Question

A project that provides annual cash flows of $2,700 for nine years costs $8,800 today. Requirement...

A project that provides annual cash flows of $2,700 for nine years costs $8,800 today.


Requirement 1:

At a required return of 9 percent, what is the NPV of the project? (Do not round intermediate calculations. Round your answer to 2 decimal places (e.g., 32.16).)


  NPV   $   


Requirement 2:

At a required return of 28 percent, what is the NPV of the project? Use the IRR function. (Do not round intermediate calculations. A negative amount should be indicated by a minus sign. Round your answer to 2 decimal places (e.g., 32.16).)


  NPV   $   


Requirement 3:

At what discount rate would you be indifferent between accepting the project and rejecting it? (Do not round intermediate calculations. Enter your answer as a percentage rounded to 2 decimal places (e.g., 32.16).)


  Discount rate %

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A project that provides annual cash flows of $11,700 for nine years costs $63,000 today. What...
A project that provides annual cash flows of $11,700 for nine years costs $63,000 today. What is the NPV for the project if the required return is 8 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) At a required return of 8 percent, should the firm accept this project? Accept Reject What is the NPV for the project if the required return is 20 percent? (A negative answer should be indicated by...
A project that provides annual cash flows of $17,300 for nine years costs $79,000 today. THREE...
A project that provides annual cash flows of $17,300 for nine years costs $79,000 today. THREE QUESTIONS: What is the NPV for the project if the required return is 8 percent What is the NPV for the project if the required return is 20 percent At what discount rate would you be indifferent between accepting the project and rejecting it ?
Suppose you are offered $8,800 today but must make the following payments:    Year Cash Flows...
Suppose you are offered $8,800 today but must make the following payments:    Year Cash Flows ($) 0 $ 8,800          1 −4,800          2 −3,500          3 −2,600          4 −1,400             a. What is the IRR of this offer? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)      IRR %   b. If the appropriate discount rate is 13 percent, should you accept this offer? Reject Accept c....
A project that provides annual cash flows of $18,100 for eight years costs $87,000 today. What...
A project that provides annual cash flows of $18,100 for eight years costs $87,000 today. What is the NPV for the project if the required return is 7 percent? What is the NPV for the project if the required return is 19 percent? At what discount rate would you be indifferent between accepting the project and rejecting it?
A project has the following cash flows: Year Cash Flow 0 $ 72,500 1 –51,500 2...
A project has the following cash flows: Year Cash Flow 0 $ 72,500 1 –51,500 2 –28,000 What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) Internal rate of return             % What is the NPV of this project if the required return is 6 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your...
An investment project costs $10,000 and has annual cash flows of $2,910 for six years.   ...
An investment project costs $10,000 and has annual cash flows of $2,910 for six years.    a. What is the discounted payback period if the discount rate is 0 percent? (Enter 0 if the project never pays back on a discounted payback basis. Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) b. What is the discounted payback period if the discount rate is 6 percent? (Enter 0 if the project never pays back...
Hello, I am having trouble with this question. I am using the HP 10bii+ calculator. A...
Hello, I am having trouble with this question. I am using the HP 10bii+ calculator. A step by step instructions on using the calculator, not excel, will help me the most. I know the answer, just not how to enter it into the calculator to get the correct answer, i keep getting it wrong. Thank you! A project that provides annual cash flows of $17,100 for nine years costs $77,000 today.    What is the NPV for the project if...
An investment project costs $10,000 and has annual cash flows of $3,000 for six years. What...
An investment project costs $10,000 and has annual cash flows of $3,000 for six years. What is the discounted payback period if the discount rate is zero percent? (Do not round intermediate calculations. Enter 0 if the project never pays back. Round your answer to 2 decimal places, e.g., 32.16.) Discounted payback period             years What is the discounted payback period if the discount rate is 6 percent? (Do not round intermediate calculations. Enter 0 if the project never pays...
For the given cash flows, suppose the firm uses the NPV decision rule. Year Cash Flow...
For the given cash flows, suppose the firm uses the NPV decision rule. Year Cash Flow 0 –$ 153,000 1 87,000 2 76,000 3 46,000 Requirement 1: At a required return of 9 percent, what is the NPV of the project? (Do not round intermediate calculations. Round your answer to 2 decimal places (e.g., 32.16).) NPV $ Requirement 2: At a required return of 21 percent, what is the NPV of the project? (Do not round intermediate calculations. Negative amount...
For the given cash flows, suppose the firm uses the NPV decision rule. Year Cash Flow...
For the given cash flows, suppose the firm uses the NPV decision rule. Year Cash Flow 0 –$ 153,000       1 78,000       2 67,000       3 49,000       Requirement 1: At a required return of 9 percent, what is the NPV of the project? (Do not round intermediate calculations. Round your answer to 2 decimal places (e.g., 32.16).)   NPV   $ Requirement 2: At a required return of 21 percent, what is the NPV of the project? (Do not round intermediate calculations. Negative...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT