Question

On January 1, 20x7, Porter Inc. entered into a 3-year construction contract for $2547273. The actual...

On January 1, 20x7, Porter Inc. entered into a 3-year construction contract for $2547273. The actual and expected costs to complete the project as at each year-end are outlined in the table below.

Dec 31,

20x7

Dec 31,

20x8

Dec 31,

20x9

Costs incurred during the year

$615470

$598465

$600,000

Expected costs to complete

$1200218

$421321


How much revenue should Porter Inc. recognize in relation to this contract for the fiscal year 20x8?

Select one:

a. $1027514

b. $863458

c. $1890972

d. $1494876

Homework Answers

Answer #1

Option A

Solving as per degree of completion method-

Revenue for 2017=Cost incurred in 2017/(cost incurred in 2017+expected cost)* total contract revenue

=615470/(615470+1200218)*2547273=$863457.9

Revenue for 2018=(Cost incurred in 2018 + cost incurred in 2017)/(cost incurred in 2017+cost incurred in 2018+ expected cost)* total contract revenue-revenue booked in 2017

=(598465+615470)/(598465+615470+421321)*2547273-863457.9=$10,27,514.45=$ 1027514 (approx.)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,225,000. During 2021, costs of $2,090,000 were incurred, with estimated costs of $4,090,000 yet to be incurred. Billings of $2,608,000 were sent, and cash collected was $2,340,000. In 2022, costs incurred were $2,608,000 with remaining costs estimated to be $3,735,000. 2022 billings were $2,858,000, and $2,565,000 cash was collected. The project was completed in 2023 after additional costs of...
On January 1, Year 1, a contractor began work on a $3.2 million construction contract that...
On January 1, Year 1, a contractor began work on a $3.2 million construction contract that is expected to be completed in 3 years. The contractor concludes that it is appropriate to recognize revenue over time using the input method based on costs incurred (cost-to-cost method). At the inception date, the estimated cost of construction was $2.4 million. The following data relate to the actual and expected construction costs: Year 1 Year 2 Year 3 Cost incurred $720,000 $1,170,000 $1,110,000...
Ayayai Construction Company began operations on January 1, 2020. During the year, Ayayai Construction entered into...
Ayayai Construction Company began operations on January 1, 2020. During the year, Ayayai Construction entered into a contract with Lundquist Corp. to construct a manufacturing facility. At that time, Ayayai estimated that it would take 5 years to complete the facility at a total cost of $4,498,000. The total contract price for construction of the facility is $6,045,000. During the year, Ayayai incurred $1,184,040 in construction costs related to the construction project. The estimated cost to complete the contract is...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,210,000. During 2021, costs of $2,070,000 were incurred with estimated costs of $4,070,000 yet to be incurred. Billings of $2,570,000 were sent, and cash collected was $2,320,000. In 2022, costs incurred were $2,570,000 with remaining costs estimated to be $3,705,000. 2022 billings were $2,820,000 and $2,545,000 cash was collected. The project was completed in 2023 after additional costs of...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
On December 31 of the current year, State Construction Inc. signs a contract with the state...
On December 31 of the current year, State Construction Inc. signs a contract with the state of West Virginia Department of Transportation to manufacture a bridge over the New River. State Construction anticipates the construction will take three years. The company’s accountants provide the following contract details relating to the project: Contract price $624 million Estimated construction costs $480 million Estimated total profit $144 million During the three-year construction period, State Construction incurred costs as follows: Year 1 $48 million...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $330 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 90 $ 70 $ 45 Estimated costs to complete as of...
On December 31, 2019, Shawshank Construction Inc. signs a contract to manufacture a bridge which it...
On December 31, 2019, Shawshank Construction Inc. signs a contract to manufacture a bridge which it anticipates the construction will take three years. The company’s accountants provide the following contract details relating to the project: Contract price: $780 million Estimated construction costs: $600 million Estimated total profit: $180 million During the three-year construction period, Shawshank incurred costs as follows: 2020 $ 60 million 2021 $360 million 2022 $180 million Shawshank uses the cost-to-cost method to recognize revenue. Which of the...
In 2016 the ole construction corp began construction work under a 3 year contract. The contract...
In 2016 the ole construction corp began construction work under a 3 year contract. The contract price was $1,600,000. The Job was completed in 2018.                                                                                 2016                       2017                       2018 Costs incurred to date                                    400000                  935000                  1070000 Estimated costs to complete                       700000                  165000                  0 Billings to date                                                  300000                  900000                  1600000 Collections to date                                           270000                  810000                  1525000 Compute the amount of Gross Profit to be recognized for 2016 and 2017 assuming that ole is required to recognize revenue overtime. Compute the...
A construction company entered into a fixed-price contract to build an office building for $12 million....
A construction company entered into a fixed-price contract to build an office building for $12 million. Construction costs incurred during the first year were $4 million and estimated costs to complete at the end of the year were $6 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company’s income statement in the first year of the contract?