Question

Assume the following: Project A NPV = $5,767 IRR = 18.2% Project B NPV = $2,398...

Assume the following: Project A NPV = $5,767 IRR = 18.2% Project B NPV = $2,398 IRR = 20.3% If projects were independent, which project(s) should be selected? Group of answer choices

Select project B only

Select project A only

Both projects would be selected

Homework Answers

Answer #1

Correct Anwer: Option C ) Both projects would be selected

Reasoning:

Since both, the projects are independent in nature and not mutually exclusive, all the projects with NPV greater than zero must be accepted. A positive net present value indicates that the projected earnings generated by projects exceed the costs, also in the present dollar.

If project A and project B would have been mutually exclusive, project A would have been given a priority over project B as it has higher NPV value. Thus Option B is incorrect. Under no circumstance project, B would have been chosen making Option C incorrect.

Please give a thumbs up if you find this helpful :)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
You are considering two mutually exclusive projects. Project A has an IRR of 10% Project B...
You are considering two mutually exclusive projects. Project A has an IRR of 10% Project B has an IRR of 8% The crossover rate is 6% Which project will have the greatest NPV if the Required Return is 4% Group of answer choices Project A and B would have the same NPV There is not enough information to answer this question. Project B Project A
Project A has an IRR of 15%. Project B has an IRR of 13%. Both projects...
Project A has an IRR of 15%. Project B has an IRR of 13%. Both projects have a cost of capital of 12%. Which of the following statements would be correct? A. Both projects have a positive NPV. True or False? Explain B. Project A must have a higher NPV than Project B, True or False? Explain. C. If Project B has a higher NPV when cost of capital is 8%, then Project B must also have higher NPV if...
1) If the NPV of a project with one sign reversal is positive, then its IRR:...
1) If the NPV of a project with one sign reversal is positive, then its IRR: Select one: a. must be greater than the required rate of return b. must be less than the required rate of return c. could be greater or less than the required rate of return d. cannot be determined without actual cash flows 2) Which of the following statements is INCORRECT? Select one: a. An acceptable project should have an NPV greater than or equal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Project A Project B Project C Project D Project E Project F Project G NPV= $4,711 ($711) ($657) $334 $9,842 $7,360 ($3,224) IRR= 44.51% 5.47% 8.06% 12.98% 22.56% 17.19% 5.47% MIRR= 25.23% 7.50% 8.97% 11.57% 16.26% 13.70% 7.50% PI= 2.178 0.822 0.945 1.028 1.394 1.294 0.871 The discounting rate (r)...
Project A has an internal rate of return (IRR) of 15 percent. Project B has an...
Project A has an internal rate of return (IRR) of 15 percent. Project B has an IRR of 14 percent. Both projects have a required return of 12 percent. Which of the following statements is most correct? a. Both projects have a positive net present value (NPV). b. Project A must have a higher NPV than project B. c. If the required return were less than 12 percent, Project B would have a higher IRR than Project A. d. Project...
1. Consider the following information for projects K and W to answer the following 2 (A...
1. Consider the following information for projects K and W to answer the following 2 (A & B) questions: Project K: NPV = $1,500. IRR = 20% Project W: NPV = $2,500. IRR = 15% A) Assume Project K and Project W are independent projects with a WACC = 10%. Which of the following is true? a. Both Projects K and W should be enacted since both have a positive NPV. b. Neither Project K or W should be enacted...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Criteria:                Project_A         Project_B             Project_C         Project_D          Project_E               Project_F             Project_G NPV= $137,083 $31,290 $6,016 $7,647 ($584) $12,521 $9,214 IRR= 31.80% 48.34% 12.03% 11.30% 9.94% 26.79% 37.87% MIRR= 18.52% 23.52% 10.62% 10.59% 9.97% 23.53% 20.76% PI= 1.69 2.25 1.040 1.038 1.00 2.25 1.92 The discounting rate...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Criteria:                Project_A         Project_B             Project_C         Project_D          Project_E               Project_F             Project_G NPV= $137,083 $31,290 $6,016 $7,647 ($584) $12,521 $9,214 IRR= 31.80% 48.34% 12.03% 11.30% 9.94% 26.79% 37.87% MIRR= 18.52% 23.52% 10.62% 10.59% 9.97% 23.53% 20.76% PI= 1.69 2.25 1.040 1.038 0.999 2.25 1.92 The discounting rate...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Criteria:                Project_A         Project_B             Project_C         Project_D          Project_E               Project_F             Project_G NPV= $137,083 $31,290 $6,016 $7,647 ($584) $12,521 $9,214 IRR= 31.80% 48.34% 12.03% 11.30% 9.94% 26.79% 37.87% MIRR= 18.52% 23.52% 10.62% 10.59% 9.97% 23.53% 20.76% PI= 1.69 2.25 1.040 1.038 0.999 2.25 1.92 The discounting rate...
The IRR of project X is 18%. The IRR of project Y is 17%. The company's...
The IRR of project X is 18%. The IRR of project Y is 17%. The company's cost of capital (cost of accessing funds to finance the projects) is 10%. If projects X and Y are independent and the company has enough funds to do both, which project (s) should they chose? If they are mutually exclusive, which do you chose?
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT
Active Questions
  • Movie stars and U.S. presidents have fished Pyramid Lake. It is one of the best places...
    asked 30 minutes ago
  • what advantages do percent distributions have over frequency distributions when comparing populations at different years?
    asked 36 minutes ago
  • Richard has just been given a 6-question multiple-choice quiz in his history class. Each question has...
    asked 57 minutes ago
  • Write about westernized elements in life; westernization in our life, and this includes Americanization.
    asked 1 hour ago
  • The college Physical Education Department offered an Advanced First Aid course last summer. The scores on...
    asked 1 hour ago
  • Researchers hypothesized that increasing a woman's level of arousal would increase her perceptions of attractiveness of...
    asked 2 hours ago
  • Equation 37-14b in the textbook gives the energy emitted by Hydrogen when electrons transition between states...
    asked 2 hours ago
  • Theory of Computation Please provide explanation too on how it works a. Give an NFA recognizing...
    asked 2 hours ago
  • Question 1 A sequential pattern detection circuit (state machine) has input A and output Y, which...
    asked 2 hours ago
  • Natural Foods Inc. is planning to invest in new manufacturing equipment to make a new garden...
    asked 2 hours ago
  • Explain why a callable bond's price would be expected to decline less than an otherwise comparable...
    asked 3 hours ago
  • . What are the three types of pricing strategies services that services employ? Using a real...
    asked 3 hours ago