Question

Compute the payback period for a project that requires an initial outlay of $231,091 that is...

Compute the payback period for a project that requires an initial outlay of $231,091 that is expected to generate $40,000 per year for 9 years.

Homework Answers

Answer #1

payback period = 5.777275 years

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Project A requires an initial outlay at t = 0 of $56,841, its expected cash inflows...
Project A requires an initial outlay at t = 0 of $56,841, its expected cash inflows are $11,000 per year for 9 years, and its WACC is 13%. What is the project's IRR? Round your answer to two decimal places. Project P requires an initial outlay at t = 0 of $45,000, its expected cash inflows are $15,000 per year for 9 years, and its WACC is 12%. What is the project's MIRR? Do not round intermediate calculations. Round your...
1.) Project L requires an initial outlay at t = 0 of $50,000, its expected cash...
1.) Project L requires an initial outlay at t = 0 of $50,000, its expected cash inflows are $15,000 per year for 9 years, and its WACC is 14%. What is the project's NPV? Do not round intermediate calculations. Round your answer to the nearest cent. $   2.) Project L requires an initial outlay at t = 0 of $57,430, its expected cash inflows are $10,000 per year for 10 years, and its WACC is 14%. What is the project's...
A firm is considering the two mutually exclusive investments projects. Project Alpha requires an initial outlay...
A firm is considering the two mutually exclusive investments projects. Project Alpha requires an initial outlay of $600 and will return $160 per year for the next seven years; Project Beta requires an initial outlay of $1,100 and will return $350 per year for the next five years. Assuming a 11% required return, calculate the NPV, Payback Period, and MIRR of each project. Please help by showing Excel calculations. Thanks!
Project L requires an initial outlay at t = 0 of $65,000, its expected cash inflows...
Project L requires an initial outlay at t = 0 of $65,000, its expected cash inflows are $15,000 per year for 9 years, and its WACC is 10%. What is the project's discounted payback? Do not round intermediate calculations. Round your answer to two decimal places. ____ years
Project L requires an initial outlay at t = 0 of $25,000, its expected cash inflows...
Project L requires an initial outlay at t = 0 of $25,000, its expected cash inflows are $5,000 per year for 9 years, and its WACC is 11%. What is the project's discounted payback? Do not round intermediate calculations. Round your answer to two decimal places.   years
Project L requires an initial outlay at t = 0 of $50,000, its expected cash inflows...
Project L requires an initial outlay at t = 0 of $50,000, its expected cash inflows are $12,000 per year for 9 years, and its WACC is 12%. What is the project's discounted payback? Do not round intermediate calculations. Round your answer to two decimal places. years
Project L requires an initial outlay at t = 0 of $40,000, its expected cash inflows...
Project L requires an initial outlay at t = 0 of $40,000, its expected cash inflows are $9,000 per year for 9 years, and its WACC is 9%. What is the project's MIRR? Do not round intermediate calculations. Round your answer to two decimal places.
5. Project L requires an initial outlay at t = 0 of $25,000, its expected cash...
5. Project L requires an initial outlay at t = 0 of $25,000, its expected cash inflows are $5,000 per year for 9 years, and its WACC is 11%. What is the project's discounted payback? Do not round intermediate calculations. Round your answer to two decimal places.
Project L requires an initial outlay at t = 0 of $40,000, its expected cash inflows...
Project L requires an initial outlay at t = 0 of $40,000, its expected cash inflows are $11,000 per year for 9 years, and its WACC is 11%. What is the project's MIRR? Do not round intermediate calculations. Round your answer to two decimal places.
Project L requires an initial outlay at t = 0 of $53,000, itsexpected cash inflows...
Project L requires an initial outlay at t = 0 of $53,000, its expected cash inflows are $11,000 per year for 11 years, and its WACC is 12%. What is the project's payback? Round your answer to two decimal places.