Question

Suppose the company is evaluating three projects with the following characteristics Each project has a cost...

Suppose the company is evaluating three projects with the following characteristics

Each project has a cost of $1mil. They will be financed using the target mix of long-term debt, preferred stock, and common equity. The cost of the common equity for each project should be based on the beta estimated for the project. All equity will come from reinvested earnings.

Beta rs rps rd(1-T) WACC Expected Return on Project
Project A 0.5 9.5% 11% 6.5% 8.23% 9%
Project B 1.0 12.5% 11% 6.5% 9.73% 10%
Project C 2.0 18.5% 11% 6.5% 12.73% 11%

Alanlyze the company's situation and explain why each project should be accepted or rejected.

Homework Answers

Answer #1

The question can be simply answered by looking at the WACC and Expected Return on Project.

If WACC< Expected Return: Accept the Project. Else Reject the Project.

Target Mix of debt, preferrence shares and common shares, beta, equity risk premium, all would be required to calculate the WACC. Since, WACC is already given, we do not have to go into those calculatations.

Project A: Accept (8.23<9)

Project B: Accept (9.73<10)

Project C: Reject (12.73>11)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Before-tax cost of debt (B-T rd) 8% Tax rate 34% Net Price of Preferred stock (after...
Before-tax cost of debt (B-T rd) 8% Tax rate 34% Net Price of Preferred stock (after deducting floatation costs) $32.00 Dividend per share of Preferred $3.40 Current price of Common stock stock $52.00 Dividend paid in the recent past for Common $2.50 Growth rate 6% Stock Beta 0.81 Market risk premium, (MRP) 6.2% Risk free rate ( rf ) 5.5% Flotation cost for common stock 5% Weight of debt in the target capital structure 40% Weight of preferred stock in...
Gradient Ltd is evaluating a new project that has the same risk as the overall firm....
Gradient Ltd is evaluating a new project that has the same risk as the overall firm. The cost is estimated at $75,000 and the expected cash flows are: Year Cash Flow 1 $18,000 2 $25,400 3 $35,000 4 $17,900 Currently the company has 50% debt and 50% equity. The cost of Spark’s debt is 9% and T-bills are yielding 5%. The market risk premium is 10% and Spark Ltd has a beta of 1.2. Tax rate is 30%. Should the...
FMA investment company is evaluating the following two projects. the cost of each project is 70,000...
FMA investment company is evaluating the following two projects. the cost of each project is 70,000 AED and the cost of capital is 9%. using the net present value method, which project should the company choose and why? the annuall cash flows are as follows: Year Project A Project B 1 20,000 14,000 2 12,000 23,000 3 12,000 26,000 4 30,000 30,000
2Assume that you are a new analyst hired to evaluate the capital budgeting projects of the...
2Assume that you are a new analyst hired to evaluate the capital budgeting projects of the company which is considering investing in two CPEC projects, “Expansion Zone North” and “Expansion Zone East”. The initial cost of each project is Rs. 10,000. Company discount all projects based on WACC. Further, all the projects are equally risky projects and the company uses only debt and common equity for financing these projects. It can borrow unlimited amounts at an interest rate of rd...
Assume CAPM holds and you have the following information regarding three investment opportunities: Project 1 has...
Assume CAPM holds and you have the following information regarding three investment opportunities: Project 1 has a project beta of 2.0 and you have estimated that the project’s NPV using a cost of capital of 20% equals zero. Project 2 has a project beta of 1.5 and its NPV using a cost of capital of 10% equals zero. Project 3 has a project beta of 1.0 and its NPV equals zero using a cost of capital of 6%. None of...
Assume CAPM holds and you have the following information regarding three investment opportunities: Project 1 has...
Assume CAPM holds and you have the following information regarding three investment opportunities: Project 1 has a project beta of 2.0 and you have estimated that the project’s NPV using a cost of capital of 20% equals zero. Project 2 has a project beta of 1.5 and its NPV using a cost of capital of 10% equals zero. Lastly, project 3 has a project beta of 1.0 and its NPV equals zero using a cost of capital of 6%. None...
Adamson Corporation is considering four average-risk projects with the following costs and rates of return: Project...
Adamson Corporation is considering four average-risk projects with the following costs and rates of return: Project Cost Expected Rate of Return 1 $2,000 16.00% 2 3,000 15.00    3 5,000 13.75    4 2,000 12.50    The company estimates that it can issue debt at a rate of rd = 11%, and its tax rate is 25%. It can issue preferred stock that pays a constant dividend of $4.00 per year at $47.00 per share. Also, its common stock currently sells for $33.00...
Adamson Corporation is considering four average-risk projects with the following costs and rates of return: Project...
Adamson Corporation is considering four average-risk projects with the following costs and rates of return: Project Cost Expected Rate of Return 1 $2,000 16.00% 2 3,000 15.00    3 5,000 13.75    4 2,000 12.50    The company estimates that it can issue debt at a rate of rd = 11%, and its tax rate is 25%. It can issue preferred stock that pays a constant dividend of $7.00 per year at $57.00 per share. Also, its common stock currently sells for $51.00...
Adamson Corporation is considering four average-risk projects with the following costs and rates of return: Project...
Adamson Corporation is considering four average-risk projects with the following costs and rates of return: Project Cost Expected Rate of Return 1 $2,000 16.00% 2 3,000 15.00 3 5,000 13.75 4 2,000 12.50 The company estimates that it can issue debt at a rate of rd = 11%, and its tax rate is 25%. It can issue preferred stock that pays a constant dividend of $4.00 per year at $51.00 per share. Also, its common stock currently sells for $36.00...
Two mutually exclusive projects have an initial cost of $60,000 each. Project A produces cash inflows...
Two mutually exclusive projects have an initial cost of $60,000 each. Project A produces cash inflows of $30,000, $37,000, and $20,000 for Years 1 through 3, respectively. Project B produces cash inflows of $80,000 in Year 2 only. The required rate of return is 10 percent for Project A and 11 percent for Project B. Which project(s) should be accepted and why? Project A, because it has the higher required rate of return. Project A, because it has the larger...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT