Information from question
Quantity per order = 2500 tiers
Annual demand= 2,50,000
No. of orders per year = 2,50,000/2500 =100 orders
Cost per order = $ 3200.
Price per tier = $ 2.5.
Handling cost = $2.5*4%= $0.1
Particulars | Calculation | Amount($) |
Tier cost | 2,50,000*$2.5 | 6,25,000 |
ordering cost | 100*$3,000 | 3,00,000 |
Carrying cost | 2,50,000*$0.1 | 25,000 |
Total cost | 9,50,000 |