rate:

Crossover rate is the cost of capital,where two projects have the same NPV.

It means at this rate NPV(project 1) = NPV(project 2) or NPV(project 1) - NPV(project 2) = 0

0 1 2 3 4
CFS (A) ($ 1,000) $ 950 $ 750 $ 550 $ 350
CFL (B) ($ 1,000) $ 500 $ 600 $ 700 $ 1,000
(A) - (B) 0 $ 450 $ 150 ($ 150) ($ 650)

Now the NPV of difference amount sholud be 0.

Will use trial and error and find out the rate at which the NPV of difference amount will be = 0.

Let Rate = 10%, NPV = $-23.6

Let Rate = 12%, NPV = $1.12

By using interpolation we get the accurate crossover rate.

Lr + (Dl/Dl + Dh)*(Hr - Lr)

=10% + (23.6/23.6 + 1.12)*(12% -10%)

Crossover rate = 11.91 %

Crossover rate tells the management of investing company about the cost of capital at which both the mutually exclusive projects are equally good.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Farmer Co. is considering Projects S and L, whose cash flows are shown below. These projects...
Farmer Co. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and repeatable. Year                           0                1                2                3                4 CFS                          -$900         $800          $600                  CFL                          -$700         $300          $200          $400          $200 WACC: 10% Given the two projects are of different length and both are repeatable, one suggestion is to use the replacement chain approach in evaluation. If this approach is used, which project will you choose? Show the calculations...
Farmer Co. is considering Projects S and L, whose cash flows are shown below. These projects...
Farmer Co. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and repeatable. Year                           0                1                2                3                4 CFS                          -$900         $800          $600                  CFL                          -$700         $300          $200          $400          $200 WACC: 10% Given the two projects are of different length and both are repeatable, one suggestion is to use the replacement chain approach in evaluation. If this approach is used, which project will you choose? Show the calculations...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method, and you were hired to advise the firm on the best procedure. If the CEO's preferred criterion is used, how much value will the firm lose as a result of this decision? WACC: 13.00% 0 1 2 3 4 CFS -$1,025...
Moerdyk & Co. is considering Projects S and L, whose cash flows are shown below. These...
Moerdyk & Co. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under certain conditions choosing projects on the basis of the IRR will not cause any value to be lost because the one with the higher IRR will also have the higher NPV, i.e., no...
ASaark Telecom is considering Projects S and L, whose cash flows are shown below. These projects...
ASaark Telecom is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under certain conditions choosing projects on the basis of the IRR will not cause any value to be lost because the one with the higher IRR will also have the higher NPV, so no value...
a firm is considering projects S and L whose cash flows are shown below. these projects...
a firm is considering projects S and L whose cash flows are shown below. these projects are mutually exclusive, equally risky, and not repeatable. the ceo wants to use the IRR criterion, while the cfo favors the npv method. you were hired to advise the firm on the best procedure. if the wrong decision criterion is used, how much potential value would the firm lose? wacc: 7.75% 0. 1. 2. 3. 4. cfs -1,025. 380. 380. 380. 380 cfl -2,150....
ast Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
ast Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher MIRR rather than the one with the higher NPV, how much value will be forgone? Note that under some conditions choosing projects on the basis of the MIRR will cause $0.00 value to be lost. WACC: 8.75% Year 0 1 2 3 4 CFS...
Kosovski Company is considering Projects S and L, whose cash flows are shown below. These projects...
Kosovski Company is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and are not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under some conditions choosing projects on the basis of the IRR will cause $0.00 value to be lost. WACC: 6.25% 0 1 2 3 4 CFS -$1,050 $675 $650 CFL -$1,050 $360 $360 $360...
Tesar Chemicals is considering Projects S and L, whose cash flows are shown below. These projects...
Tesar Chemicals is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO believes the IRR is the best selection criterion, while the CFO advocates the NPV. If the decision is made by choosing the project with the higher IRR rather than the one with the higher NPV, how much, if any, value will be forgone, i.e., what's the chosen NPV versus the maximum possible NPV? Note...
Tesar Chemicals is considering Projects S and L, whose cash flows are shown below. These projects...
Tesar Chemicals is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO believes the IRR is the best selection criterion, while the CFO advocates the NPV. If the decision is made by choosing the project with the higher IRR rather than the one with the higher NPV, how much, if any, value will be forgone, i.e., what's the chosen NPV versus the maximum possible NPV? Note...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT