Question

A firm must choose between two mutually exclusive projects, A & B. Project A has an...

A firm must choose between two mutually exclusive projects, A & B. Project A has an initial cost of $10000. Its projected net cash flows are $800, $2000, $3000, $4000, and $5000 at the end of years 1 through 5, respectively. Project B has an initial cost of $14000, and its projected net cash flows are $7000, $5000, $3000, $2000, and $1000 at the end of years 1 through 5, respectively. The firm’s cost of capital is 6.00%. Choose the correct statement:

Project B should be chosen because it has the higher IRR

Project B should be chosen because it has the higher NPV

Project A should be chosen because it has the higher IRR

Project A should be chosen because it has the higher NPV

Both projects should be chosen because both have a positive NPV

Homework Answers

Answer #1

NPV = Present Value of cash Inflows - Present Value of cash Outflows

NPV of Project A = [800*1/(1.06)^1+2000*1/(1.06)^2+3000*1/(1.06)^3+4000*1/(1.06)^4+5000*1/(1.06)^5]-10000

= $ 1,958.23

NPV of Project B = [7000*1/(1.06)^1+5000*1/(1.06)^2+3000*1/(1.06)^3+2000*1/(1.06)^4+1000*1/(1.06)^5]-14000

= $ 1,904.06

When a decision has to be made between two mutually exclusive projects, only one project can be chosen and the the project with the higher NPV is chosen.

Hence, Project A would be chosen

Answer = Project A should be chosen because it has the higher NPV

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A firm must choose between two mutually exclusive projects, A & B. Project A has an...
A firm must choose between two mutually exclusive projects, A & B. Project A has an initial cost of $11000. Its projected net cash flows are $900, $2000, $3000, $4000, and $5000 at the end of years 1 through 5, respectively. Project B has an initial cost of $15000, and its projected net cash flows are $7000, $5000, $3000, $2000, and $1000 at the end of years 1 through 5, respectively. If the firm’s cost of capital is 6.00%: Project...
A firm must choose between two mutually exclusive projects, A & B. Project A has an...
A firm must choose between two mutually exclusive projects, A & B. Project A has an initial cost of $11000. Its projected net cash flows are $900, $2000, $3000, $4000, and $5000 at the end of years 1 through 5, respectively. Project B has an initial cost of $15000, and its projected net cash flows are $7000, $5000, $3000, $2000, and $1000 at the end of years 1 through 5, respectively. If the firm’s cost of capital is 6.00%: A....
A firm must choose between two mutually exclusive projects, A & B. Project A has an...
A firm must choose between two mutually exclusive projects, A & B. Project A has an initial cost of $11000. Its projected net cash flows are $900, $2000, $3000, $4000, and $5000 at the end of years 1 through 5, respectively. Project B has an initial cost of $15000, and its projected net cash flows are $7000, $5000, $3000, $2000, and $1000 at the end of years 1 through 5, respectively. If the firm’s cost of capital is 6.00%: The...
a firm must choose between two mutually exclusive projects, a & b. project a has an...
a firm must choose between two mutually exclusive projects, a & b. project a has an initial cost of $10000. its projected net cash flows are $800, $2000, $3000, $4000, and $5000 at the end of years 1 through 5, respectively. project b has an initial cost of $14000, and its projected net cash flows are $7000, $5000, $3000, $2000, and $1000 at the end of years 1 through 5, respectively. at what cost of capital would the firm be...
A firm must choose between two mutually exclusive projects, A & B. Project A has an...
A firm must choose between two mutually exclusive projects, A & B. Project A has an initial cost of $11000. Its projected net cash flows are $900, $2000, $3000, $4000, and $5000 at the end of years 1 through 5, respectively. Project B has an initial cost of $15000, and its projected net cash flows are $7000, $5000, $3000, $2000, and $1000 at the end of years 1 through 5, respectively. At what cost of capital would the firm be...
You are trying to determine which of two mutually exclusive projects to undertake. Project Adam has...
You are trying to determine which of two mutually exclusive projects to undertake. Project Adam has an initial outlay of $10,000, an NPV of $4,392.15, an IRR of 11.33%, and an EAA of $1,158.64. Project Eve has an initial outlay of $15,000, an NPV of $5,833.73, an IRR of 9.88%, and an EAA of $1,093.50. The cost of capital for both projects is 9%, and the projects have different lives. If the projects are repeatable, then: You should do both...
You are trying to determine which of two mutually exclusive projects to undertake. Both projects have...
You are trying to determine which of two mutually exclusive projects to undertake. Both projects have the same initial outlay. Project Adam has an NPV of $4,392.15, an IRR of 11.33%, and an EAA of $1,158.64. Project Eve has an NPV of $5,833.73, an IRR of 9.88%, and an EAA of $1,093.50. The cost of capital for both projects is 9%, the projects have different lives, and the projects are not repeatable. What should you do? You should do Project...
Two projects being considered are mutually exclusive and have the following cash flows: Year Project A...
Two projects being considered are mutually exclusive and have the following cash flows: Year Project A Project B 0 −$50,000 −$50,000 1 15,625 0 2 15,625 0 3 15,625 0 4 15,625 0 5 1,562 89,500 If the required rate of return on these projects is 13 percent, which would be chosen and why? a. Project B because of higher NPV. b. Project B because of higher IRR. c. Project A because of higher NPV. d. Project A because of...
Two projects being considered are mutually exclusive and have the following cash flows: Year Project A...
Two projects being considered are mutually exclusive and have the following cash flows: Year Project A Project B 0 −$50,000 −$50,000 1 15,625 0 2 15,625 0 3 15,625 0 4 15,625 0 5 1,562 89,500 If the required rate of return on these projects is 13 percent, which would be chosen and why? a. Project B because of higher NPV. b. Project B because of higher IRR. c. Project A because of higher NPV. d. Project A because of...
Project X and Project Y are two mutually exclusive projects. Project X requires an initial outlay...
Project X and Project Y are two mutually exclusive projects. Project X requires an initial outlay of $38,000 and generates a net cash flow of $14,000 per year for six years. Project Y requires an initial outlay of $52,000, and will generate cash flows of $15,300 per year for eight years. Which project should be chosen and why? (Assume that the discount rate for both projects is 10 percent). A.  Project X because Project X has a larger NPV than Project...