Question

A project has the following projected cash flows Year 0- R280,000( investment) Year 1 R70,000 Year...

A project has the following projected cash flows
Year 0- R280,000( investment)
Year 1 R70,000
Year 2 R100,000
Year 3 R130,000
a) Assuming a discount rate of 10% what is the Net Present Value (NPV) of this project over the 3 year period?
b) Based on your answer above, should the project be recommended for acceptance?
c) would your answer to b above change if the discount rate was 5%? Why?
d) what do you understand by the term nominal cash flows? In terms of the nominal cash flows above , at approximately what point does the project break-even?

Homework Answers

Answer #1

Answer a):

With discount rate of 10%, Net Present Value (NPV) of this project over the 3 year period

= - R36,048

Workings are as below:

Answer b):

As the NPV is negative, project is not recommended.

Answer c):

Even if we change the discount rate to 5%, still NPV is negative; as such answer will not change. At discount rate of 5%, the NPV is - R10,331 and project is not recommended.

Workings are as below:

Answer d):

Nominal cash flows are the future cash flows with any adjustment made for inflation.

We find the cumulative cash flows over year 1,2 and 3 as follows:

From cumulative cash flows we find that project will break-even in year 3.

Break-even point = 2 + 110,000 / 130,000 = 2.85 years

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Answer Question 1-3 Project A has the following projected cash flows: Year           Cash Flow 0                -11,23
Answer Question 1-3 Project A has the following projected cash flows: Year           Cash Flow 0                -11,235 1                4,400 2                4,400 3                4,400 4                4,400 5                7,400 Q1) The NPV of the above project is $_____. Assume a discount rate of 6%. a)9541 b)20776 c)17623 d)6388 Q2) The IRR for the above project is __ %. a)21.09 b)26.76 c)33.95 d)31.25 Q3)Which of the following statement is correct? a)If the discount rate increases, the IRR will decrease. b)If the discount rate increases, the NPV will stay the same. c)If...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0 –$ 61,000 –$ 76,000 1 41,000 40,000 2 36,000 49,000 3 31,000 52,000    The cash flows of Project A are expressed in real terms while those of Project B are expressed in nominal terms. The appropriate nominal discount rate is 12 percent and the inflation rate is 3 percent.    Calculate the NPV for each project. (Do not round intermediate calculations and round...
Assuming a project having the following cash flows: Year 0 1 2 3 4 Cash flow...
Assuming a project having the following cash flows: Year 0 1 2 3 4 Cash flow -6000 500 -500 5000 3000 What is the NPV of this project if the discount rate is 5%? Report the answer with 2 numbers after decimal place What is the IRR of this project? Report the answer in percentage term with 2 numbers after decimal place such as 12.43%. What discount rate will make NPV of this project equals to -494.258 Report the answer...
Company ABC is considering a project with the following projected cash flows (in thousands): Year 0:...
Company ABC is considering a project with the following projected cash flows (in thousands): Year 0: -$60 Year 1: 10 Year 2: 20 Year 3: 30 Year 4: 40 Year 5: -$25 a. Assuming a 10% hurdle rate, the NPV for the project is b. Assuming a 10% hurdle rate, the IRR for company ABC project is: c. Based on the NPV calculation (10% hurdle rate) , should company ABC undertake the project d. Based on the IRR calculation (10%...
A firm has projected free cash flows of $575,000 for Year 1, $625,000 for Year 2,...
A firm has projected free cash flows of $575,000 for Year 1, $625,000 for Year 2, and 750,000 for Year 3. The projected terminal value at the end of Year 3 is $8,000,000. The firm's Weighted Average cost of Capital (WACC) is 12.5%. Please post the answer in an Excel Document Determine the Discounted Cash Flow (DCF) value of the firm. Recommend acceptance of this project using net present value criteria. Display your calculations.
Net present value. Quark Industries has a project with the following projected cash​ flows: Initial​ cost:...
Net present value. Quark Industries has a project with the following projected cash​ flows: Initial​ cost: ​$200,000 Cash flow year​ one: ​$23,000 Cash flow year​ two: ​$72,000 Cash flow year​ three: ​$157,000 Cash flow year​ four: ​$157,000 a.  Using a discount rate of 10​% for this project and the NPV​ model, determine whether the company should accept or reject this project. b.  Should the company accept or reject it using a discount rate of 14​%? c.  Should the company accept...
Net present value. Lepton Industries has a project with the following projected cash​ flows: Initial cost  ...
Net present value. Lepton Industries has a project with the following projected cash​ flows: Initial cost   Cash flow year one   Cash flow year two   Cash flow year three   Cash flow year four $463,000   $124,000   $240,000   $185,000   $124,000 a. Using a discount rate of 99​% for this project and the NPV​ model, determine whether the company should accept or reject this project. b. Should the company accept or reject it using a discount rate of 1717​%? c. Should the company accept...
A project has the following cash flows: Year Cash Flow 0 –$ 15,400 1 6,100 2...
A project has the following cash flows: Year Cash Flow 0 –$ 15,400 1 6,100 2 7,400 3 5,900 What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.) NPV $ 4,000 What is the NPV at a discount rate of 8 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) NPV $ 1,276.06 What is...
A project has the following cash flows: Year Cash Flow 0 –$ 16,600 1 7,300 2...
A project has the following cash flows: Year Cash Flow 0 –$ 16,600 1 7,300 2 8,600 3 7,100 What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.) What is the NPV at a discount rate of 12 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) What is the NPV at a discount rate...
Lepton Industries has a project with the following projected cash​ flows: Initial cost: $470,000 Cash flow...
Lepton Industries has a project with the following projected cash​ flows: Initial cost: $470,000 Cash flow year one: $120,000 Cash flow year two: $300,000 Cash flow year three: $193,000 Cash flow year four: $120,000 a. Using a discount rate of 11% for this project and the NPV​ model, determine whether the company should accept or reject this project. b. Should the company accept or reject it using a discount rate of 14%? c. Should the company accept or reject it...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT