Question

Assume CAPM holds and you have the following information regarding three investment opportunities: Project 1 has...

Assume CAPM holds and you have the following information regarding three investment opportunities:

Project 1 has a project beta of 2.0 and you have estimated that the project’s NPV using a cost of capital of 20% equals zero. Project 2 has a project beta of 1.5 and its NPV using a cost of capital of 10% equals zero. Lastly, project 3 has a project beta of 1.0 and its NPV equals zero using a cost of capital of 6%. None of these projects are ‘scale-enhancing’ for the firm, i.e. they are different than the regular operations the firm currently maintains. As the head of the capital budgeting department you are trying to decide which projects should be accepted. The company has a levered equity beta of 0.8 and a debt-to-equity ratio of 0.5, which the company is planning to maintain for the foreseeable future. The company currently faces a 40% tax rate. Given that the expected return on the market portfolio is 8% and the risk-free rate is 3%, which projects would you accept and why? (Assume there is no capital rationing and the projects are going to be financed with 100% equity.)

I am not sure how to use Company Beta and D/E ratio in solving this question

Homework Answers

Answer #1

We have been given the levered beta, we have to calculate the unlevered beta using Hamada equation since its 100% equity

BL = BU [1 + (1-T)*D/E]

0.8 = BU * [ 1+(1-0.4)*0.5]

BU = 0.8/1.3

BU = 0.6153

Unlevered beta = 0.6153

Now, using the CAPM , Expected retun = Rf + unlevered beta*(Rm - Rf) = 3% + 0.6153*(8-3) = 6.0765%

The expceted rate of return for the company is 6.0765% and unlevered beta is 0.6153

All the three projects have a beta greater than the unlevered beta, hence they are all risky. Now, we have to accept projects which have an IRR greater than 6.0765%. Hence it would be best to choose Projects 1 and 2 since IRR for project 1 is 20% and that of project 2 is 10% (both hgiher than the return expected of 6.07%).

We cannot select project C since its return is lower than the expected return

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Assume CAPM holds and you have the following information regarding three investment opportunities: Project 1 has...
Assume CAPM holds and you have the following information regarding three investment opportunities: Project 1 has a project beta of 2.0 and you have estimated that the project’s NPV using a cost of capital of 20% equals zero. Project 2 has a project beta of 1.5 and its NPV using a cost of capital of 10% equals zero. Project 3 has a project beta of 1.0 and its NPV equals zero using a cost of capital of 6%. None of...
A company is considering the following investment opportunities: Project A Initial cost = $5,500,000 Expected life...
A company is considering the following investment opportunities: Project A Initial cost = $5,500,000 Expected life = 10 yrs NPV = $340,000 IRR = 20% Project B Initial cost = $3,000,000 Expected life = 10 yrs NPV = $300,000 IRR = 30% Project C Initial cost = $2,000,000 Expected life = 10 yrs NPV = $200,000 IRR = 40% If the company has a WACC of 15% and the company is using capital rationing with a fixed capital budget of...
Suppose you are a financial manager and you have the following investment opportunities: Project Investment (in...
Suppose you are a financial manager and you have the following investment opportunities: Project Investment (in $1,000) NPV (in $1,000) 1 500 100 2 200 -4 3 125 -7 4 50 50 5 250 60 Which of the following projects should you pursue if you have only $700,000 allocated for capital expenditures? How much does the budget limit cost the company in terms of forgone NPV? The opportunity cost of capital for each project is 15%.
8. An all-equity firm is considering financing its next investment project with a combination of equity...
8. An all-equity firm is considering financing its next investment project with a combination of equity and debt. The asset beta for the firm as a whole is 1.2 (recall that this is the same as the equity beta for an all-equity firm, but not the same as the equity beta for a “levered” firm). Assume the average rate of return on the market is 6% and the risk-free rate is 1%. The cost of debt for the company is...
If you assume that a project being considered has normal cash flows, with one outflow followed...
If you assume that a project being considered has normal cash flows, with one outflow followed by a series of inflows, which statement would be correct? Question 11 options: a) The lower the cost of capital used to calculate a project's NPV, the lower the calculated NPV will be. b) If a project's NPV is less than zero, then its IRR must be less than the cost of capital. c) A project’s NPV is found by compounding the cash inflows...
Which of the following statements is correct? Assume the project being considered has normal cash flows,...
Which of the following statements is correct? Assume the project being considered has normal cash flows, with one outflow, followed by a series of inflows: If a project’s NPV is > 0, the IRR must be less than WACC The higher the WACC used to calculate NPV, the lower the calculated NPV will be The NPV’s of relatively risky projects should be found using relatively low WACC’s If a project’s NPV is > 0, the IRR must be less than...
Using the Modigliani-Miller (MM) theory in a perfect market, you want to evaluate a project and...
Using the Modigliani-Miller (MM) theory in a perfect market, you want to evaluate a project and how to finance it. The project has free cash flows in one year (year 1) of $90 in a weak economy or $120 in a strong economy. There is 75% chance that the economy is strong. The initial investment required for the project is $80, and the project's cost of capital is 10%. The risk free interest rate is 5%. Suppose that to raise...
Your firm is planning to invest in an automated packaging plant. Harburtin Industries is an​ all-equity...
Your firm is planning to invest in an automated packaging plant. Harburtin Industries is an​ all-equity firm that specializes in this business. Suppose​ Harburtin's equity beta is 0.83​, the​ risk-free rate is 3%, and the market risk premium is 5% a. If your​ firm's project is​ all-equity financed, estimate its cost of capital. After computing the​ project's cost of capital you decided to look for other comparables to reduce estimation error in your cost of capital estimate. You find a...
Which of the following statements is CORRECT? Assume that the project being considered has normal cash...
Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. a. The NPVs of relatively risky projects should be found using relatively low costs of capital. b. If a project's NPV is greater than zero, then its IRR must be less than the cost of capital. c. The higher the cost of capital used to calculate the NPV, the lower the calculated NPV will...
SA company is trying to estimate its optimal capital structure. Right now, it has a capital...
SA company is trying to estimate its optimal capital structure. Right now, it has a capital structure that consists of 20% debt and 80% equity, based on market values (its debt to equity D/S ratio is 0.25). The risk-free rate (rRF) is 6% and the market risk premium (rM – rRF) is 5%. Currently the company’s cost of equity, which is based on the CAPM, is 12% and its tax rate is 40%. Find the firm’s current leveraged beta using...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT