Question

Assume the following additional values: Price of selling regulation services to PJM is $35/MWh Capacity sold...

Assume the following additional values:

Price of selling regulation services to PJM is $35/MWh

Capacity sold for regulation is 1 MW (1 MW up or 1 MW down).

Battery can operate 23 hours per day, 365 days per year, for 10 years.

(a) What is the revenue in one year from this way of using the battery? Show your work.

(b) Create a vector to hold 10 years of the annual revenue in nominal dollars.   Use pvvar() to calculate the present value of this stream of revenues at a discount rate of 8%.

(c) Subtract the capital cost from the present value of revenue to get the NPV for Project B. What is the NPV of this project? Is it profitable?

(d) Would the project be profitable at a discount rate of 10%? What is the NPV?

(e) Would the project be profitable at a discount rate of 6%? What is the NPV?

Homework Answers

Answer #1

a. Total revenue for 1 year = 23*365*$35/MWh = $293,825

b. Present value of the annual stream of cash flow of $298,825 for 10 years is calculated using the PV of an annuity formula as in:

PV =P*(1-(1+r)^-n)/r

We have P = 293,825 from previous part and r = 0.08

PV = 293,825*(1-(1+ 0.08)^-10)/0.08

PV = $1,971,589.67

The present value of this stream of revenues at a discount rate of 8% =$1,971,589.67

Note: We have solved (a) and (b). Parts(c),(d) and (e) cannot be solved since we do not know the capital cost. Please provide the full question to answer all parts

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
You are considering the following project. What is the NPV of the project? Project life: 3...
You are considering the following project. What is the NPV of the project? Project life: 3 years Equipment:      Cost: $18,000      Economic life: 3 years      Salvage value: $4,000 Initial investment in net working capital: $2,000 Revenue: $13,000 in year 1, with a nominal growth rate of 5% per year Fixed cost: $3,000 in year 1 Variable cost: 30% of revenue Corporate tax rate (T): 40% WACC for the project: 10% This project does not create incidental effect.
A project has the following projected cash flows Year 0- R280,000( investment) Year 1 R70,000 Year...
A project has the following projected cash flows Year 0- R280,000( investment) Year 1 R70,000 Year 2 R100,000 Year 3 R130,000 a) Assuming a discount rate of 10% what is the Net Present Value (NPV) of this project over the 3 year period? b) Based on your answer above, should the project be recommended for acceptance? c) would your answer to b above change if the discount rate was 5%? Why? d) what do you understand by the term nominal...
1. Assume per visitors benefits will accrue in increments of RM 100 at the end of...
1. Assume per visitors benefits will accrue in increments of RM 100 at the end of each of the next TWO years. Find the present value of benefits (PVB) in nominal terms for each VISITOR, assuming an annual inflation rate of 5% and a nominal annual discount rate of 10%. 2. Assume per visitors benefits will accrue in increments of RM 100 at the end of each of the next TWO years. Find the present value of benefits (PVB) in...
. Calculate the IRR and NPV for the following cash flows. Assume a 15% discount rate...
. Calculate the IRR and NPV for the following cash flows. Assume a 15% discount rate Year Project 1 Cash flow Project 2 Cash flow 0 -$20,000 -$20,000 1 1,000 12,000 2 3,000 15,000 3 4,000 3,000 4 12,000 4,000 5 15,000 1,000 9. If your tenant pays you rent of $24,000 a year for 10 years, what is the present value of the series of payments discounted at 10% annually? 10. You are going to invest $300,000 in a...
The following assignment deals with the construction of a 500 MW offshore wind farm. Following the...
The following assignment deals with the construction of a 500 MW offshore wind farm. Following the decision to construct the wind farm, it will take 4 years for the design, construction, purchase, production and construction of the turbines until they can go into operation. The time when the turbines begin operation is referred to as time 0, and the costs for the previous 4 years have been: year -4: 200 million DKK year -3: 500 million DKK year -2: 1,500...
You are considering the following project. What is the NPV of the project? Project life: 3...
You are considering the following project. What is the NPV of the project? Project life: 3 years Equipment:      Cost: $18,000      Economic life: 3 years      Salvage value: $4,000 Initial investment in net working capital: $2,000 Revenue: $13,000 in year 1, with a nominal growth rate of 5% per year Fixed cost: $3,000 in year 1 Variable cost: 30% of revenue Corporate tax rate (T): 40% WACC for the project: 10% This project does not create incidental effect. Select...
A capital project requires an initial capacity of outlay of 2,000,000 and will return the following...
A capital project requires an initial capacity of outlay of 2,000,000 and will return the following amounts (paid at the end of the 5 years) 600,000, 500,000, 250,000, 150,000, 75,000 solve for each, assume that cost of the capital 10% per year, solve for a) payback b) net present value c)internal rate of return d)present value index please explain profitable or not or any other key elements
Each of the following scenarios is independent. Assume that all cash flows are after-tax cash flows....
Each of the following scenarios is independent. Assume that all cash flows are after-tax cash flows. Campbell Manufacturing is considering the purchase of a new welding system. The cash benefits will be $480,000 per year. The system costs $2,250,000 and will last 10 years. Evee Cardenas is interested in investing in a women's specialty shop. The cost of the investment is $280,000. She estimates that the return from owning her own shop will be $50,000 per year. She estimates that...
1/ A retrofit project is estimated to cost $150,000. The energy savings are expected to last...
1/ A retrofit project is estimated to cost $150,000. The energy savings are expected to last 25 years, but will need a minor upgrade of $10,000 at year 15. The retrofit is expected to save 100 MWh per year. Assuming a discount rate of 6%, and an electricity cost of $0.12/kWh: a/ What is the net-present value of the system ? b/ What is the equivalent cost of the saved energy?
Assume a project will cost $10,000. Expected Cash Flows to be received are $2,000 per year...
Assume a project will cost $10,000. Expected Cash Flows to be received are $2,000 per year at end of years 1 & 2, then $4,000 per year at end of years 3 & 4 and $5,000 at the end of year 5. No cash flows beyond year 5. Discount rate is 10%. What is the NPV (value created)?
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT