Question

Question Suppose a company has project X with the following cash flows to evaluate. Calculate NPV...

Question

Suppose a company has project X with the following cash flows to evaluate.

  1. Calculate NPV and Estimate the IRR of project X using the data given at a cost of capital of 10%.                                                                           10 marks

Project Y                                                           Cash flows                   

                                                         Year                       K’000

                                                                                    

                                                            0                          (30,000)

                                                            1                                 2000

  1.        2000
  2. 150,000
  3. 140,000
  1. Examine when you will payback initial cash outflow and also apply how this helps us to implement Appraisal process.                                                 10 marks
  2. Discuss the essence of project leadership and how you would use project emotional intelligence to manage projects                                                                   10 marks

Homework Answers

Answer #1

Calculation of NPV and IRR

Year Cash Flow PV Factor @10% Present Value
0 (30,000) 1 (30,000)
1 2,000 0.909 1,818.18
2 2,000 0.826 1,652.89
3 150,000 0.751 112,697.22
4 140,000 0.683 95,621.88
NPV 181,790.17

For IRR Calculation

Year Cash Flow PV Factor @15% Present Value
0 (30,000) 1 (30,000)
1 2,000 0.870 1,739.13
2 2,000 0.756 1,512.29
3 150,000 0.658 98,627.43
4 140,000 0.572 80,045.45
NPV 151,924.30

IRR = 15% + 0.05 / ( 181,790-151,924 ) * 151924 = 40.43%

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
For the following cash flows, find the NPV and IRR for a project. Use a 12.5%...
For the following cash flows, find the NPV and IRR for a project. Use a 12.5% discount rate for the NPV. Year   Investment     Projected Cash Inflow    Projected Cash Outflow                  ($000)              ($000)                               ($000) 2015   $    18,546 2016                                  $44,550                             $52,250 2017                                  $54,256                            $54,892        2018                                  $62,025                             $58,000 2019                                  $68,000                             $61,258 2020                                  $74,555                             $66,598 2021                                  $78,562                             $71,964 2022                                  $82,365                             $77,125 2023                                  $86,879                             $83,124 2024                                  $90,125                             $88,654 2025                                  $96,526                             $92,000...
Given the following cash flows for a capital project, calculate the NPV and IRR. The required...
Given the following cash flows for a capital project, calculate the NPV and IRR. The required rate of return is 8 percent. Year 0 1 2 3 4 5 Cash Flows $-37004 $11550 $12750 $16800 $10700 $5350 NPV=4947. IRR=18.0% NPV=4947. IRR=9.9% NPV=9464. IRR=9.9% NPV=9464. IRR=18.0%
Suppose your firm is considering investing in a project with the cash flows shown as follows,...
Suppose your firm is considering investing in a project with the cash flows shown as follows, that the required rate of return on projects of this risk class is 10 percent, and that the maximum allowable payback and discounted payback statistics for the project are three and a half and four and a half years, respectively. Use the IRR decision to evaluate this project; should it be accepted or rejected? Time 0 1 2 3 4 5 6 Cash Flow...
Compute the NPV for Project X and accept or reject the project with the cash flows...
Compute the NPV for Project X and accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent. Time 0 1 2 3 4 5 Cash Flow -1000 -75 100 100 0 2000 Group of answer choices $331.44 $-639.96 $392.44 $486.29
Braun Industries is considering an investment project which has the following cash flows: Year Cash Flow...
Braun Industries is considering an investment project which has the following cash flows: Year Cash Flow 0 -$1,000 1 400 2 300 3 500 4 400 The company's WACC is 10 percent. What is the project's payback, internal rate of return, and net present value? Select one: a. Payback = 2.6, IRR = 21.22%, NPV = $300. b. Payback = 2.6, IRR = 21.22%, NPV = $260. c. Payback = 2.4, IRR = 10.00%, NPV = $600. d. Payback =...
ABC Corporation is considering a project that provides the following cash flows steam: Year 0 1...
ABC Corporation is considering a project that provides the following cash flows steam: Year 0 1 2 3 4 5 Cash flows -$1,000 $375 $425 $250 $110 $100 If WACC is 10%, what is NPV and should the company accept the project? Find IRR, MIRR, payback, and discounted payback period. Considering the following projects. Project Year 0 1 2 3 4 A Cash flows -$100 $35 $35 $35 $35 B Cash flows -$100 $60 $50 $40 $30 Project A has...
Telesis Corp is considering a project that has the following cash flows: Year Cash Flow 0...
Telesis Corp is considering a project that has the following cash flows: Year Cash Flow 0 -$1,000 1 400 2 300 3 500 4 400 The company’s weighted average cost of capital (WACC) is 10%. What are the project’s payback period (Payback), internal rate of return (IRR), net present value (NPV), and profitability index (PI)? A. Payback = 3.5, IRR = 10.22%, NPV = $1260, PI=1.26 B. Payback = 2.6, IRR = 21.22%, NPV = $349, PI=1.35 C. Payback =...
2. A project has the following cash flows             C0                    C1    &n
2. A project has the following cash flows             C0                    C1                    C2                    C3                                       ($1000)             $300                $400                $600 What is the project’s payback period? Year 0 1 2 3 Cash Flow ($1000) $300 $400 $600 Cumulative ($1000) ($700) ($300) 300 a. Calculate the projects NPV at 10%. b. Calculate the project’s PI at 10%. c. Calculate an IRR for the project in question 2 How would you answer a,b, and c in excel? I am getting...
Which of the following statements is correct? Assume the project being considered has normal cash flows,...
Which of the following statements is correct? Assume the project being considered has normal cash flows, with one outflow, followed by a series of inflows: If a project’s NPV is > 0, the IRR must be less than WACC The higher the WACC used to calculate NPV, the lower the calculated NPV will be The NPV’s of relatively risky projects should be found using relatively low WACC’s If a project’s NPV is > 0, the IRR must be less than...
4.   Suppose your firm is considering investing in a project with the cash flows shown as...
4.   Suppose your firm is considering investing in a project with the cash flows shown as follows, that the required rate of return on projects of this risk class is 8 percent, and that the maximum allowable payback and discounted payback statistic for the project are two and two and .25 years respectively. Time Years   0       1   2   3   4   5   6 Cash Flow   -150,000   30,000   50,000   45,000 25000   35000   10000       Use the payback decision rule to evaluate...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT