You've estimated the following cash flows (in $) for two projects:
Year | Project A | Project B |
0 | -5,100 | -7,650 |
1 | 1,325 | 1,325 |
2 | 2,148 | 2,148 |
3 | 3,444 | 6,967 |
The required return for both projects is 8%.
What is the NPV for project A?
What is the NPV for project B?
Which project seems better according to the NPV method?
Project A or Project B