Use the appropriate information provided below to estimate a weighted average cost of capital for a project with a planning life of about 10 years.
Tax rate used for future estimates = 33.0%
Current yield to maturity on company bonds = 5.78%
Current yield on US Treasury bills = 1.73%
Current yield on 10-year Treasury note = 3.76%
Total assets = $560465
Current liabilities = $77696
Long-term debt = $95098
Shareholders' equity = $385213
Estimated market risk premium = 6.94%
Current company beta = 0.87
Recent stock price = $34.78
For this problem, you must enter your answer as a PERCENT, rounded to the nearest second decimal.
Weighted average cost of capital (WACC) = Cost of debt (Kd) * Weight of debt (Wd) + Cost of equity (Ke) 8 Weight of equity (We)
Cost of debt (Kd) = Current yield to maturity on company bonds*(1-tax rate )= 5.78%*(1-0.33) = 3.8726%
Cost of equity (Ke) = Rf + beta*Market risk premium = 1.73 (T-bill rate) + 0.87*6.94% = 7.7678%
Total long term debt = 95098
Total equity = 385213
Total of debt and equity = 480,311
Weight of Equity (We) =385213/480311 = 0.8020
Weight of Debt (Wd) = 0.1980
WACC = 0.1980*3.8726 + 0.8020*7.7678 = 6.9965%
Weighted average cost of capital = 6.996% or 7.00%