Question

Do you accept this project with the estimated required rate of return being 8.5%? You will...

Do you accept this project with the estimated required rate of return being 8.5%? You will use IRR as the measure.
Time 0 1 2 3 4
Total CFs -1,250 325 485 435 425

Homework Answers

Answer #1
Year Cash flow
0 -1250
1 325
2 485
3 435
4 425
IRR= 12.24% <<using excel formula>>
Since IRR is higher than required rate therefore project should be accepted.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
You've estimated the following cash flows (in $) for a project: The required return is 8.5%....
You've estimated the following cash flows (in $) for a project: The required return is 8.5%. What is the IRR for the project? What is the NPV of the project? A B 1 Year Cash flow 2 0 -3,320 3 1 974 4 2 1,281 5 3 1,875
You've estimated the following cash flows (in $) for a project: A B 1 Year Cash...
You've estimated the following cash flows (in $) for a project: A B 1 Year Cash flow 2 0 -3,430 3 1 974 4 2 1,281 5 3 1,996 The required return is 8.5%. 1. What is the IRR for the project? 2. What is the NPV of the project? 3 .What should you do? Check all that apply: Reject the project based on its NPV Reject the project based on its IRR Accept the project based on its IRR...
Intro You've estimated the following cash flows (in $) for a project: A B 1 Year...
Intro You've estimated the following cash flows (in $) for a project: A B 1 Year Cash flow 2 0 -3,200 3 1 974 4 2 1,281 5 3 1,647 The required return is 8.5%. Attempt 1/1 for 10 pts. Part 1 What is the IRR for the project? Submit Attempt 1/1 for 10 pts. Part 2 What is the NPV of the project? Submit Attempt 1/1 for 10 pts. Part 3 What should you do? Check all that apply:...
You are considering an investment with the following cash flows. If the required rate of return...
You are considering an investment with the following cash flows. If the required rate of return for this investment is 16.5 percent, should you accept the investment based solely on the internal rate of return rule? Why or why not? Year: 0, 1, 2, 3 Cash Flow: -152000, 98,200, 102,300, -4,900 A. Yes; The IRR exceeds the required return. B. Yes; The IRR is less than the required return. C. No; The IRR is less than the required return. D....
   1.       Consider the following project.  The firm’s cost of funds and its required rate of return is...
   1.       Consider the following project.  The firm’s cost of funds and its required rate of return is 13 percent.   Year Cash Flow 0 -31,000 1 13,000 2 14,000 3 9,000 What is the nondiscounted payback for this project?  If the firm must have payback in less than 2.5 years should it accept or reject the project? (5 Points) What is the Net Present Value of the project assuming the required rate of return is 13 percent?  Should the firm accept or reject the...
You are considering the following two mutually exclusive projects. The required rate of return is 12%...
You are considering the following two mutually exclusive projects. The required rate of return is 12% for project A and 11% for project B. Which project should you accept and why? Year Project A Project B 0           -$68,000   -$75,000 1                     28,000 15,000 2                     20,000   20,000 3                     20,000 20,000 4                     10,000 30,000
The following table shows the cash flows for a project. The required rate of return in...
The following table shows the cash flows for a project. The required rate of return in 20%. Compute the IRR. Year Project cash flow 0 -$120,000 1 $100,000 2 $40,000 3 $10,000 Group of answer choices 17% 20% 18% 19%
1.       Consider the following project.  The firm’s cost of funds and its required rate of return is 13...
1.       Consider the following project.  The firm’s cost of funds and its required rate of return is 13 percent.   Year Cash Flow 0 -31,000 1 13,000 2 14,000 3 9,000 What is the nondiscounted payback for this project?  If the firm must have payback in less than 2.5 years should it accept or reject the project? (5 Points) What is the Net Present Value of the project assuming the required rate of return is 13 percent?  Should the firm accept or reject the project?...
If your required rate of return is 7%, calculate the MIRR of a project with the...
If your required rate of return is 7%, calculate the MIRR of a project with the following expected cashflows (in thousands):- (8) Time 0 1 2 3 4 5 Cashflow -130 60 70 -60 50 50
You are considering two independent projects with the following cash flows. The required return for both...
You are considering two independent projects with the following cash flows. The required return for both projects is 10%. Given this information, which one of the following statements is correct? Year  Project A  Project B 0    -950,000  -125,000 1      330,000    55,000 2      400,000    50,000 3      450,000      50,000 You should accept project B because it has the higher IRR and reject project A You should accept project A because it has the higher NPV and you can not accept both projects You should accept...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT