Question

Consider projects A and B: Cash Flows (dollars) Projects A B C0 450,000 320,000 C1 310,000...

  1. Consider projects A and B: Cash Flows (dollars)

Projects

A

B

C0

450,000

320,000

C1

310,000

80,000

C2

120,000

100,000

C3

85,000

250,000

What is the NPV at 10% required rate? Which is the best Project?

Homework Answers

Answer #1

Given about Project A,

Initial cost C0 = $450000

Cash flow in year 1 CF1 = $310000

Cash flow in year 2 CF2 = $120000

Cash flow in year 3 CF3 = $85000

discount rate d = 10%

NPV of the project is sum of Present value of cash flows minus initial cost. NPV is calculated using formula

PV = CF1/(1+d) + CF2/(1+d)^2+ CF3/(1+d)^3 - C0

=> PV = 310000/1.10 + 120000/1.10^2 + 85000/1.10^3 - 450000 = -5146.51

Similarly, given about project B,

Initial cost C0 = $320000

Cash flow in year 1 CF1 = $80000

Cash flow in year 2 CF2 = $100000

Cash flow in year 3 CF3 = $25000

discount rate d = 10%

NPV of the project is sum of Present value of cash flows minus initial cost. NPV is calculated using formula

PV = CF1/(1+d) + CF2/(1+d)^2+ CF3/(1+d)^3 - C0

=> PV = 80000/1.10 + 100000/1.10^2 + 250000/1.10^3 - 320000 = $23200.60

Since NPV of project B is positive, this investment is better.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Consider projects A and B: Cash Flows (dollars) Projects A B C0 450,000 320,000 C1 310,000...
Consider projects A and B: Cash Flows (dollars) Projects A B C0 450,000 320,000 C1 310,000 80,000 C2 120,000 100,000 C3 85,000 250,000 What is the NPV at 10% required rate? Which is the best Project?
A project has the following forecasted cash flows: Cash Flows Thousands of dollars C0 C1 C2...
A project has the following forecasted cash flows: Cash Flows Thousands of dollars C0 C1 C2 C3 -100 40 60 50 The investor expected rate of return is 10%. The cost of capital is 12%. Required: 1.What will you choose to be the discount rate? Why? 2.Please calculate the payback period (PP) and return on investment (ROI). 3.Please calculate NPV,PVI and IRR.. 4.Make decision based on the above calculation and explain the reasons. 5.David said that the profit is the...
Here are the the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3...
Here are the the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A -21,200 9,328 9,328 9,328 B -21,200 0 0 28,620 what is the IRR of each project? (round answer to 2 decimal places)
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A...
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A −$ 22,200 +$ 9,768 +$ 9,768 +$ 9,768 B − 22,200 0 0 + 29,970 What is the IRR of each project? (Round your answers to 2 decimal places.)
2. A project has the following cash flows             C0                    C1    &n
2. A project has the following cash flows             C0                    C1                    C2                    C3                                       ($1000)             $300                $400                $600 What is the project’s payback period? Year 0 1 2 3 Cash Flow ($1000) $300 $400 $600 Cumulative ($1000) ($700) ($300) 300 a. Calculate the projects NPV at 10%. b. Calculate the project’s PI at 10%. c. Calculate an IRR for the project in question 2 How would you answer a,b, and c in excel? I am getting...
Suppose the cash flows for project are C0 = -2000; C1 = 500; C2 = 1000;...
Suppose the cash flows for project are C0 = -2000; C1 = 500; C2 = 1000; C3 = 4000, C4= 1000, C5= 500. The discounted payback period is ____________________ and profitability index is ___________________ at a discount rate of 10 percent.
Consider the following cash flows: Cash Flows ($) C0 C1 C2 −6,950 4,700 18,400 a. Calculate...
Consider the following cash flows: Cash Flows ($) C0 C1 C2 −6,950 4,700 18,400 a. Calculate the net present value of the above project for discount rates of 0, 50, and 100%. NPV @ 0% $ NPV @ 50% $ NPV @100% $ b. What is the IRR of the project? (Do not round intermediate calculations. Enter your answer as a percent rounded to the nearest whole number.) IRR %
Given the following Cash flows: C0 = - $6,750 C1 = $4,500 C2 = $18,000 Calculate...
Given the following Cash flows: C0 = - $6,750 C1 = $4,500 C2 = $18,000 Calculate the NPV of the above project for discount rates of 0%, 50%, and 100%. What is the IRR of the project?
Consider the following projects: Project C0 C1 C2 A − $ 2,850 + $ 2,750 +...
Consider the following projects: Project C0 C1 C2 A − $ 2,850 + $ 2,750 + $ 1,950 B − 2,850 + 2,190 + 1,878 a. Calculate the profitability index for A and B assuming a 22% opportunity cost of capital. Project A: Project B:
Consider the following projects: Cash Flows ($) Project C0 C1 D –10,900 21,800 E –20,900 36,575...
Consider the following projects: Cash Flows ($) Project C0 C1 D –10,900 21,800 E –20,900 36,575 Assume that the projects are mutually exclusive and that the opportunity cost of capital is 8%. a. Calculate the profitability index for each project. (Do not round intermediate calculations. Round your answers to 2 decimal places.) Project Profitability Index D E b-1. Calculate the profitability-index using the incremental cash flows. (Do not round intermediate calculations. Round your answer to 2 decimal places.) Profitability-index b-2....
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT