Question

Question Two: (A) What is the likely response by the stock market when a firm announces...

Question Two:

(A)

What is the likely response by the stock market when a firm announces a positive NPV project? Is there

any reason to believe that this response might sometimes be negative?

(B)

The IRR of normal project X is greater than the IRR of normal project Y, and both IRR's are greater than

zero. (A normal project is defined as having a cash outflow in time 0 and cash inflows in all subsequent

periods). Also, the NPV of X is greater than the NPV of Y at the cost of capital. If the two projects are

mutually exclusive, Project X should definitely be selected, and the investment made, provided we have

confidence in the data. Put another way, it is impossible to draw NPV profiles that would suggest not accepting Project X.

(true/false/uncertain) Explain your answer.

Homework Answers

Answer #1

1:The stock price will increase in anticipation of higher profits. Suppose the project is very high risk, the stock price may decline due to high amount of risk passing to the shareholders even though NPV is positive.

2: TRUE

IRRX>IRRy>0

NPVx> NPVy

Since the IRR of project X is greater than Y, it implies greater returns from project X. Also the NPV of X Is higher which means greater dollar returns from X. So Project X should be selected. NPV profile determines NPV at various discount rates. Since NPV of X is higher at the cost of capital it will alsway be so at other rates. Hence the profiles will always suggest preference of X over Y.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Two mutually exclusive projects each have a cost of $10,000. The total, undiscounted cash flows from...
Two mutually exclusive projects each have a cost of $10,000. The total, undiscounted cash flows from Project L are $15,000, while the undiscounted cash flows from Project S total $13,000. Their NPV profiles cross at a discount rate of 10 percent. Which of the following statements best describes this situation? Please leave an explanation.  a. The NPV and IRR methods will select the same project if the cost of capital is greater than 10 percent; for example, 18 percent. b. The...
4. Internal rate of return (IRR) The internal rate of return (IRR) refers to the compound...
4. Internal rate of return (IRR) The internal rate of return (IRR) refers to the compound annual rate of return that a project generates based on its up-front cost and subsequent cash flows. Consider the case of Blue Llama Mining Company: Blue Llama Mining Company is evaluating a proposed capital budgeting project (project Sigma) that will require an initial investment of $800,000. The company has been basing capital budgeting decisions on a project’s NPV; however, its new CFO wants to...
The Basics of Capital Budgeting: NPV Profile A project's NPV profile graph intersects the Y-axis at...
The Basics of Capital Budgeting: NPV Profile A project's NPV profile graph intersects the Y-axis at 0% cost of capital and intersects the X-axis at the project's -Select-paybackMIRRIRRCorrect 1 of Item 1 (where NPV = 0). The Y-axis intersection point represents the project's undiscounted NPV. The point at which 2 projects' profiles cross one another is the crossover rate. The crossover rate can be found by calculating the -Select-IRRpaybackMIRRCorrect 2 of Item 1 of the differences in the projects' cash...
13. NPV and IRR Analysis Cummings Products Company is considering two mutually exclusive investments whose expected...
13. NPV and IRR Analysis Cummings Products Company is considering two mutually exclusive investments whose expected net cash flows are as follows: Expected Net Cash Flows Year Project A Project B 0 -$400 -$650 1 -528 210 2 -219 210 3 -150 210 4 1,100 210 5 820 210 6 990 210 7 -325 210 Select the correct graph for NPV profiles for Projects A and B.     The correct graph is (select one) graph __? What is each project's...
An oil-drilling company must choose between two mutually exclusive extraction projects, and each requires an initial...
An oil-drilling company must choose between two mutually exclusive extraction projects, and each requires an initial outlay at t = 0 of $11.6 million. Under Plan A, all the oil would be extracted in 1 year, producing a cash flow at t = 1 of $13.92 million. Under Plan B, cash flows would be $2.0612 million per year for 20 years. The firm's WACC is 12.1%. Construct NPV profiles for Plans A and B. Enter your answers in millions. For...
An oil-drilling company must choose between two mutually exclusive extraction projects, and each requires an initial...
An oil-drilling company must choose between two mutually exclusive extraction projects, and each requires an initial outlay at t = 0 of $13 million. Under Plan A, all the oil would be extracted in 1 year, producing a cash flow at t = 1 of $15.6 million. Under Plan B, cash flows would be $2.31 million per year for 20 years. The firm's WACC is 12.2%. Construct NPV profiles for Plans A and B. Enter your answers in millions. For...
An oil-drilling company must choose between two mutually exclusive extraction projects, and each requires an initial...
An oil-drilling company must choose between two mutually exclusive extraction projects, and each requires an initial outlay at t = 0 of $11.6 million. Under Plan A, all the oil would be extracted in 1 year, producing a cash flow at t = 1 of $13.92 million. Under Plan B, cash flows would be $2.0612 million per year for 20 years. The firm's WACC is 12.7%. Construct NPV profiles for Plans A and B. Enter your answers in millions. For...
An oil-drilling company must choose between two mutually exclusive extraction projects, and each requires an initial...
An oil-drilling company must choose between two mutually exclusive extraction projects, and each requires an initial outlay at t = 0 of $11 million. Under Plan A, all the oil would be extracted in 1 year, producing a cash flow at t = 1 of $13.2 million. Under Plan B, cash flows would be $1.9546 million per year for 20 years. The firm's WACC is 12.8%. Construct NPV profiles for Plans A and B. Enter your answers in millions. For...
An oil-drilling company must choose between two mutually exclusive extraction projects, and each requires an initial...
An oil-drilling company must choose between two mutually exclusive extraction projects, and each requires an initial outlay at t = 0 of $12.8 million. Under Plan A, all the oil would be extracted in 1 year, producing a cash flow at t = 1 of $15.36 million. Under Plan B, cash flows would be $2.2744 million per year for 20 years. The firm's WACC is 11.1%. Construct NPV profiles for Plans A and B. Enter your answers in millions. For...
An oil-drilling company must choose between two mutually exclusive extraction projects, and each requires an initial...
An oil-drilling company must choose between two mutually exclusive extraction projects, and each requires an initial outlay at t = 0 of $11.6 million. Under Plan A, all the oil would be extracted in 1 year, producing a cash flow at t = 1 of $13.92 million. Under Plan B, cash flows would be $2.0612 million per year for 20 years. The firm's WACC is 11.3%. Construct NPV profiles for Plans A and B. Enter your answers in millions. For...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT