Question

You are considering the following two mutually exclusive projects. The crossover rate between these two projects...

You are considering the following two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is greater than the crossover rate.

Year Project A Project B
0 −$27,000 −$27,000
1 10,000 18,100
2 10,000 8,000
3 18,000 10,120

Multiple Choice

a.) 18.64%; A

b.) 11.75%; B

c.) 11.75%; A

d.) 17.19%; B

e.) 17.19%; A

Homework Answers

Answer #1

Crossover rate is the internal rate of return in difference in cash flows of projects.

first calculate difference in cash flow then find IRR of that difference.

so crossover rate is 11.75%

Project B has higher cashflow early and it will have the greater NPV at higher interest rates.

The option b) is correct that is 11.75%;B

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
You are considering the following two mutually exclusive projects. The crossover rate between these two projects...
You are considering the following two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is greater than the crossover rate. Year Project A Project B 0 −$21,000 −$21,000 1 7,000 15,040 2 7,000 5,000 3 15,000 7,060 Multiple Choice 12.59%; B 15.61%; A 15.61%; B 12.59%; A 16.70%; A
You are considering the following two mutually exclusive projects. The crossover rate between these two projects...
You are considering the following two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is greater than the crossover rate. Year Project A Project B 0 −$40,000 −$40,000 1 21,500 13,730 2 13,500 11,500 3 13,500 25,700
You are considering the following two mutually exclusive projects. The crossover rate between these two projects...
You are considering the following two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is greater than the crossover rate. Year Project A Project B 0 −$21,000 −$21,000 1 7,000 15,040 2 7,000 5,000 3 15,000 7,060 16.70%; A 12.59%; B 12.59%; A 15.61%; B 15.61%; A
Dominic Walls, the infamous investor, is considering the following two mutually exclusive projects. The crossover rate...
Dominic Walls, the infamous investor, is considering the following two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is greater than the crossover rate. Year Project A Project B 0 −$42,000 −$42,000 1 21,500 13,750 2 13,500 11,500 3 13,500 25,900 rev: 05_02_2019_QC_CS-167236, 09_25_2019_QC_CS-182411, 09_27_2019_QC_CS-182208 Multiple Choice 8.29%; B 9.35%; B 14.24%; A 14.24%; B 8.29%; A
You are considering the following two mutually exclusive projects. What is the crossover point? Year Cash...
You are considering the following two mutually exclusive projects. What is the crossover point? Year Cash Flow A Cash Flow B 0 -$50,000.00 -$51,000.00 1 $0.00 $12,000.00 2 $33,000.00 $29,000.00 3 $40,000.00 $27,000.00 A) 29.72 percent B) 30.01 percent C) 25.76 percent D) 30.53 percent E) 32.08 percent Steele, Inc., is considering an investment with an initial cost of $155,000 that would be depreciated straight-line to a zero book value over the life of the project. The cash inflows generated...
You are considering the following two mutually exclusive projects. The required rate of return is 12%...
You are considering the following two mutually exclusive projects. The required rate of return is 12% for project A and 11% for project B. Which project should you accept and why? Year Project A Project B 0           -$68,000   -$75,000 1                     28,000 15,000 2                     20,000   20,000 3                     20,000 20,000 4                     10,000 30,000
Anderson Associates is considering two mutually exclusive projects that have the following cash flows: Project A...
Anderson Associates is considering two mutually exclusive projects that have the following cash flows: Project A Project B Year Cash Flow Cash Flow 0 -$10,000 -$8,000 1 2,000 7,000 2 2,000 3,000 3 6,000 1,000 4 8,000 3,000 At what cost of capital do the two projects have the same net present value? (That is, what is the crossover rate?) Enter your answer rounded to two decimal places. Do not enter % in the answer box. For example, if your...
You are considering the following two mutually exclusive projects. The required return on each project is...
You are considering the following two mutually exclusive projects. The required return on each project is 16 percent. Which project should you accept and what is the best reason for that decision? Year Project A Project B 0 -$10,000 -$20,000 1 $8,000 $16,000 2 $4,000 $9,000 3 $3,000 $5,000 4 $9,000 $7,000 A. Project A; because it pays back faster B. Project A; because it has the higher internal rate of return C. Project B; because it has the higher...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as follows. The required rate of return on projects of both of their risk class is 8 percent, and the maximum allowable payback and discounted payback statistic for the projects are two and three years, respectively. Time 0 1 2 3 Project A Cashflow -20,000 10,000 30,000 1,000 Project B Cashflow -30,000 10,000 20,000 50,000 Calculate the NPV and use the NPV decision rule to...
you are considering the following two mutually exclusive projects. the require return in each project is...
you are considering the following two mutually exclusive projects. the require return in each project is 12 percent. which project you should accept and what the best reason for the decision? year project A project B 0 -$10,000 -$ 20,000 1 3,000 5,000 2 8,000 7,000 3 4,000 12,000 4 $ 2,000 $ 10,000 A.project A because it pays back faster B. project A because it has the higher profitability index C.project B because it has the higher profitability index...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT