Question

Beta    IRR Project 1        0.3      3% Project 2        0.6      7% Project 3   &nb

Beta    IRR

Project 1        0.3      3%

Project 2        0.6      7%

Project 3        0.8      11%

The expected return on the market is 10%.

The risk-free rate is 2%.

The weighted average cost of capital is 8% for all 3 projects.

Which project will be incorrectly rejected?

Homework Answers

Answer #1

Expected return of project 1= risk free rate + beta (market return - risk free rate)

= 3% + 0.3 (10% - 2%)

= 2% + 0.3 (8%)

= 2% + 2.4%

= 4.4%

As the expected return and IRR, both are less than WACC, the project is rightly rejected

Expected return of project 2= risk free rate + beta (market return - risk free rate)

= 2% + 0.6 (10% - 2%)

= 2% + 0.6 ( 8%)

= 2% + 4.8%

= 6.8%

As the expected return and IRR both are less than WACC , the project is rightly rejected.

Expected return of project 3= Risk free rate + beta (market return - risk free rate)

= 2% + 0.8 ( 10% - 2%)

= 2% + 0.8 (8%)

= 2% + 6.4%

= 8.4%

As the expected return and IRR are more than WACC , the project 3 will be rightly accepted.

Therefore none of the projects are incorrectly rejected

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
********NEED IT ASAP****** THANKS                       Beta    IRR Project 1       &nbsp
********NEED IT ASAP****** THANKS                       Beta    IRR Project 1        0.3      3% Project 2        0.6      7% Project 3        0.8      11% The expected return on the market is 10%. The risk-free rate is 2%. The weighted average cost of capital is 8% for all 3 projects. Which project will be incorrectly rejected? A. Project 1 B. Project 2 C. Project 3 D. None
An all-equity firm is considering the following projects: Project Beta IRR X .87 9.7% Y 1.13...
An all-equity firm is considering the following projects: Project Beta IRR X .87 9.7% Y 1.13 11.9% The risk-free rate is 4.2 %, and the expected return on the market is 11.2%. B. Using CAPM/SML, which projects should be accepted? Question 10 options: 12 Project Y 12 Project X 1. Reject 2. Accept
An all-equity firm is considering the following projects: Project Beta IRR A 0.75 8.4% B 0.95....
An all-equity firm is considering the following projects: Project Beta IRR A 0.75 8.4% B 0.95. 12.6% C 1.15 13.5% D 1.32 14.5% E 1.45 15.9% The T-bill rate is 3 percent, and the expected return on the market is 12 percent. a. Which projects have a higher expected return than the firm’s 13 percent cost of capital? (5 points) b. Which projects should be accepted? Why? (5 points)
Assume CAPM holds and you have the following information regarding three investment opportunities: Project 1 has...
Assume CAPM holds and you have the following information regarding three investment opportunities: Project 1 has a project beta of 2.0 and you have estimated that the project’s NPV using a cost of capital of 20% equals zero. Project 2 has a project beta of 1.5 and its NPV using a cost of capital of 10% equals zero. Project 3 has a project beta of 1.0 and its NPV equals zero using a cost of capital of 6%. None of...
Polycorp is investigating two projects. The risk-free rate is 5% pa and the market premium is...
Polycorp is investigating two projects. The risk-free rate is 5% pa and the market premium is 6%pa. Project A has a beta of .7 and Project B has beta of 1.8. The projects are independent. If accepted the projects will initially be funded by borrowing at 7%pa. The relevant net cash flows for each project are below. The firm's current weighted average cost of capital is 11% pa (before taking either or both A and B). Assume no taxes. Calculate...
An all-equity firm is considering the projects shown below. The T-bill rate is 6 percent and...
An all-equity firm is considering the projects shown below. The T-bill rate is 6 percent and the market risk premium is 6 percent. Project Expected Return Beta A 11 % 0.8    B 21 % 1.5    C 15 % 1.7    D 19 % 1.9    Calculate the project-specific benchmarks for each project. (Round your answers to 2 decimal places.) Project A %   Project B %   Project C %   Project D % If the firm uses its current WACC of...
Assume CAPM holds and you have the following information regarding three investment opportunities: Project 1 has...
Assume CAPM holds and you have the following information regarding three investment opportunities: Project 1 has a project beta of 2.0 and you have estimated that the project’s NPV using a cost of capital of 20% equals zero. Project 2 has a project beta of 1.5 and its NPV using a cost of capital of 10% equals zero. Lastly, project 3 has a project beta of 1.0 and its NPV equals zero using a cost of capital of 6%. None...
Your company has a Beta of 1.75. a) If risk-free rates are 1% and the market...
Your company has a Beta of 1.75. a) If risk-free rates are 1% and the market has an expected return of 8%, what is your company’s expected return? b) Assuming they are all equity financed, should they undertake a project with a 12% IRR? Why or why not?
As manager of ACME industries, your company is 30% debt financed, 70% equity financed. Assuming the...
As manager of ACME industries, your company is 30% debt financed, 70% equity financed. Assuming the debt is risk-free, and assuming that your equity beta is 1.1, that treasury bills yield 1%, and that the market has an expected return of 8%, what is your weighted average cost of capital assuming a 35% tax rate? Should you invest in a new project with a 10% IRR?
Puckett Inc. risk-adjusts its WACC to account for project risk. It uses a risk-adjusted project cost...
Puckett Inc. risk-adjusts its WACC to account for project risk. It uses a risk-adjusted project cost of capital of 8% for below-average risk projects, 10% for average-risk projects, and 12% for above-average risk projects. Which of the following independent projects should Puckett accept, assuming that the company uses the NPV method when choosing projects? a. Project C, which has above-average risk and an IRR = 11%. b. Without information about the projects' NPVs we cannot determine which project(s) should be...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT