Question

You've estimated the following cash flows (in $) for two projects: Year Project A Project B...

You've estimated the following cash flows (in $) for two projects:

Year Project A Project B
0 -5,400 -8,100
1 1,325 1,325
2 2,148 2,148
3 3,942 7,751

The required return for both projects is 8%.

A:What is the NPV for project A?

B:What is the NPV for project B?

C:Which project seems better according to the NPV method?

Homework Answers

Answer #1

The NPV is computed as shown below:

= Initial investment + Present value of future cash flows

Present value is computed as follows:

= Future value / (1 + r)n

A. The NPV of Project A is computed as follows:

= - $ 5,400 + $ 1,325 / 1.08 + $ 2,148 / 1.082 + $ 3,942 / 1.083

= $ 797.70 Approximately

B. The NPV of Project B is computed as follows:

= - $ 8,100 + $ 1,325 / 1.08 + $ 2,148 / 1.082 + $ 7,751 / 1.083

= $ 1,121.41 Approximately

C. The Project B is better since the NPV of Project B is greater than the NPV of Project A.

Feel free to ask in case of any query relating to this question

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
You've estimated the following cash flows (in $) for two projects: Year Project A Project B...
You've estimated the following cash flows (in $) for two projects: Year Project A Project B 0 -5,100 -7,650 1 1,325 1,325 2 2,148 2,148 3 3,444 6,967 The required return for both projects is 8%. What is the NPV for project A? What is the NPV for project B? Which project seems better according to the NPV method? Project A or Project B
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A Project B 0 -5,600 -8,400 1 1,325 1,325 2 2,148 2,148 3 4,193 8,192 The required return for both projects is 8%. Part 1 : What is the IRR for project A? 3+ Decimals Part 2 What is the IRR for project B? 3+ Decimals Part 3 Which project seems better according to the IRR method? Project A or Project B Part 4 What...
Intro You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project...
Intro You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A Project B 0 -5,500 -8,250 1 1,325 1,325 2 2,148 2,148 3 4,010 7,918 The required return for both projects is 8%.    Attempt 1/10 for 10 pts. Part 1 What is the IRR for project A? Submit    Attempt 1/10 for 10 pts. Part 2 What is the IRR for project B? Submit    Attempt 1/5 for 10 pts. Part 3 Which project seems better...
You've estimated the following cash flows (in $) for a project: A B 1 Year Cash...
You've estimated the following cash flows (in $) for a project: A B 1 Year Cash flow 2 0 -5,400 3 1 1,325 4 2 2,148 5 3 2,258    Attempt 3/10 for 6 pts. Part 1 What is the IRR for the project?
You've estimated the following cash flows (in $) for a project: A B 1 Year Cash...
You've estimated the following cash flows (in $) for a project: A B 1 Year Cash flow 2 0 -3,430 3 1 974 4 2 1,281 5 3 1,996 The required return is 8.5%. 1. What is the IRR for the project? 2. What is the NPV of the project? 3 .What should you do? Check all that apply: Reject the project based on its NPV Reject the project based on its IRR Accept the project based on its IRR...
You've estimated the following cash flows (in $) for a project: The required return is 8.5%....
You've estimated the following cash flows (in $) for a project: The required return is 8.5%. What is the IRR for the project? What is the NPV of the project? A B 1 Year Cash flow 2 0 -3,320 3 1 974 4 2 1,281 5 3 1,875
Intro You've estimated the following cash flows (in $) for a project: A B 1 Year...
Intro You've estimated the following cash flows (in $) for a project: A B 1 Year Cash flow 2 0 -3,200 3 1 974 4 2 1,281 5 3 1,647 The required return is 8.5%. Attempt 1/1 for 10 pts. Part 1 What is the IRR for the project? Submit Attempt 1/1 for 10 pts. Part 2 What is the NPV of the project? Submit Attempt 1/1 for 10 pts. Part 3 What should you do? Check all that apply:...
The following are the cash flows of two projects: Year Project A Project B 0 $...
The following are the cash flows of two projects: Year Project A Project B 0 $ (390 ) $ (390 ) 1 220 290 2 220 290 3 220 290 4 220 a. Calculate the NPV for both projects if the opportunity cost of capital is 17%. Project A: Project B:
The following are the cash flows of two projects: Year Project A Project B 0 $...
The following are the cash flows of two projects: Year Project A Project B 0 $ (210 ) $ (210 ) 1 90 110 2 90 110 3 90 110 4 90 a. Calculate the NPV for both projects if the opportunity cost of capital is 17%. (Do not round intermediate calculations. Round your answers to 2 decimal places.)
The following are the cash flows of two projects: Year Project A Project B 0 $...
The following are the cash flows of two projects: Year Project A Project B 0 $ (350 ) $ (350 ) 1 180 250 2 180 250 3 180 250 4 180 a. Calculate the NPV for both projects if the opportunity cost of capital is 16%. (Do not round intermediate calculations. Round your answers to 2 decimal places.)