Question

Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year...

Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year for five years. Project Q costs $37,500 and is expected to produce cash flows of $11,100 per year for five years. Calculate each project’s (a) net present value (NPV), (b) internal rate of return (IRR), and (c) mod- ified internal rate of return (MIRR). The firm’s required rate of return is 14 percent.  Compute the (a) NPV, (b) IRR, (c) MIRR, and (d) discounted payback for the following independent capital budgeting projects. (r = 9%)

Year 0: Project T = ($8000) Project U = ($10,000)

Year 1: Project T = 2,000 Project U = 9,000

Year 2: Project T = 1,000 Project U = 5,000

Year 3: Project T = 7,000 Project U = (3,100)

Which project(s) should the company purchase? Why?

Homework Answers

Answer #1

For any investment decision to be made sound appraisal techniques should be used to maximise the shareholder's wealth. A number of such investment criteria (or capital budgeting techniques) are used to choose from various investment decision.

NPV or Net Present Value method is a classic method which recognises the time value of money and discounts the future cash flows using the opportunity cost of capital/ (required rate of return). The NPV is found out be subtracting present values of cash outflows from present value of cash inflows.

[Excel function used ‘=NPV(rate,value1,value2…..)]

IRR or Internal Rate of Return is another discounted cash flow technique which takes in account the magnitude and timing of cashflows. It gives us the rate that equates the investment outlay with the present value of cash inflows received after one period.

[Excel Function used ‘=IRR(values)]

MIRR or Modified Internal Rate of Return assumes that a company reinvests its positive cash flows at the firm's cost of capital and that the initial outlays are financed at the firm's financing cost.

[Excel Function used ‘=MIRR(values,finance_rate,reinvest_rate)

Discounted Payback Method is a method which calculates the number of periods taken in recovering the investment outlays on the present value basis.

As per the question the calculations for the Project P and Project Q are as under:

Based on the above calculation it is clear that both projects P and Q has equal time of investment and IRR. But project Q has more NPV than that of Project P. Hence the company should purchase Project Q.

As per the question the calculations for the Project T and Project U are as under:

Based on the above calculation it is clear that the company should Purchase company Project U as it has a higher Internal Rate of Return and a smaller Discounted Payback Period.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Project S costs $16,000 and is expected to produce cash flows of $5,000 per year for...
Project S costs $16,000 and is expected to produce cash flows of $5,000 per year for 6 years. What is the discounted payback period for this project if the cost of capital is 21%? A) 3.92 years B) 5.61 years C) 4.86 years D) 5.85 years What is the NPV for this project is the cost capital is 21%? A) $157.65 B) -$110.23 C) $199.36 D) $223.08 What is the NPV for this project if the cost of capital is...
You are considering a project with an initial cash outlay of $100,000 and expected free cash...
You are considering a project with an initial cash outlay of $100,000 and expected free cash flows of $23,000 at the end of each year for 6 years. The required rate of return for this project is 10 percent. a. What is the project’s payback period? b. What is the project’s discounted payback period? c. What is the project’s NPV ? d. What is the project’s PI ? e. What is the project’s IRR ? f. What is the project’s...
A project that costs $370,000 is expected to produce $250,000 (year 1) and $185,000 (year 2)....
A project that costs $370,000 is expected to produce $250,000 (year 1) and $185,000 (year 2). If the required rate of return is 12 percent, what is the project's (a) NPV, (b) IRR, and (c) MIRR?
The IRR evaluation method assumes that cash flows from the project are reinvested at a rate...
The IRR evaluation method assumes that cash flows from the project are reinvested at a rate equal to the project’s IRR. However, in reality, the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, using the modified IRR approach, you can make a more reasonable estimate of a project’s rate of return than the project’s IRR can. Consider the following situation: Cold Goose Metal Works Inc. is analyzing a project that requires an initial investment...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Blue Llama Mining Company is analyzing a project that requires an initial investment of $450,000. The project’s expected cash flows are: Year Cash...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Green Caterpillar Garden Supplies Inc. is analyzing a project that requires an initial investment of $2,500,000. The project’s expected cash flows are: Year...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Green Caterpillar Garden Supplies Inc. is analyzing a project that requires an initial investment of $400,000. The project’s expected cash flows are: Year...
Project S costs $16,000 and is expected to produce cash flows of $5,000 per year for...
Project S costs $16,000 and is expected to produce cash flows of $5,000 per year for 6 years. What is the discounted payback period for this project if the cost of capital is 21%? A) 3.92 years B) 5.61 years C) 4.86 years D) 5.85 years
11-11 CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS $225 $225 $50 $49 Project S costs $15,000, and...
11-11 CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS $225 $225 $50 $49 Project S costs $15,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $37,500, and its expected cash flows would be $11,100 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Explain
Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the...
Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Fuzzy Button Clothing Company is analyzing a project that requires an initial investment of $500,000. The project’s...