Puckett Inc. risk-adjusts its WACC to account for project risk. It uses a risk-adjusted project cost of capital of 8% for below-average risk projects, 10% for average-risk projects, and 12% for above-average risk projects. Which of the following independent projects should Puckett accept, assuming that the company uses the NPV method when choosing projects?
|
|||
|
|||
|
|||
|
|||
|
Answer is “Project B, which has below-average risk and an IRR = 8.5%”
Company is analyzing three independent projects; therefore,
decision under NPV method and IRR method will be same.
Company should accept project whose IRR is higher than its
risk-adjusted WACC for that project.
Project A:
Risk Adjusted WACC = 10%
Internal Rate of Return = 9%
Therefore, company should reject Project A its IRR is less than WACC
Project B:
Risk Adjusted WACC = 8%
Internal Rate of Return = 8.5%
Therefore, company should accept Project B its IRR is greater than WACC
Project C:
Risk Adjusted WACC = 12%
Internal Rate of Return = 11%
Therefore, company should reject Project C its IRR is less than WACC
Get Answers For Free
Most questions answered within 1 hours.