Question

Compute the PI statistic for Project X with the cash flows shown below if the appropriate...

Compute the PI statistic for Project X with the cash flows shown below if the appropriate cost of capital is 10 percent.

Time    0 1 2 3 4

Cash Flow -$10,000 $3,500 $2,000 -$5,148 $6,000

A. 1.11

B. 0.42

C. 1.19

D. 1.25

Homework Answers

Answer #1

Given about project X

current cost C0 = $10000

cost of capital r = 10%

expected future cash flow are as follow:

CF1 = $3500

CF2 = $2000

CF3 = -$5148

CF4 = $6000

So, PV of the future cash flow using compounding formula is

PV = CF1/(1+r) + CF2/(1+r)^2 + CF3/(1+r)^3 + CF4/(1+r)^4

=> PV = 3500/1.1 + 2000/1.1^2 - 5148/1.1^3 + 6000/1.1^4 = $5065.02

So, profitability index of the project is PV/C0 = 5065.02/10000 = 0.51

Given the data, profitability index of the project is 0.51

There is some problem with option available. Calculation and methods are explained properly above.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 11 percent.   Time: 0 1 2 3 4 5   Cash flow: -83 -83 0 108 83 58   rev: 11_25_2016_QC_CS-70617 Multiple Choice 25.71, accept 9.27, reject 11.00, reject 1.11, accept
Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent. Time 0 1 2 3 4 5 Cash Flow -250 75 0 100 75 50
6. Compute the NPV for Project X with the cash flows shown below if the appropriate...
6. Compute the NPV for Project X with the cash flows shown below if the appropriate cost of capital is 8 percent.   Time: 0 1 2 3 4 5   Cash flow: -160 -160 0 270 245 220 $196.48 $218.52 $236.00 $544.15
Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 11 percent. Time: 0 1 2 3 4 5 Cash flow: -78 -78 0 113 88 63 51.00%, accept 29.71%, accept 38.09%, accept 11.00%, reject
Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 6 percent.   Time: 0 1 2 3 4 5   Cash flow: -79 -79 0 104 79 54 answers to choose from: 60.45, accept 6.00, reject 34.64, accept 1.44, accept
Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 8 percent.   Time: 0 1 2 3 4 5   Cash flow: -82 -82 0 117 92 67 rev: 05_08_2019_QC_CS-167988 Multiple Choice 67.62, accept 1.59, accept 48.17, accept 8.00, reject
Compute the PI statistic for Project Z if the appropriate cost of capital is 6 percent....
Compute the PI statistic for Project Z if the appropriate cost of capital is 6 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Z Time: 0 1 2 3 4 5 Cash flow: −$1,200 $390 $520 $690 $340 $140 PI=?
Compute the PI statistic for Project Q if the appropriate cost of capital is 11 percent....
Compute the PI statistic for Project Q if the appropriate cost of capital is 11 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.)      Project Q   Time: 0 1 2 3 4   Cash flow –$12,300 $4,000 $4,830 $2,170 $2,800      PI       Should the project be accepted or rejected? Accepted Rejected
Compute the NPV for Project X and accept or reject the project with the cash flows...
Compute the NPV for Project X and accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent. Time 0 1 2 3 4 5 Cash Flow -1000 -75 100 100 0 2000 Group of answer choices $331.44 $-639.96 $392.44 $486.29
Compute the PI statistic for Project Z if the appropriate cost of capital is 6 percent....
Compute the PI statistic for Project Z if the appropriate cost of capital is 6 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Z Time: 0 1 2 3 4 5 Cash flow –$3,100 $690 $820 $990 $640 $440
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT