Question

Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent....

Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)

Project U
Time: 0 1 2 3 4 5
Cash flow: –$1,600 $590 $2,080 –$640 $540 –$220

NPV=

Should the project be accepted or rejected?

Homework Answers

Answer #1

Solution:-

To Calculate NPV of the Project-

NPV = PV of cash Inflow - PV of cash Outflow

NPV =

NPV =

NPV = 590 * 0.909 + 2,080 * 0.826 - 640 * 0.751 + 540 * 0.683 - 220 * 621 - 1,600

NPV = 536.36 + 1,719.01 - 480.84 + 368.83 - 136.60 - 1,600

NPV = $406.76

Project is accepted when NPV of the Project is greater than or equal to zero. Hence, the Project is accepted.

If you have any query related to question then feel free to ask me in a comment.Thanks.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent....
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal place.) Project Y Time: 0 1 2 3 4 Cash flow: –$9,300 $3,610 $4,440 $1,780 $560 NPV $ _________ Should the project be accepted or rejected? _____________
Compute the NPV statistic for Project U if the appropriate cost of capital is 11 percent....
Compute the NPV statistic for Project U if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: 0 1 2 3 4 5 Cash flow: –$2,500 $750 $2,480 –$720 $700 –$300
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent....
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: 0 1 2 3 4 5 Cash flow: –$2,300 $670 $2,280 –$680 $620 –$260
Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project M Time: 0 1 2 3 4 5 Cash flow –$2,200 $590 $720 $760 $840 $340 NPV $ Should the project be accepted or rejected?
Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project M Time: 0 1 2 3 4 5 Cash flow: –$1,200 $390 $520 $560 $640 $140 Problem 13-3 NPV with Non-normal Cash Flows (LG13-3) Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project M Time: 0 1 2 3 4 5 Cash flow: –$3,100 $710 $840 $880 $960 $460 Should the project be rejected or accepted?
Compute the PI statistic for Project Q if the appropriate cost of capital is 13 percent....
Compute the PI statistic for Project Q if the appropriate cost of capital is 13 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Q Time: 0 1 2 3 4 Cash flow: −$11,800 $3,750 $4,580 $1,920 $2,550 Should the project be accepted or rejected? rejected accepted
Compute the PI statistic for Project Q if the appropriate cost of capital is 11 percent....
Compute the PI statistic for Project Q if the appropriate cost of capital is 11 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.)      Project Q   Time: 0 1 2 3 4   Cash flow –$12,300 $4,000 $4,830 $2,170 $2,800      PI       Should the project be accepted or rejected? Accepted Rejected
Compute the MIRR statistic for Project J if the appropriate cost of capital is 8 percent....
Compute the MIRR statistic for Project J if the appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project J Time: 0 1 2 3 4 5 Cash flow: −$2,700 $860 $2,330 −$690 $810 −$270 Should the project be accepted or rejected? accepted rejected
Compute the MIRR statistic for Project J if the appropriate cost of capital is 9 percent....
Compute the MIRR statistic for Project J if the appropriate cost of capital is 9 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project J Time: 0 1 2 3 4 5 Cash flow –$2,000 $650 $1,980 –$620 $600 –$200 MIRR % Should the project be accepted or rejected? Accepted Rejected