Year A B C

0 $ (1,000) $(5,000) $(50,000)

1 $ 300 $ 1,700 $ 0

2 $300 $ 1,700 $15,000

3 $ 600 $1,700 $ 28,500

4 $300 $1,700 $ 33,000

What is the IRR of the best project? % terms to 2 decimal places w/o % sign

Homework Answers

Answer #1

Using the BA 2 PLUS financial calculator we will find the IRR. Please press the following keys on your calculator-

CF

2ND CE|C

CFo = -1000

Down arrow

CO1 = 300

Down arrow (2)

CO2 = 300

Down arrow (2)

CO3 = 600

Down arrow (2)

CO4 = 300

IRR CPT

IRR = 17.49% (Project A)

Similarly IRR for project B and C will be-

IRR = 13.54% (Project B)

IRR = 14.23% (Project C)

IRR of the best project i.e. project A is 17.49%

Do let me know in the comment section in case of any doubt.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
You are considering the following two mutually exclusive projects. The required rate of return is 12%...
You are considering the following two mutually exclusive projects. The required rate of return is 12% for project A and 11% for project B. Which project should you accept and why? Year Project A Project B 0           -$68,000   -$75,000 1                     28,000 15,000 2                     20,000   20,000 3                     20,000 20,000 4                     10,000 30,000
You are considering the following two mutually exclusive projects. The crossover rate between these two projects...
You are considering the following two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is greater than the crossover rate. Year Project A Project B 0 −$21,000 −$21,000 1 7,000 15,040 2 7,000 5,000 3 15,000 7,060 16.70%; A 12.59%; B 12.59%; A 15.61%; B 15.61%; A
You are considering the following two mutually exclusive projects. The crossover rate between these two projects...
You are considering the following two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is greater than the crossover rate. Year Project A Project B 0 −$21,000 −$21,000 1 7,000 15,040 2 7,000 5,000 3 15,000 7,060 Multiple Choice 12.59%; B 15.61%; A 15.61%; B 12.59%; A 16.70%; A
You are considering the following two mutually exclusive projects. The required return on each project is...
You are considering the following two mutually exclusive projects. The required return on each project is 16 percent. Which project should you accept and what is the best reason for that decision? Year Project A Project B 0 -$10,000 -$20,000 1 $8,000 $16,000 2 $4,000 $9,000 3 $3,000 $5,000 4 $9,000 $7,000 A. Project A; because it pays back faster B. Project A; because it has the higher internal rate of return C. Project B; because it has the higher...
Dorati Inc. is considering two mutually exclusive projects.  Dorati used a 15% required rate of return to...
Dorati Inc. is considering two mutually exclusive projects.  Dorati used a 15% required rate of return to evaluate capital expenditure projects.  If the two projects have the costs and cash flows shown below, determine the NPV for each. Year                             Project S                                   Project T    0                                -$70,000                                   -$100,000    1                                  $50,000                                      $60,000    2                                  $60,000                                      $70,000    3                                                                                    $80,000                        4                                                                                    $90,000
If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV)...
If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV) and internal rate of return (IRR) methods   agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. Year Project Y Project Z 0 –$1,500 –$1,500 1 $200 $900 2 $400 $600 3 $600 $300 4 $1,000 $200    If the weighted average cost of capital (WACC) for each project is 14%, do the NPV and...
Your company is considering two mutually exclusive projects, X and Y, whose costs and cash flows...
Your company is considering two mutually exclusive projects, X and Y, whose costs and cash flows are shown below: Year X Y 0 -$5,000 -$5,000 1 1,000 4,500 2 1,500 1,500 3 2,000 1,000 4 4,000 500 The projects are equally risky, and their cost of capital is 14%. You must make a recommendation, and you must base it on the modified IRR (MIRR). Calculate the two projects' MIRRs. Round your answers to two decimal places. Project X % Project...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as follows. The required rate of return on projects of both of their risk class is 8 percent, and the maximum allowable payback and discounted payback statistic for the projects are two and three years, respectively. Time 0 1 2 3 Project A Cashflow -20,000 10,000 30,000 1,000 Project B Cashflow -30,000 10,000 20,000 50,000 Calculate the NPV and use the NPV decision rule to...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as follows. The required rate of return on projects of both of their risk class is 10 percent, and the maximum allowable payback and discounted payback statistic for the projects are two and a half and three and a half years, respectively. Time 0 1 2 3 Project A Cash Flow ?1,000 300 400 700 Project B Cash Flow ?500 200 400 300 Use...
You have to pick between three mutually exclusive projects with the following cash flows to the...
You have to pick between three mutually exclusive projects with the following cash flows to the firm: Year Project A Project B Project C 0 -$10,000 $5,000 -$15,000 1 $8,000 $5,000 $10,000 2 $7,000 -$8,000 $10,000 The cost of capital is 12%. a. Which project would you pick using the NPV rule? b. Which project would you pick using the IRR rule? c. How would you explain the differences between the two rules? Which one would you rely on to...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT