Question

In mutually exclusive projects, project that is selected for comparison with others must have a. Internal...

In mutually exclusive projects, project that is selected for comparison with others must have

a. Internal rate of return greater than zero

b. Positive net present value

c. Zero net present value

d. Highest net present value

e. Shortest discounted pay back

Homework Answers

Answer #1

Option "E" is correct,

As IRR greater 0, doesn't tell if it is less than or greater than the other project.

Positive NPV is just a criterion for the project being selected, it doesn't tell us which is better, as both projects could have positive NPV.

0 NPV is not a selection criterion.

Highest NPV can also mean that all projects have negative NPV.

Shortest discounted pay back is the only fitting response as it tell us the selected project recovers its cost fastest and only takes into account the time value of money.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Which of the following statements is correct: A. projects with unconventional cash flows have multiple internal...
Which of the following statements is correct: A. projects with unconventional cash flows have multiple internal rates of return B. if 2 projects are mutually exclusive, you should select the project with the shortest payback period C. If the IRR exceeds the required return, the profitability index will be less than 1.0 D. the Profitability index will be greater than 1.0 when the net present value is negative E. when the internal rate of return is greater than the required...
Consider the following two mutually exclusive projects: Year Project A Project B 0 -180,000 -18,000 1...
Consider the following two mutually exclusive projects: Year Project A Project B 0 -180,000 -18,000 1 60,000 15,000 2 100,000 15,000 3 150,000 12,000 Calculate the internal rate of return, and net present value. Assume a discount rate of 15%. Which project should be selected?
You are considering the following two mutually exclusive projects. The required return on each project is...
You are considering the following two mutually exclusive projects. The required return on each project is 16 percent. Which project should you accept and what is the best reason for that decision? Year Project A Project B 0 -$10,000 -$20,000 1 $8,000 $16,000 2 $4,000 $9,000 3 $3,000 $5,000 4 $9,000 $7,000 A. Project A; because it pays back faster B. Project A; because it has the higher internal rate of return C. Project B; because it has the higher...
20) You are considering the following two mutually exclusive projects. The required return on each project...
20) You are considering the following two mutually exclusive projects. The required return on each project is 12 percent. Which project should you accept and what is the best reason for that decision? Cash Flow Cash Flow Year A B         0 1 2 3 -$32,000.00 $11,500.00 $15,900.00 $13,200.00 -$26,000.00 $23,500.00 $5,800.00 $4,900.00             A) Project A, because it has the higher net present value B) Project A, because it pays back faster C) Project B, because it has the...
When mutually exclusive projects have different lives, a company should select the project with the ____...
When mutually exclusive projects have different lives, a company should select the project with the ____ Highest IRR Longest life Lowest equivalent annual cost Highest NPV discounted at the cost of capital
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Project A Project B Project C Project D Project E Project F Project G NPV= $4,711 ($711) ($657) $334 $9,842 $7,360 ($3,224) IRR= 44.51% 5.47% 8.06% 12.98% 22.56% 17.19% 5.47% MIRR= 25.23% 7.50% 8.97% 11.57% 16.26% 13.70% 7.50% PI= 2.178 0.822 0.945 1.028 1.394 1.294 0.871 The discounting rate (r)...
Project Brady and Project Grey are two mutually exclusive projects with equal risk that are competing...
Project Brady and Project Grey are two mutually exclusive projects with equal risk that are competing to use the same finite resource of limited-edition hotstoppers, which are reusable plastic sticks designed to stop hot coffee spilling from your takeaway coffee cup. Both projects commence with an initial up-front cash inflow followed in future years by a series of annual cash outflows. Both projects have positive internal rates of return (IRR) and both projects share the same positive net present value...
Project A has a net present value of $1,500, a payback period of 2 years, and...
Project A has a net present value of $1,500, a payback period of 2 years, and an internal rate of return of 12%.  Project B has a net present value of $1,800, a payback period of 4 years, and an internal rate of return of 10%.  Project C has a netpresent value of $1,750, a payback period of 3 years, and an internal rate of return of 11%.  If the projects are mutually exclusive, which project should be undertaken? A. Project A because...
11) Your company is choosing between two MUTUALLY EXCLUSIVE projects that have a required rate of...
11) Your company is choosing between two MUTUALLY EXCLUSIVE projects that have a required rate of return of 8.25%. You have gathered the following data. Which of the project(s) should be accepted? IRR NPV Project A 6.40% $ 22.6 million Project B 8.50% $ 16.1 million A) Accept neither project, as both have a required return that is above the IRR. B) Accept project B with the higher IRR. C) Accept project A with the higher NPV. D) Accept both...
6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen....
6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen. The internal rate of return (IRR) and the net present value (NPV) methods will not always choose the same project. If the crossover rate on the NPV profile is below the horizontal axis, the methods will agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. Year Project Y Project Z 0 –$1,500 –$1,500 1...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT