Answer a):
With discount rate of 10%, Net Present Value (NPV) of this project over the 3 year period
= - R36,048
Workings are as below:
Answer b):
As the NPV is negative, project is not recommended.
Answer c):
Even if we change the discount rate to 5%, still NPV is negative; as such answer will not change. At discount rate of 5%, the NPV is - R10,331 and project is not recommended.
Workings are as below:
Answer d):
Nominal cash flows are the future cash flows with any adjustment made for inflation.
We find the cumulative cash flows over year 1,2 and 3 as follows:
From cumulative cash flows we find that project will break-even in year 3.
Break-even point = 2 + 110,000 / 130,000 = 2.85 years
Get Answers For Free
Most questions answered within 1 hours.