|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
ACB Manufacturing is analyzing investment decisions. Two projects are evaluated using the IRR technique. The prevailing interest rate is 12.5%. MARR is 15%. a. Calculate the IRR for each project. b. Calculate the NPV for each project. c. Which project should be selected if IRR is the deciding factor. d. Which project should be selected if NPV is the deciding factor?
Year | Project 236 | Project 264 |
0 | -64000 | -58000 |
1 | 12500 | 11589 |
2 | 12500 | 11995 |
3 | 12500 | 12414 |
4 | 12500 | 12849 |
5 | 12500 | 13299 |
6 | 12500 | 13764 |
7 | 12500 | 14246 |
8 | 12500 | 14744 |
9 | 12500 | 15260 |
10 | 12500 | 15795 |
11 | 12500 | 16347 |
12 | 12500 | 16920 |
13 | 12500 | 17512 |
14 | 12500 | 18125 |
15 | 12500 | 18759 |
NPV | 9092.126233 | 22025.5696 |
NPV Rule | Accept Project 264 | |
IRR | 17.874% | 21.728% |
IRR Rule | Accept Project 264 |
Get Answers For Free
Most questions answered within 1 hours.