Question

How to calculate the estimated value of the company in the project part

How to calculate the estimated value of the company in the project part

Homework Answers

Answer #1

Valuation of a company is the process of determining the true worth of a company.

We can determine the value of the company by the following methods

- NAV i.e. Net Asset Value Method which is total assets - total external liability

- Market Value Added which is current value of the securities of the company - value of shareholder's fund

- Value of company using future maintainable profits

- Value of the firm by using discounted cash flow model

- Value of the company using chop shop approach

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
M11-5 Calculating Net Present Value [LO 11-3] Citrus Company is considering a project that has estimated...
M11-5 Calculating Net Present Value [LO 11-3] Citrus Company is considering a project that has estimated annual net cash flows of $39,405 for five years and is estimated to cost $185,000. Citrus’s cost of capital is 10 percent.     Determine the net present value of the project. (Future Value of $1, Present Value of $1, Future Value Annuity of $1, Present Value Annuity of $1.) (Use appropriate factor(s) from the tables provided. Negative amount should be indicated by a minus...
Your company is considering two projects and has estimated the following cash flows: Year Project A...
Your company is considering two projects and has estimated the following cash flows: Year Project A Project B 0 -15,000 -20,000 1 10,000 10,000 2 10,000 18,000 Attempt 1/1 for 10 pts. Part 1 If project B expands your manufacturing capacity by building a separate factory, what is the relevant cash flow for evaluating project B in year 2? Submit Attempt 1/1 for 10 pts. Part 2 If project B replaces an existing factory (project A), what is the relevant...
Part 1 a) Earned Value Management (EVM) is a project management technique for measuring project performance...
Part 1 a) Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original...
With an example, explain how the following factors influence the estimated cost of a project: 1....
With an example, explain how the following factors influence the estimated cost of a project: 1. Year of construction 2. Project site location 3. Size of the project
Q 1. From the following information, calculate the net present value of the two project and...
Q 1. From the following information, calculate the net present value of the two project and suggest which of the two projects should be accepted. Particulars Project X Project Y Investment 400,000 dhs 420,000 dhs Estimated Life 4 years 4 years Scrap Value 60,000 dhs 70,000 dhs The cash inflows are as follows: Project Name Year 1 Year 2 Year 3 Year 4 Project X 90,000 120,000 140,000 70,000 Project Y 80,000 148,000 98,000 60,000 Note: The following are the...
A machine that cost $400,000 has an estimated residual value of $40,000 and an estimated useful...
A machine that cost $400,000 has an estimated residual value of $40,000 and an estimated useful life of four years. The company uses double-declining-balance depreciation. Required: 1. Calculate the machine's depreciable cost. 2. Calculate the machine's depreciation expense for each year. 3. Calculate the machine's accumulated depreciation and book value at the end of each year.
A machine that cost $400,000 has an estimated residual value of $40,000 and an estimated useful...
A machine that cost $400,000 has an estimated residual value of $40,000 and an estimated useful life of four years. The company uses straight-line depreciation. Required: 1. Calculate the machine's depreciable cost. 2. Calculate the amount of depreciation expense that will be taken on the machine each year. 3. Calculate the machine's accumulated depreciation and book value at the end of each year.
EF company wishes to assess the value of its AS Devision. The AS Devision’s estimated free...
EF company wishes to assess the value of its AS Devision. The AS Devision’s estimated free cash flow for shareholders (ECF) each year 2020 through 2023 is given in the following table. Beyond 2023 to infinity, the firm expects its free cash flow to grow at 3% annually. The required ate of retyrn by shareholders is equal 12% year FCF 2020 700 000 2021 1 200 000 2022 1 100 000 2023 1 200 000 Use the ECF valuation model...
Calculate the payment and performance bond premium for a contract for a building project with an...
Calculate the payment and performance bond premium for a contract for a building project with an estimated cost of $12.5 million. Project duration is estimated at 18 months. If the project actual cost turns out to be $12.75m (same duration), what is the adjustment for the premium (how much extra should the contractor pay the surety)?
Rock Haven has a proposed project with a 9-year life that is estimated to bring in...
Rock Haven has a proposed project with a 9-year life that is estimated to bring in sales sales of 8,700 units each year at a price of $74 per unit. The variable cost is $45 per unit. The fixed assets required for the project have a cost $301,000. They will be depreciated on a straight-line basis over the life of the project with no salvage value. The project has fixed costs estimated to be $180,000 annually. The tax rate is...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT