Question

Suppose a project generates positive cash flows for the next 12 years and the project’s NPV...

Suppose a project generates positive cash flows for the next 12 years and the project’s NPV is $110,000 when discount rate is 6%. Also suppose that the IRR=8.7%. Which of the following may be a possible value for NPV when discount rate is 7.4%?

A. -$25,000

B. 0

C. $25,000

D. $125,000

E. None of the above

Homework Answers

Answer #2

Discount Rate is the rate used to find out the present value of cash flows that are expected to occur in future.The cash flows are discounted back to the present time. The discount rate used is often the WACC (weighted average cost of capital) of the company.
NPV = -C0 + C1/(1+r) + C2/(1+r)2 + ............ Cn/(1+r)n

Possible vaue of NPV when Discountig rate is 7.4% (step by step)
1. When discount rates go up, the annuity factor increases.

2. Due to increase in annuity factor, the denominator of each fraction goes up.

3. The present value of each cash flow decreases

4. The NPV will come down.

Possible value: 25,000 ( 0 and -25,000 can't be possible values because IRR > Discounting rate)  

answered by: anonymous
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The IRR of a project is 12.2%. What is the NPV of the project’s cash flows,...
The IRR of a project is 12.2%. What is the NPV of the project’s cash flows, discounted at 12.2%? Do not round intermediate calculations. Round your answer to the nearest cent
An investment project generates after-tax cash flows of $5,000 per year for the next 10 years....
An investment project generates after-tax cash flows of $5,000 per year for the next 10 years. Suppose the payback period for the project is 5 years and the appropriate discount rate is 15 percent. What is the initial cost of the project? a. $25,000 b. $32,167 c. $30,000 d. $16,761 Please provide the formula you used and numbers you plugged in to get the answer.
What is the NPV of a project if IRR < discount rate (Assuming that the first...
What is the NPV of a project if IRR < discount rate (Assuming that the first cash flow is negative and all of the cash flows from the project are positive)? < 0 > 0 = 0 None
You are evaluating an investment project and learn the following: The project’s NPV at a discount...
You are evaluating an investment project and learn the following: The project’s NPV at a discount rate of 20% is +$35,879 The project’s NPV at a discount rate of 24% is +$12,356 The project’s NPV at a discount rate of 26% is -$1,923 Based on (i)-(iii) above you know the project’s IRR must be: a) Less than 20% b) Greater than 26% c) Between 20% and 24% d) Between 24% and 26%
Suppose for a project, initial investment is $13,000. The cash flows for next 4 years are...
Suppose for a project, initial investment is $13,000. The cash flows for next 4 years are $2,000, $4,000, $6,000 and $9,000. Calculate the net present value (NPV) and IRR of this project. Should you accept the project?
Consider a project with an initial outflow at time 0 and positive cash flows in all...
Consider a project with an initial outflow at time 0 and positive cash flows in all subsequent years. As the discount rate increases, the _____________. A.  IRR remains constant while the NPV increases. B.  IRR decreases while the NPV remains constant. C.  IRR increases while the NPV remains constant. D.  IRR remains constant while the NPV decreases. E.  IRR decreases while the NPV decreases.
A capital investment project requires an initial investment of $100 and generates positive cash flows, $50...
A capital investment project requires an initial investment of $100 and generates positive cash flows, $50 and $100, at the end of the first and second years, respectively. (There is no cash flow after the second year) The firm uses a hurdle rate of 15% for projects of similar risk. Determine whether you should accept or reject the project based on NPV. Determine whether you should accept or reject the project based on IRR. Determine whether you should accept or...
When a capital budgeting project has an NPV of zero, what does this mean? The project’s...
When a capital budgeting project has an NPV of zero, what does this mean? The project’s IRR will be less than the required hurdle rate for the project The firm’s stockholders will earn a positive return, but it will be less than their required return, given the risk of the investment The firm’s stockholders will earn a negative return The firm’s security holders will earn their required rate of return, given the risk of the investment none of the above
NPV A project has annual cash flows of $7,500 for the next 10 years and then...
NPV A project has annual cash flows of $7,500 for the next 10 years and then $11,000 each year for the following 10 years. The IRR of this 20-year project is 11.71%. If the firm's WACC is 10%, what is the project's NPV? Round your answer to the nearest cent. Do not round your intermediate calculations.
NPV A project has annual cash flows of $6,000 for the next 10 years and then...
NPV A project has annual cash flows of $6,000 for the next 10 years and then $9,500 each year for the following 10 years. The IRR of this 20-year project is 12.14%. If the firm's WACC is 10%, what is the project's NPV? Round your answer to the nearest cent. Do not round your intermediate calculations
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT