Question

question 1 Consider the following two projects: Time         Cash Flows                 A           

question 1

Consider the following two projects:

Time         Cash Flows

                A                      B

0          -$4,000               -$4,000

1           $2,003               $0

2            $2,003               $0

3            $2,003               $0

4           $2,003               $10,736

Assuming a 14 percent discount rate, which project would you prefer?

Hint: Use NPV method

I.

Project B, because it has a higher NPV

II.

None of the above

III.

Project A, because it has a higher NPV
                     
      

IV.

Project A, because it has a higher IRR

V.

Project B, because it has a higher IRR

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Two projects being considered are mutually exclusive and have the following cash flows: Year Project A...
Two projects being considered are mutually exclusive and have the following cash flows: Year Project A Project B 0 −$50,000 −$50,000 1 15,625 0 2 15,625 0 3 15,625 0 4 15,625 0 5 1,562 89,500 If the required rate of return on these projects is 13 percent, which would be chosen and why? a. Project B because of higher NPV. b. Project B because of higher IRR. c. Project A because of higher NPV. d. Project A because of...
Two projects being considered are mutually exclusive and have the following cash flows: Year Project A...
Two projects being considered are mutually exclusive and have the following cash flows: Year Project A Project B 0 −$50,000 −$50,000 1 15,625 0 2 15,625 0 3 15,625 0 4 15,625 0 5 1,562 89,500 If the required rate of return on these projects is 13 percent, which would be chosen and why? a. Project B because of higher NPV. b. Project B because of higher IRR. c. Project A because of higher NPV. d. Project A because of...
You are considering two independent projects with the following cash flows. The required return for both...
You are considering two independent projects with the following cash flows. The required return for both projects is 10%. Given this information, which one of the following statements is correct? Year  Project A  Project B 0    -950,000  -125,000 1      330,000    55,000 2      400,000    50,000 3      450,000      50,000 You should accept project B because it has the higher IRR and reject project A You should accept project A because it has the higher NPV and you can not accept both projects You should accept...
You are choosing between two projects. The cash flows for the projects are given in the...
You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A: - $49   $23 $19 $22 $17 B: - $102 $20 $40 $48 $60 a. What are the IRRs of the two​ projects? - The IRR for project A is ? - The IRR for project B is ? b. If your discount rate is 5.5 %​, what are...
You are choosing between two projects. The cash flows for the projects are given in the...
You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A: - $50 $25 $22 $19 $13 B: - $98 $21 $41 $50 $62 a. What are the IRRs of the two​ projects? - The IRR for project A is ? - The IRR for project B is ? b. If your discount rate is 5.1 %​, what are...
NPV verses IRR Consider the following cash flows on the two mutually exclusive projects for the...
NPV verses IRR Consider the following cash flows on the two mutually exclusive projects for the Bahamas Recreation Corporations (BRC). Both projects require an annual return on 14% Year Deep Water  Fishing New Submarine Ride 0 -$850,000 -$1,650,000 1 320,000 810,000 2 470,000 750,000 3 410,000 690,000 a) If your decision rile is to accept the project with the greater IRR, which project should you choose? c) To be prudent, you compute the NPV for both projects. Which project should you...
Tara is evaluating two mutually exclusive capital budgeting projects that have the following characteristics: Cash Flows...
Tara is evaluating two mutually exclusive capital budgeting projects that have the following characteristics: Cash Flows Year Project Q Project R 0 $(4,000) $(4,000) 1 0 3,500 2 5,000 2,100 IRR 11.8% 28.40% If the firm's required rate of return (r) is 10 percent, which project should be purchased? a. Both projects should be purchased, because the IRRs for both projects exceed the firm's required rate of return. b. Neither project should be accepted, because their NPVs are too small...
Tara is evaluating two mutually exclusive capital budgeting projects that have the following characteristics: Cash Flows...
Tara is evaluating two mutually exclusive capital budgeting projects that have the following characteristics: Cash Flows Year Project Q Project R 0 $(4,000) $(4,000) 1 0 3,500 2 5,000 2,100 IRR 11.8% 28.40% If the firm's required rate of return (r) is 10 percent, which project should be purchased? a. Both projects should be purchased, because the IRRs for both projects exceed the firm's required rate of return. b. Neither project should be accepted, because their NPVs are too small...
You are choosing between two projects. The cash flows for the projects are given in the...
You are choosing between two projects. The cash flows for the projects are given in the following table? ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A -$52 $ 26 $ 21 $20 $17 B -$101 $ 21 $ 38 $48 $61 a. What are the IRRs of the two? projects? IRR for project A is _ ?IRR for project B is _ b. If your discount rate is 5.1 % what are the NPVs...
1.The Hyatt Group Inc., has identified the following two mutually exclusive projects:                         Cash Flows  &n
1.The Hyatt Group Inc., has identified the following two mutually exclusive projects:                         Cash Flows                 Cash Flows Year                Project A                     Project B    0                   -$10,000                      _$10,000    1                           200                            5,000    2                           500                            6,000    3                        8,200                               500    4                        4,800                               500 What is the IRR of each of these projects?  If you apply the IRR decision rule, which project should the company accept?  Is this decision necessarily correct? If the required rate of return is 9 percent, what is the NPV of each of the projects?  Which project will you choose if you apply the NPV decision rule? Over what range...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT