Question

A project to build a new taxiway at Culpepper Airport is 5 days behind at day...

A project to build a new taxiway at Culpepper Airport is 5 days behind at day 65. It had a planned cost of $735,000 for this point in time, but the actual cost is only $550,000. Estimate the variances and what do they say about the health of the project? Re-estimate if the actual cost to date had been $750,000.

Homework Answers

Answer #1

Planned Value for 65 day time = $735000

Actual Cost incurred = $550000

Earned Value = Budgeted cost per day * Work days completed

Earned Value = 735000/65*60 = $678461 (rounded off to nearest dollar)

Cost Variance = Earned Value - Actual cost

Cost Variance = $678461 - $550000 = $128461

Schedule Variance = Earned Value - Planned Value

Schedule Variance = $678461 - $735000 = -$56539

Since the cost variance of the project is positive, this means the project is within the budget and sine the schedule variance is negative, this means the project is behind schedule.

If the actual cost incurred is $750000. then,

No change in schedule variance. But cost variance will change which are as follow:

Cost Variance = $678461 - $750000 = -$71539

Now negative cost variance shows the project is over-budget.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A project to build a new bridge seems to be going very well since the project...
A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 65% complete. The planners were only expecting to be 55% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that...
Your project to obtain charitable donations is now 48 days into a planned 58-day project. The...
Your project to obtain charitable donations is now 48 days into a planned 58-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 44 days of the project and to bring in $24,600. Even though we are 48 days into the project, we still see that we have only 90% of this activity complete. The second activity relates to company donations and is scheduled to...
In 2017, Chicago Construction began work on a three-year construction project to build a new performing...
In 2017, Chicago Construction began work on a three-year construction project to build a new performing arts complex (the "PAC"). Chicago uses the percentage-of-completion method of accounting. At the end of 2017, the company completed 25% of the project. The following financial statement information indicates the results to date for the PAC at the end of 2017: Actual Cost incurred in 2017                                                                                                                                                              $35 million Construction in progress (as of 12/31/2017)                                                                                                   $50 million Accounts Receivable from construction billings (as of...
Suppose your company needs $24 million to build a new assembly line. Your target debt?equity ratio...
Suppose your company needs $24 million to build a new assembly line. Your target debt?equity ratio is .60. The flotation cost for new equity is 7 percent, but the flotation cost for debt is only 3 percent. Your boss has decided to fund the project by borrowing money because the flotation costs are lower and the needed funds are relatively small. What do you think about the rationale behind borrowing the entire amount? What is your company’s weighted average flotation...
Calculating Flotation Costs Suppose your company needs $24 million to build a new assembly line. Your...
Calculating Flotation Costs Suppose your company needs $24 million to build a new assembly line. Your target debt?equity ratio is .60. The flotation cost for new equity is 7 percent, but the flotation cost for debt is only 3 percent. Your boss has decided to fund the project by borrowing money because the flotation costs are lower and the needed funds are relatively small. a. What do you think about the rationale behind borrowing the entire amount? b. What is...
Revenue Recognition In 2017, Chicago Construction began work on a three-year construction project to build a...
Revenue Recognition In 2017, Chicago Construction began work on a three-year construction project to build a new performing arts complex (the "PAC"). Chicago uses the percentage-of-completion method of accounting. At the end of 2017, the company completed 25% of the project. The following financial statement information indicates the results to date for the PAC at the end of 2017: Actual Cost incurred in 2017     $35 million Construction in progress (as of 12/31/2017)                                                                                                    $50 million Accounts Receivable from construction billings (as...
Ralph wants to build a new two (2) car garage. The contractor Ralph hired provided the...
Ralph wants to build a new two (2) car garage. The contractor Ralph hired provided the following schedule and cost estimate. What is the budget at completion (BAC) for Ralph’s garage? At the end of week 1, the contractor completed 80% of the footing, framing, and siding. He spent 3,000 on concrete, lumber and vinyl siding. He also paid 1,500 in wages to laborers to complete the footing, framing, and siding. what is the earned value (EV) for Task A...
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's...
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's the end of week two on this three week project. The actual cost is $72,000. They have 7 minutes of usable film. The budgeted total cost is $100,000. Determine PV,EV,CV,CPI,SV, ans SPI a. First, map each description to an EVA category. Then, fill in the table. Week AC PV EV CV CPI SV SPI 2 72,000 b. What do the SPI and CPI values...
1. ‘We have to get this new product and fast’, said the Operations Director. ‘Our competitors...
1. ‘We have to get this new product and fast’, said the Operations Director. ‘Our competitors are close behind us and I believe their products will be almost as good as ours when they launch them’. She was talking about a new product that the company hoped would establish them as the leader in the market. The company had put together a special development team together with their own development laboratory. They had spent £10,000 on equipping the laboratory and...
Case Study 1: A Day in the Life Rachel, the project manager of a large information...
Case Study 1: A Day in the Life Rachel, the project manager of a large information systems project, arrives at her office early to get caught up with work before her co- workers and project team arrive. However, as she enters the office she meets Neil, one of her fellow project managers, who also wants to get an early start on the day. Neil has just completed a project overseas. They spend 10 minutes socializing and catching up on personal...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT