Suppose your firm is considering investing in a project with the cash flows shown as follows, that the required rate of return on projects of this risk class is 10 percent, and that the maximum allowable payback and discounted payback statistics for the project are three and a half and four and a half years, respectively. Use the IRR decision to evaluate this project; should it be accepted or rejected?
Time | 0 | 1 | 2 | 3 | 4 | 5 | 6 |
Cash Flow | -85000 | 12000 | 11000 | 13000 | 21000 | 31000 | 32000 |
A: IRR = 16.92 percent, accept the project
B: IRR = 7.123 percent, reject the project
C: IRR = 8.81 percent, reject the project
D: IRR = 10.59 percent, accept the project
First we will calculate Npv of project at 8% discount rate
Npv is present value of cash flows less initial investment
P.v of cash flows is
12000/(1.08) + 11000/(1.08)^2 + 13000/(1.08)^3 + 21000/(1.08)^4 +31000/(1.08)^5+32000/1.08)^6 = 87560
Less initial investment is 85000
Npv is 2560
Now Npv at 10% rate is
=12000/(1.1)+11000/(1.1)^2+13000/(1.1)^3+21000/(1.1)^4+31000/(1.1)^5+32000/1.1^6 -85000
= -3578
Now IRR shall be calculated by using interpolation method
Formula is
Lower rate +[ NPV at lower rate / (NPV at lower rate - NPV at higher rate)] * ( Higher rate - Lowe rate)
= 8% +(2560)×(10-8)/(2560-(-3578)
IRR is 8.81%
As IRR is less than expected return project shall be rejected
So correct answer is C
Get Answers For Free
Most questions answered within 1 hours.