Question

You are analyzing a project and have developed the following estimates. The depreciation is $19,800 a...

You are analyzing a project and have developed the following estimates. The depreciation is $19,800 a year and the tax rate is 34 percent. What is the best case operating cash flow?
                                           Base Case                       Lower Bound                        Upper Bound

Unit Sales                             4,400                                 3,800                                     4,500

Sales Price                            $62                                      $59                                       $65

Variable Costs per Unit          $47                                      $44                                       $50

Fixed Costs                        $23,000                                $21,500                               $24,500   

Homework Answers

Answer #1

Please give thumbs up. It will help me.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ABC Co. is analyzing a proposed project with anticipated sales of 12,000 units, give or take...
ABC Co. is analyzing a proposed project with anticipated sales of 12,000 units, give or take 4 percent. The expected variable cost per unit is $7 and the expected fixed cost is $36,000. The cost estimates have a range of plus or minus 6 percent. The depreciation expense is $29,600. The tax rate is 34 percent. The sale price is estimated at $14.99 a unit, give or take 1 percent. What is the operating cash flow under the best-case scenario?...
A project under consideration costs $200,000, has a five-year life and has no salvage value. Depreciation...
A project under consideration costs $200,000, has a five-year life and has no salvage value. Depreciation is straight-line to zero. The firm has made the following projections related to this project: Base Case Lower Bound Upper Bound Unit Sales 2,000 1,800 2,200 Price Per Unit $400 $360 $440 Variable Cost Per Unit $200 $180 $220 Fixed Costs $300,000 $270,000 $330,000 The required return is 15 percent and the tax rate is 21 percent. No additional investment in net working capital...
Sloan Transmissions, Inc., has the following estimates for its new gear assembly project: price = $3,100...
Sloan Transmissions, Inc., has the following estimates for its new gear assembly project: price = $3,100 per unit; variable costs = $620 per unit; fixed costs = $4.4 million; quantity = 92,000 units. Suppose the company believes all of its estimates are accurate only to within ±15 percent. What values should the company use for the four variables given here when it performs its best-case scenario analysis? What about the worst-case scenario?    Scenario Units Sales Unit Price Unit Variable...
Sloan Transmissions, Inc., has the following estimates for its new gear assembly project: price = $3,100...
Sloan Transmissions, Inc., has the following estimates for its new gear assembly project: price = $3,100 per unit; variable costs = $620 per unit; fixed costs = $4.4 million; quantity = 92,000 units. Suppose the company believes all of its estimates are accurate only to within ±15 percent. What values should the company use for the four variables given here when it performs its best-case scenario analysis? What about the worst-case scenario? Complete the table below.    Scenarios Unit Sales...
Sloan Transmissions, Inc., has the following estimates for its new gear assembly project: price = $1,200...
Sloan Transmissions, Inc., has the following estimates for its new gear assembly project: price = $1,200 per unit; variable costs = $240 per unit; fixed costs = $2.6 million; quantity = 70,000 units. Suppose the company believes all of its estimates are accurate only to within ±10 percent. What values should the company use for the four variables given here when it performs its best-case scenario analysis? What about the worst-case scenario? Scenario Units Sales Unit Price Unit Variable cost...
Whitewater Transmissions, Inc., has the following estimates for its new gear assembly project: price = $2,020...
Whitewater Transmissions, Inc., has the following estimates for its new gear assembly project: price = $2,020 per unit; variable costs = $800 per unit; fixed costs = $5.7 million; quantity = 111,000 units. Suppose the company believes all of its estimates are accurate only to within ±15%. What values should the company use for the four variables given here when it performs its best-case scenario analysis? What about the worst-case scenario? (Enter the answers in dollars, not millions of dollars,...
Whitewater Transmissions, Inc., has the following estimates for its new gear assembly project: price = $1,720...
Whitewater Transmissions, Inc., has the following estimates for its new gear assembly project: price = $1,720 per unit; variable costs = $500 per unit; fixed costs = $4.2 million; quantity = 96,000 units. Suppose the company believes all of its estimates are accurate only to within ±15%. What values should the company use for the four variables given here when it performs its best-case scenario analysis? What about the worst-case scenario? (Enter the answers in dollars, not millions of dollars,...
Precise Machinery is analyzing a proposed project. The company expects to sell 2,100 units, give or...
Precise Machinery is analyzing a proposed project. The company expects to sell 2,100 units, give or take 5 percent. The expected variable cost per unit is $260 and the expected fixed costs are $589,000. Cost estimates are considered accurate within a plus or minus 4 percent range. The depreciation expense is $129,000. The sales price is estimated at $750 per unit, give or take 2 percent. What is the amount of the total costs per unit under the best case...
λambda Corp. is analyzing a project which has the following estimates: Sales price per unit: $63...
λambda Corp. is analyzing a project which has the following estimates: Sales price per unit: $63 Variable costs per unit: $31.50 Fixed costs: $7,300; Required return: 13% Initial investment: $12,000, with no salvage value Depreciation method: Straight-line Project life: five years. λambda Corp. is a non-profit organization and is not subject to income taxes.       What sales quantity will result in an NPV of zero?
Desai Industries is analyzing an average-risk project, and the following data have been developed. Unit sales...
Desai Industries is analyzing an average-risk project, and the following data have been developed. Unit sales will be constant, but the sales price should increase with inflation. Fixed costs will also be constant, but variable costs should rise with inflation. The project should last for 3 years. Under the new tax law, the equipment used in the project is eligible for 100% bonus depreciation, so it will be fully depreciated at t = 0. At the end of the project’s...