You are considering the following three mutually exclusive projects. The required rate of return for all three projects is 14%.
Year A B C
0 $ (1,000) $(5,000) $(50,000)
1 $ 300 $ 1,700 $ 0
2 $300 $ 1,700 $15,000
3 $ 600 $1,700 $ 28,500
4 $300 $1,700 $ 33,000
What is the IRR of the best project? % terms to 2 decimal places w/o % sign
Using the BA 2 PLUS financial calculator we will find the IRR. Please press the following keys on your calculator-
CF
2ND CE|C
CFo = -1000
Down arrow
CO1 = 300
Down arrow (2)
CO2 = 300
Down arrow (2)
CO3 = 600
Down arrow (2)
CO4 = 300
IRR CPT
IRR = 17.49% (Project A)
Similarly IRR for project B and C will be-
IRR = 13.54% (Project B)
IRR = 14.23% (Project C)
IRR of the best project i.e. project A is 17.49%