Question

Wilson Co. purchased land as a factory site for $600,000. Wilson paid $60,000 to tear down...

  1. Wilson Co. purchased land as a factory site for $600,000. Wilson paid $60,000 to tear down two buildings on the land. Salvage was sold for $5,400. Legal fees of $3,480 were paid for title investigation and making the purchase. Architect's fees were $31,200. Title insurance cost $2,400, and liability insurance during construction cost $2,600. Excavation cost $10,440. The contractor was paid $2,200,000.

An assessment made by the city for pavement was $6,400. Interest costs during construction were $170,000. (compute cost of land and building)

Homework Answers

Answer #1

Assets are acquired at purchase price and the costs that are directly attributable to the cost of the asset.

Cost of Building

Particulars Amount
Architect Fees $31,200
(+)Liability Insurance $2,600
(+)Excavation Cost $10,440
(+)Contractor Cost $2,200,000
(+)Interest Costs $170,000
Cost of Building $2,414,240

Cost of Land

Particulars Amount
Purchase Price $600,000
(+) Tear Down Cost $60,000
(-) Salvage $5,400
(+) Legal Fees $3,480
(+) Title Insurance Cost $2,400
(+) Pavement Cost $6,400
Cost of Land $666,880
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Waterway Industries purchased land as a factory site for $1315000. Waterway paid $117000 to tear down...
Waterway Industries purchased land as a factory site for $1315000. Waterway paid $117000 to tear down two buildings on the land. Salvage was sold for $8400. Legal fees of $5480 were paid for title investigation and making the purchase. Architect's fees were $47000. Title insurance cost $3700, and liability insurance during construction cost $4000. Excavation cost $15800. The contractor was paid $4200000. An assessment made by the city for pavement was $9800. Interest costs during construction were $252000. The cost...
Vaughn Manufacturing purchased land as a factory site for $1330000. Vaughn paid $112000 to tear down...
Vaughn Manufacturing purchased land as a factory site for $1330000. Vaughn paid $112000 to tear down two buildings on the land. Salvage was sold for $8100. Legal fees of $5000 were paid for title investigation and making the purchase. Architect's fees were $46300. Title insurance cost $3500, and liability insurance during construction cost $3800. Excavation cost $15440. The contractor was paid $4400000. An assessment made by the city for pavement was $9600. Interest costs during construction were $257000. The cost...
Bob the Builder purchased land as a factory site for $282,000. He paid $10,000 to tear...
Bob the Builder purchased land as a factory site for $282,000. He paid $10,000 to tear down two buildings on the land, and the salvage from these old buildings was sold for $1,350. Legal fees of $870 were paid for title investigation and making the purchase. Architect's fees were $10,300. Liability insurance during construction cost $650. Excavation costs were $2,610. A contractor was paid $600,000 to construct the new building. An assessment made by the city for pavement was $1,600....
Sage Co. purchased land as a factory site for $ 592,000. The process of tearing down...
Sage Co. purchased land as a factory site for $ 592,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $ 62,160 to raze the old buildings and sold salvaged lumber and brick for $ 9,324. Legal fees of $ 2,738 were paid for title investigation and drawing the purchase contract. Sage paid $ 3,256 to an engineering firm for a land survey, and $ 100,640 for drawing...
Martin Buber Co. purchased land as a factory site for $758,400. The process of tearing down...
Martin Buber Co. purchased land as a factory site for $758,400. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $79,632 to raze the old buildings and sold salvaged lumber and brick for $11,945. Legal fees of $3,508 were paid for title investigation and drawing the purchase contract. Martin Buber paid $4,171 to an engineering firm for a land survey, and $128,928 for drawing the factory plans. The...
On February 1, 2020, Crane Company purchased a parcel of land as a factory site for...
On February 1, 2020, Crane Company purchased a parcel of land as a factory site for $318000. An old building on the property was demolished, and construction began on a new building which was completed on November 1, 2020. Costs incurred during this period are listed below: Demolition of old building $ 21000 Architect's fees 36000 Legal fees for title investigation and purchase contract 5300 Construction costs 1392000 (Salvaged materials resulting from demolition were sold for $10800.) Crane should record...
On February 1, 2020, Coronado Industries purchased a parcel of land as a factory site for...
On February 1, 2020, Coronado Industries purchased a parcel of land as a factory site for $325000. An old building on the property was demolished, and construction began on a new building which was completed on November 1, 2020. Costs incurred during this period are listed below: Demolition of old building $ 21300 Architect's fees 33900 Legal fees for title investigation and purchase contract 5400 Construction costs 1379000 (Salvaged materials resulting from demolition were sold for $9600.) Coronado should record...
On March 1, 2017, Beldon Corporation purchased land as a factory site for $58125. An old...
On March 1, 2017, Beldon Corporation purchased land as a factory site for $58125. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2017. Costs incurred during this period are listed below: Demolition of old building $3300 Architect's fees for new building $13578 Legal fees for title investigation of land $1649 Property taxes on land for period beginning March 1, 2016 $2084 Construction costs $552822 Interest on construction...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $71,000. An old...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $71,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2018. Costs incurred during this period are listed below: Demolition of old building $ 9,500 Architect’s fees (for new building) 10,000 Legal fees for title investigation of land 7,500 Property taxes on land (for period beginning March 1, 2018) 4,100 Construction costs 610,000 Interest on...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $72,000. An old...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $72,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2018. Costs incurred during this period are listed below: Demolition of old building $ 5,000 Architect’s fees (for new building) 11,000 Legal fees for title investigation of land 8,000 Property taxes on land (for period beginning March 1, 2018) 4,200 Construction costs 620,000 Interest on...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT