Question

Compute the payback statistic for Project A if the appropriate cost of capital is 9 percent...

Compute the payback statistic for Project A if the appropriate cost of capital is 9 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.)

Project A
Time: 0 1 2 3 4 5
Cash flow: −$3,000 $1,150 $1,080 $920 $700 $500



Should the project be accepted or rejected?

  • accepted

  • rejected

Homework Answers

Answer #1

Statement showing cummulative cash flow

Year Cash flow Cummulative cash flow
1 1150 1150
2 1080 2230
3 920 3150
4 700 3850
5 500 4350

Now using interpolation we can find payback period

Year Cummulative cash flow
2 2230
3 3150
1 920
? 770

= 770/920

=0.84

Thus payback perid = 2 + 0.84 = 2.84 years

Yeas project should be selected as payback period of the project is less than  maximum allowable payback period is four years

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
COMPUTE THE DISCOUNTED PAYBACK STATISTIC FOR PROJECT C. IF THE APPROPRIATE COST OF CAPITAL IS 6...
COMPUTE THE DISCOUNTED PAYBACK STATISTIC FOR PROJECT C. IF THE APPROPRIATE COST OF CAPITAL IS 6 PERCENT AND THE MAXIMUN ALLOWABLE DISCOUNTED PAYBACK PERIOD IS 3 YEARS. TIME:    0 1 2 3    4    5 CASH FLOW:    $-3,000    $1,280 $1,080    $1,120 $700 $500 ACCEPT OR REJECT THE PROJECT?
Compute the payback statistic for Project B if the appropriate cost of capital is 12 percent...
Compute the payback statistic for Project B if the appropriate cost of capital is 12 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "0" (zero).) Project B Time: 0 1 2 3 4 5 Cash flow: –$12,500 $3,500 $4,480 $1,820 $0 $1,300 Should the project be accepted or rejected?
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.)      Project C   Time: 0 1 2 3 4 5   Cash flow –$2,400 $1,040 $900 $940 $580 $380      Discounted payback period years    Should the project be accepted or rejected? Accepted Rejected
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$1,300 $600 $570 $610 $360 $160 Should the project be accepted or rejected? accepted rejected
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 13...
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 13 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "0" (zero).) Project D Time: 0 1 2 3 4 5 Cash flow: −$11,800 $3,430 $4,340 $1,680 $0 $1,160 Should the project be accepted or rejected? accepted rejected
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7 percent and the maximum allowable discounted payback period is three years. Having a hard time coming up with the solution to this problem. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: Cash flow: –    0          1          2       3         4      5                      $2,000   $880 $780   $820 $500 $300 Should I accepted or rejected the problem? Discounted...
Compute the payback statistic for Project B if the appropriate cost of capital is 11 percent...
Compute the payback statistic for Project B if the appropriate cost of capital is 11 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "0" (zero).) Project B Time: 0 1 2 3 4 5 Cash flow: –$11,700 $3,420 $4,320 $1,660 $0 $1,140
Compute the payback statistic for Project B if the appropriate cost of capital is 12 percent...
Compute the payback statistic for Project B if the appropriate cost of capital is 12 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "0" (zero).) Project C Time 0 1 2 3 4 5 Cash Flow -11,000.00 3350.00 4180.00 1520.00 0.00 1000.00
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$2,300 $1,000 $870 $910 $560 $360 Discounted payback period    years
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$1,000 $480 $480 $520 $300 $100
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT