Question

Compute the IRR static for Project E. The appropriate cost of capital is 9 percent. (Do...

Compute the IRR static for Project E. The appropriate cost of capital is 9 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.)

Time: 0 1 2 3 4 5
Cash Flow: -$1,800 $670 $720 $680 $460 $260

IRR _____________ %

Should the project be accepted or rejected?

Homework Answers

Answer #1

The IRR is the rate at which NPV is zero.

Lets compute NPV at 19% as shown below:

= - $ 1,800 + $ 670 / 1.19 + $ 720 / 1.192 + $ 680 / 1.193 + $ 460 / 1.194 + $ 260 / 1.195

= $ 13.3270954 Approximately

Lets compute NPV at 20% as shown below:

= - $ 1,800 + $ 670 / 1.20 + $ 720 / 1.202 + $ 680 / 1.203 + $ 460 / 1.204 + $ 260 / 1.205

= - $ 21.82355967 Approximately

It means that the IRR lies between 19% and 20% and is computed as follows:

= Lower rate + [ Lower rate NPV / ( Lower rate NPV - Higher rate NPV ) ] x ( Higher rate - Lower rate)

= 19 + [ $ 13.3270954 / ( $ 13.3270954 - ( - $ 21.82355967) ] x ( 20 - 19)

= 19 + [ $ 13.3270954 / $ 35.15065507 ] x 1

= 19 + 0.38

= 19.38% Approximately

Since the IRR is greater than the cost of capital, hence the project shall be accepted.

Feel free to ask in case of any query relating to this question

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do...
Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.)         Project E   Time: 0 1 2 3 4 5   Cash flow –$2,700 $830 $840 $760 $540 $340 IRR % ____________ Should the project be accepted or rejected? _________
Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do...
Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Time 0 1 2 3 4 5 Cash flow -$2800 $870 $870 $780 $560 $360 IRR ___ %
Problem 13-9 IRR (LG13-4) Compute the IRR static for Project E. The appropriate cost of capital...
Problem 13-9 IRR (LG13-4) Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: 0 1 2 3 4 5 Cash flow –$1,600 $590 $660 $640 $420 $220
Compute the IRR statistic for Project F. The appropriate cost of capital is 11 percent. (Do...
Compute the IRR statistic for Project F. The appropriate cost of capital is 11 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project F Time: 0 1 2 3 4 Cash flow: −$11,600 $4,150 $4,980 $2,320 $2,950 Should the project be accepted or rejected? accepted rejected
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent....
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: 0 1 2 3 4 5 Cash flow: –$2,300 $670 $2,280 –$680 $620 –$260
Compute the MIRR statistic for Project J if the appropriate cost of capital is 9 percent....
Compute the MIRR statistic for Project J if the appropriate cost of capital is 9 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project J Time: 0 1 2 3 4 5 Cash flow –$2,000 $650 $1,980 –$620 $600 –$200 MIRR % Should the project be accepted or rejected? Accepted Rejected
Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project M Time: 0 1 2 3 4 5 Cash flow: –$3,100 $710 $840 $880 $960 $460 Should the project be rejected or accepted?
Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project M Time: 0 1 2 3 4 5 Cash flow –$2,200 $590 $720 $760 $840 $340 NPV $ Should the project be accepted or rejected?
Compute the PI statistic for Project Q if the appropriate cost of capital is 13 percent....
Compute the PI statistic for Project Q if the appropriate cost of capital is 13 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Q Time: 0 1 2 3 4 Cash flow: −$11,800 $3,750 $4,580 $1,920 $2,550 Should the project be accepted or rejected? rejected accepted
Compute the PI statistic for Project Q if the appropriate cost of capital is 11 percent....
Compute the PI statistic for Project Q if the appropriate cost of capital is 11 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.)      Project Q   Time: 0 1 2 3 4   Cash flow –$12,300 $4,000 $4,830 $2,170 $2,800      PI       Should the project be accepted or rejected? Accepted Rejected
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT