Question

The IRR of project X is 18%. The IRR of project Y is 17%. The company's...

The IRR of project X is 18%. The IRR of project Y is 17%. The company's cost of capital (cost of accessing funds to finance the projects) is 10%. If projects X and Y are independent and the company has enough funds to do both, which project (s) should they chose? If they are mutually exclusive, which do you chose?

Homework Answers

Answer #1

Answer:
In case projects are Independent:

In case the Project X and Y are independent, the Company will choose the projects whose IRR is more than the Company’s Cost of Capital. So, the Company will choose both the projects i.e. Project X and Project Y.

In case projects are mutually exclusive:
In case the Project X and Y are mutually exclusive, the Company will chose the project with higher IRR. So, the Company will choose Project X as its IRR is more than IRR of Project Y.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Consider two projects, X and Y. Project X's IRR is 19% and Project Y's IRR is...
Consider two projects, X and Y. Project X's IRR is 19% and Project Y's IRR is 17%. The projects have the same risk and the same lives, and each has constant cash flows during each year of their lives. If the cost of capital is 10%, Project Y has a higher NPV than X. Given this information, which of the following statements is CORRECT? (Hint: it is useful to draw NPV profiles) The crossover rate must be less than 10%....
You are analyzing two proposed capital investments with the following cash flows: Year Project X Project...
You are analyzing two proposed capital investments with the following cash flows: Year Project X Project Y 0 - $20,000 - $20,000 1 12,730 6,670 2 5,660 6,670 3 5,860 6,670 4 2,020 6,670 The cost of capital for both projects is 10 percent. Calculate the profitability index (PI) for each project. (Do not round discount factors. Round intermediate calculations to 2 decimal places, e.g. 15.25 and final answer to 4 decimal places, e.g. 1.2527.) The PI for project X...
A firm is considering to undertake Projects X and Y, whose cash flows are shown below....
A firm is considering to undertake Projects X and Y, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. WACC: 6.00% )million of N) Year Year 0 Year 1 Year 2 Year 3 Year 4 CFx -N 1,025 N 380 N 380 N 380 N 380 CFy...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Project A Project B Project C Project D Project E Project F Project G NPV= $4,711 ($711) ($657) $334 $9,842 $7,360 ($3,224) IRR= 44.51% 5.47% 8.06% 12.98% 22.56% 17.19% 5.47% MIRR= 25.23% 7.50% 8.97% 11.57% 16.26% 13.70% 7.50% PI= 2.178 0.822 0.945 1.028 1.394 1.294 0.871 The discounting rate (r)...
Two projects are being considered. An office building has an IRR of 20%; NPV of $100,000...
Two projects are being considered. An office building has an IRR of 20%; NPV of $100,000 and a payback of 3 years. Alternatively a small sandwich shop has an IRR of 40%; NPV of $25,000 and a payback of 1 year. Which of the two projects should be chosen? If projects are mutually exclusive, choose both; if projects are independent, choose Sandwich shop. If projects are mutually exclusive, choose Sandwich Shop; if projects are independent, choose both. Do not choose...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Criteria:                Project_A         Project_B             Project_C         Project_D          Project_E               Project_F             Project_G NPV= $137,083 $31,290 $6,016 $7,647 ($584) $12,521 $9,214 IRR= 31.80% 48.34% 12.03% 11.30% 9.94% 26.79% 37.87% MIRR= 18.52% 23.52% 10.62% 10.59% 9.97% 23.53% 20.76% PI= 1.69 2.25 1.040 1.038 0.999 2.25 1.92 The discounting rate...
Project X and Project Y are two mutually exclusive projects. Project X requires an initial outlay...
Project X and Project Y are two mutually exclusive projects. Project X requires an initial outlay of $38,000 and generates a net cash flow of $14,000 per year for six years. Project Y requires an initial outlay of $52,000, and will generate cash flows of $15,300 per year for eight years. Which project should be chosen and why? (Assume that the discount rate for both projects is 10 percent). A.  Project X because Project X has a larger NPV than Project...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Criteria:                Project_A         Project_B             Project_C         Project_D          Project_E               Project_F             Project_G NPV= $137,083 $31,290 $6,016 $7,647 ($584) $12,521 $9,214 IRR= 31.80% 48.34% 12.03% 11.30% 9.94% 26.79% 37.87% MIRR= 18.52% 23.52% 10.62% 10.59% 9.97% 23.53% 20.76% PI= 1.69 2.25 1.040 1.038 1.00 2.25 1.92 The discounting rate...
Frazier Fudge, Inc. is considering 2 mutually exclusive projects with the following cash flows. Which project...
Frazier Fudge, Inc. is considering 2 mutually exclusive projects with the following cash flows. Which project should be accepted? Assume a cost of capital of 10%. Years Project X Project Y 0 ($350) ($350) 1 $130 $200 2 $150 $120 3 $180 $120 a. Project X because NPV is $27.4 b. Project Y because NPV is $31 c. Project X because IRR is 13.7% d. Project Y because IRR is 12.2%
A company is considering the following investment opportunities: Project A Initial cost = $5,500,000 Expected life...
A company is considering the following investment opportunities: Project A Initial cost = $5,500,000 Expected life = 10 yrs NPV = $340,000 IRR = 20% Project B Initial cost = $3,000,000 Expected life = 10 yrs NPV = $300,000 IRR = 30% Project C Initial cost = $2,000,000 Expected life = 10 yrs NPV = $200,000 IRR = 40% If the company has a WACC of 15% and the company is using capital rationing with a fixed capital budget of...