Question

Anne is considering two independent projects with 2-year lives. Both projects have been assigned a discount...

Anne is considering two independent projects with 2-year lives. Both projects have been assigned a discount rate of 13 percent. She has sufficient funds to finance one or both projects. Project A costs $38,500 and has cash flows of $19,400 and $28,700 for Years 1 and 2, respectively. Project B costs $41,000, and has cash flows of $25,000 and $22,000 for Years 1 and 2, respectively. Which project, or projects, if either, should you accept based on the profitability index method and what is the correct reason for that decision?

a. You should accept both projects since both of their PIs are positive.

b. You should accept Project A since it has the higher PI and you can only select one.

c. You should accept both projects since both of their PIs are greater than 1.

d. You should only accept project A since it has the largest PI and the PI exceeds one.

e. Neither project is acceptable.

Homework Answers

Answer #1

Project A:

Cash Flows:

Year 0 = -$38,500
Year 1 = $19,400
Year 2 = $28,700

Discount Rate = 13%

Present Value of Cash Inflows = $19,400/1.13 + $28,700/1.13^2
Present Value of Cash Inflows = $39,644.45

Profitability Index = Present Value of Cash Inflows / Initial Cash Outflow
Profitability Index = $39,644.45 / $38,500
Profitability Index = 1.03

Project B:

Cash Flows:

Year 0 = -$41,000
Year 1 = $25,000
Year 2 = $22,000

Discount Rate = 13%

Present Value of Cash Inflows = $25,000/1.13 + $22,000/1.13^2
Present Value of Cash Inflows = $39,353.12

Profitability Index = Present Value of Cash Inflows / Initial Cash Outflow
Profitability Index = $39,353.12 / $41,000
Profitability Index = 0.96

You should only accept project A since it has the largest PI and the PI exceeds one.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
You are considering two independent projects both of which have been assigned a discount rate of...
You are considering two independent projects both of which have been assigned a discount rate of 11.5% percent. Based on the project NPV, what is your recommendation concerning these projects? Project A Year Cash Flow 0 -$91,850 1 $28,405 2 $64,890 Project B Year Cash Flows 0 -$45,000 1 $38,500 2 $17,325 Select one: a. You should reject both projects. b. You should accept project A and reject project B. c. You should accept project B and reject project A....
You are considering two independent projects both of which have been assigned a discount rate of...
You are considering two independent projects both of which have been assigned a discount rate of 15% percent. Based on the project NPV, what is your recommendation concerning these projects? Project A Project B Year Cash Flow Year Cash Flow 0 -$40,000 0 -$51,173 1 $35,000 1 $18,400 2 $27,000 2 $14,750 You should accept both projects. You should reject both projects. You should accept project B and reject project A. You should accept project A and reject project B....
11.    You are considering two independent projects both of which have been assigned a discount...
11.    You are considering two independent projects both of which have been assigned a discount rate of 15 percent. Based on the NPV rule, what is your recommendation concerning these projects? (a) You should accept both projects. (b) You should reject both projects. (c) You should accept project A and reject project B. (d) You should accept project B and reject project A. (e) None of the above is correct. 12.    New Labs just announced that it has...
You are considering two independent projects with the following cash flows. The required return for both...
You are considering two independent projects with the following cash flows. The required return for both projects is 10%. Given this information, which one of the following statements is correct? Year  Project A  Project B 0    -950,000  -125,000 1      330,000    55,000 2      400,000    50,000 3      450,000      50,000 You should accept project B because it has the higher IRR and reject project A You should accept project A because it has the higher NPV and you can not accept both projects You should accept...
Two mutually exclusive projects have 3-year lives and a required rate of return of 10.5 percent....
Two mutually exclusive projects have 3-year lives and a required rate of return of 10.5 percent. Project A costs $75,000 and has cash flows of $18,500, $42,900, and $28,600 for Years 1 to 3, respectively. Project B costs $72,000 and has cash flows of $22,000, $38,000, and $26,500 for Years 1 to 3, respectively. Using the IRR, which project, or projects, if either, should be accepted? reject both projects accept both projects accept Project A and reject Project B. accept...
You are considering two mutually exclusive projects. Based upon risk, the appropriate discount rate for both...
You are considering two mutually exclusive projects. Based upon risk, the appropriate discount rate for both projects is 10%. The first project has an IRR of 22% and an NPV of $22,432. The second project has an IRR of 12% and an NPV of $24,456. Which project should you select? accept both projects since both are acceptable. pick the project with the shorter payback period. choose the project with the higher NPV. unable to determine due to insufficient information. choose...
You are considering two mutually exclusive projects that have been assigned the same discount rate of...
You are considering two mutually exclusive projects that have been assigned the same discount rate of 10.5 percent. Project A has an initial cost of $54,500, and should produce cash inflows of $16,400, $28,900, and $31,700 for Years 1 to 3, respectively. Project B has an initial cost of $79,400, and should produce cash inflows of $0, $48,300, and $42,100, for Years 1 to 3, respectively. What is the incremental IRR? 7.83% 5.40% −15.40% -4.67% 13.89%
You are considering two independent projects. The required rate of return is 13.75 percent for Project...
You are considering two independent projects. The required rate of return is 13.75 percent for Project A and 14.25 percent for Project B. Project A has an initial cost of $51,400 and cash inflows of $21,400, $24,900, and $22,200 for Years 1 to 3, respectively. Project B has an initial cost of $38,300 and cash inflows of $18,000 a year for 3 years. Which project(s), if any, should you accept? A. Reject both Projects. B. Accept both projects. C. Accept...
1.     Suppose your firm is considering two independent projects with the cash flows shown as follows....
1.     Suppose your firm is considering two independent projects with the cash flows shown as follows. The required rate of return on projects of both of their risk class is 12 percent, and the maximum allowable payback and discounted payback statistic for the projects are two and a half and three years, respectively. Time 0 1 2 3 Project A Cash Flow ?5,000 1,000 3,000 5,000 Project B Cash Flow ?10,000 5,000 5,000 5,000 Use the payback decision rule to...
You have two projects to consider. Both have 4-years of cash flows and a 4% discount...
You have two projects to consider. Both have 4-years of cash flows and a 4% discount rate is appropriate for both projects. The cash flows for project X have a present value of $362.99. Present Value @ 4% End of Year 1 End of Year 2 End of Year 3 End of Year 4 Project X 362.99 100 100 100 100 Project Y -100 -100 -100 -100 Which of the following is correct? You would accept project X if the...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT