Question

Cowboy Corp. is about to expand its operations and they have several projects with various cash...

Cowboy Corp. is about to expand its operations and they have several projects with various cash flows available in Excel upload file. Each project has an 8-year life and the firm has a cost of capital at 8%. The firm has $15,000 for the expansion and will invest in multiple projects with that capital constraint.

1. Calculate NPV for each project

2. Find the project combination that maximizes total NPV for Cowboy Corp. and calculate total capital spending

3. Find the optimum combination under following constraints; Project A and C can only be invested together and at least one out of Project E, F or G must be invested.

Cost of capital 8%
YEAR 0 1 2 3 4 5 6 7 8
Project A -5000 1000 1250 1000 900 850 750 700 700
Project B -3000 400 600 800 600 600 600 600 600
Project C -4500 1200 1500 1200 1200 500 500 300 300
Project D -2000 450 450 450 400 400 300 300 200
Project E -7500 1350 1350 1350 1350 1350 1350 1350 1350
Project F -8000 2000 2000 2000 1500 1500 1500 500 100
Project G -6500 1400 1400 1200 1200 900 900 900 900

Homework Answers

Answer #1

Solution.>

Since it is a 8-year project, the values of year 7 and year 8 is missing in the question. So i have solved it till the year 6. The answer would be different if we include the year 7 and 8, but the methodology will remain the same. I have solved this question in Excel. The formula used are written along with the values. If you still have any doubt, kindly ask in the comment section.

Note: Give it a thumbs up if it helps! Thanks in advance!

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Quantity Private Value Private Cost Social Cost 100 $2000 $500 $800 200 $1800 $600 $900 300...
Quantity Private Value Private Cost Social Cost 100 $2000 $500 $800 200 $1800 $600 $900 300 $1600 $700 $1000 400 $1400 $800 $1100 500 $1200 $900 $1200 600 $1000 $1000 $1300 700 $800 $1100 $1400 800 $600 $1200 $1500 900 $400 $1300 $1600 How large would the per-unit tax on paper need to be, in order to induce the paper factory to produce the socially optimal level of paper? (Hint: Table shows value and costs per 100 units and questions...
You have the following investment options as laid out in the table below: Project Cash Flow...
You have the following investment options as laid out in the table below: Project Cash Flow Year A B C D E 0 -$1000 -$1200 -$2000 -$1600 -$1400 1 900 800 950 900 400 2 500 700 950 900 400 3 100 700 950 900 1200 4 50 300 950 900 400 If your MARR is 15%, which of these options should you select? Solve this problem by challenger-defender analysis.
Make an estimate of how long would it take for the tank to empty from 2500mL...
Make an estimate of how long would it take for the tank to empty from 2500mL to 2000mL. Is the amount of time longer than it takes to empty from 2000mL to 1500mL? Explain. Time(s) Volume (mL) 0 2000 4.3 1900 9.5 1800 13.7 1700 18.5 1600 23.2 1500 28.2 1400 34.7 1300 40.4 1200 46.7 1100 52.5 1000 58.7 900 65 800 73 700 82 600 91 500 101 400
Consider two projects with the following cash flows: Project S is a 4 year project with...
Consider two projects with the following cash flows: Project S is a 4 year project with initial (time 0) cash outflow of 3000 and time 1 through 4 cash inflows of 1500, 1200, 800 and 300 respectively. Project L is a 4 year project with initial (time 0) cash outflow of 3000 and time 1 through 4 cash inflows of 400, 900, 1300, and 1500 respectively. Assuming a 5% cost of capital, determine which project should be chosen if the...
Consider two projects with the following cash flows: Project S is a 4 year project with...
Consider two projects with the following cash flows: Project S is a 4 year project with initial (time 0) cash outflow of 3000 and time 1 through 4 cash inflows of 1500, 1200, 800 and 300 respectively. Project L is a 4 year project with initial (time 0) cash outflow of 3000 and time 1 through 4 cash inflows of 400, 900, 1300, and 1500 respectively. Assuming a 5% cost of capital, determine which project should be chosen if the...
Langton Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Langton Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO believes the IRR is the best selection criterion, while the CFO advocates the NPV. If the decision is made by choosing the project with the higher IRR rather than the one with the higher NPV, how much, if any, value will be forgone? In other words, what's the NPV of the chosen project versus...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as follows. The required rate of return on projects of both of their risk class is 10 percent, and the maximum allowable payback and discounted payback statistic for the projects are two and a half and three and a half years, respectively. Time 0 1 2 3 Project A Cash Flow ?1,000 300 400 700 Project B Cash Flow ?500 200 400 300 Use...
If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV)...
If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV) and internal rate of return (IRR) methods   agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. Year Project Y Project Z 0 –$1,500 –$1,500 1 $200 $900 2 $400 $600 3 $600 $300 4 $1,000 $200    If the weighted average cost of capital (WACC) for each project is 14%, do the NPV and...
Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been...
Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 8%. 0 1 2 3 4 Project A -920 700...
Moerdyk & Co. is considering Projects S and L, whose cash flows are shown below. These...
Moerdyk & Co. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under certain conditions choosing projects on the basis of the IRR will not cause any value to be lost because the one with the higher IRR will also have the higher NPV, i.e., no...