Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)
Project U | ||||||
Time: | 0 | 1 | 2 | 3 | 4 | 5 |
Cash flow: | –$1,600 | $590 | $2,080 | –$640 | $540 | –$220 |
NPV=
Should the project be accepted or rejected?
Solution:-
To Calculate NPV of the Project-
NPV = PV of cash Inflow - PV of cash Outflow
NPV =
NPV =
NPV = 590 * 0.909 + 2,080 * 0.826 - 640 * 0.751 + 540 * 0.683 - 220 * 621 - 1,600
NPV = 536.36 + 1,719.01 - 480.84 + 368.83 - 136.60 - 1,600
NPV = $406.76
Project is accepted when NPV of the Project is greater than or equal to zero. Hence, the Project is accepted.
If you have any query related to question then feel free to ask me in a comment.Thanks.
Get Answers For Free
Most questions answered within 1 hours.