National Electric Company (NEC) is considering a $45.17 million project in its power systems division. Tom Edison, the company’s chief financial officer, has evaluated the project and determined that the project’s unlevered cash flows will be $4.02 million per year in perpetuity. Mr. Edison has devised two possibilities for raising the initial investment: Issuing 10-year bonds or issuing common stock. The company’s pretax cost of debt is 7.7 percent and its cost of equity is 12.5 percent. The company’s target debt-to-value ratio is 80 percent. The project has the same risk as the company’s existing businesses and it will support the same amount of debt. The tax rate is 22 percent.
Calculate the weighted average cost of capital. (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)
Calculate the net present value of the project. (Do not round intermediate calculations and enter your answer in dollars, not millions of dollars, rounded to 2 decimal places, e.g., 1,234,567.89)
a) | Weight of Debt = 80% = 0.80 | ||||||
Weight of Equity = 1-Weight of Debt = 1-0.80 = 0.20 | |||||||
Post Tax Cost of Debt | |||||||
= Pre Tax Cost of Debt*(1-Tax Rate) | |||||||
= 7.70%*(1-22%) | |||||||
= 7.70%*0.78 | |||||||
= 6.006% | |||||||
Weighted Average Cost of Capital (WACC) | |||||||
= Weight of Debt*Post Tax Cost of Debt | |||||||
+ Weight of Equity*Cost of Equity | |||||||
= 0.80*6.006% + 0.20*12.50% | |||||||
= 4.8048% + 2.50% | |||||||
= 7.3048% | |||||||
= 7.30% | |||||||
b) | Net Present Value of Project | ||||||
= -Initial Cost + (Unlevered Cash Flow / WACC) | |||||||
= -$45,170,000 + ($4,020,000 / 7.30%) | |||||||
= -$45,170,000 + $55,068,493.15 | |||||||
= $9,898,493.15 | |||||||