Question

If NPV, IRR and/or PI methods return conflicting results (one rule suggests project A is better...

If NPV, IRR and/or PI methods return conflicting results (one rule suggests project A is better the other rule suggests project B is better) your decision primarly will be based on which rule?

Homework Answers

Answer #1

Profitability index suffers from many limitations such as that it is difficult to estimate the required rate of return ands that it values short term gains better than long term gains.

The NPV and IRR approaches use different reinvestment rate assumptions so there can be a conflict in project acceptance when mutually exclusive projects are considered.

The NPV methods reinvests cash flow at the WACC and IRR methods reinvests cash flow at the IRR.

Reinvestment at WACC is the superior assumption, so when mutually exclusive projects are evaluated the NPV approach should be used for the capital budgeting decision.

Hence, the NPV method is the better rule.

In case of any query, kindly comment on the solution.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Which of the following is not one of the benefits of using NPV over IRR to...
Which of the following is not one of the benefits of using NPV over IRR to judge a capital budgeting decision? IRR assumes that cash flows generated from the capital budgeting decision can be reinvested at the same rate of return as the project itself, NPV does not. NPV can be used to judge capital budgeting decisions with nonstandard cash flows, whereas IRR cannot. Unlike for IRR, the results from an NPV analysis can be easily compared to other capital...
(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash...
(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash outlay of ​$75,000 and expected free cash flows of ​$26,000 at the end of each year for 5 years. The required rate of return for this project is 7 percent. a. What is the​ project's payback​ period? b. What is the​ project's NPV​? c. What is the​ project's PI​? d. What is the​ project's IRR​?
Which one of the following is TRUE? The NPV decision rule says to accept an investment...
Which one of the following is TRUE? The NPV decision rule says to accept an investment if the NPV is negative. The IRR decision rule states that a project should be accepted if its IRR exceeds the required return. The discount rate that causes the net present value of a project to equal zero is called the market rate. IRR is superior to NPV for choosing between different projects. Payback ignores the project's cost.
​(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash...
​(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash outlay of ​$80,000 and expected free cash flows of ​$26,000 at the end of each year for 6 years. The required rate of return for this project is 7 percent. a. What is the​ project's payback​ period? b. What is the​ project's NPV​? c. What is the​ project's PI​? d. What is the​ project's IRR​? a. The​ project's payback period is nothing years.  ​(Round...
Your firm is considering a project that has an NPV of $32,600, an IRR of 9.5...
Your firm is considering a project that has an NPV of $32,600, an IRR of 9.5 percent, and a payback period of 8.9 years. The required return is 9% and the required payback period is 9 years. Which one of the following statements correctly applies to this project? A) The net present value indicates accept while the internal rate of return indicates reject. B) The payback decision rule is sufficient in making the decision about the project. C) The payback...
When NPV and IRR rules result in a conflicting decision regarding acceptance of a project managers...
When NPV and IRR rules result in a conflicting decision regarding acceptance of a project managers could use the MIRR. It assumes reinvestment of projects' cash flows at the WACC, so it produces results consistent with NPV method. Let's try to find the MIRR for the project with the following cash flows: Initial cost of -800 at time zero, CF1 = 400, CF 2 = 570, CF3 = -130. Here we have two negative cash flows and two positive cash...
1) If the NPV of a project with one sign reversal is positive, then its IRR:...
1) If the NPV of a project with one sign reversal is positive, then its IRR: Select one: a. must be greater than the required rate of return b. must be less than the required rate of return c. could be greater or less than the required rate of return d. cannot be determined without actual cash flows 2) Which of the following statements is INCORRECT? Select one: a. An acceptable project should have an NPV greater than or equal...
6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen....
6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen. The internal rate of return (IRR) and the net present value (NPV) methods will not always choose the same project. If the crossover rate on the NPV profile is below the horizontal axis, the methods will agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. Year Project Y Project Z 0 –$1,500 –$1,500 1...
11-2: Net Present Value (NPV) 11-3: Internal Rate of Return (IRR) Problem Walk-Through IRR and NPV...
11-2: Net Present Value (NPV) 11-3: Internal Rate of Return (IRR) Problem Walk-Through IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $888.29 $250 $5 $15 Project L -$1,000 $0 $240 $420 $765.23 The company's WACC is 10.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round...
The prevailing interest rate is 8%. If the following three projects are mutually exclusive, which one...
The prevailing interest rate is 8%. If the following three projects are mutually exclusive, which one should you take? Use NPV, IRR and Profitability Index to make your decision. Do all three rules agree? Project Year 0 Year 1 Year 2 A -100 +70 +70 B -240 +120 +140 C -370 +50 +400 Select one: a. Yes they agree. Project C dominates the other two. These are there calculations Project NPV IRR PI A $      24.83 25.69% 1.25 B $     ...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT