A project is expected to provide cash flows of $12,600, $12,900, $16,000, and $10,500 over the next four years, respectively. At a required return of 8.8 percent, the project has a profitability index of .865. For this to be true, what is the project's cost at Time 0?
Please refer to below spreadsheet for calculation and answer. Cell reference also provided.