Project L costs $50,000, its expected cash inflows are $14,000 per year for 12 years, and its WACC is 11%. What is the project's NPV? Do not round intermediate calculations. Round your answer to the nearest cent
Ans NPV = $ 40892.99
roject L costs $50,000, its expected cash inflows are $14,000 per year for 12 years, and its WACC is 11%. The project's NPV is $ 40892.99